Findings-b9f951e32df5
“The PUC had a history of strategic ineptitude when it came to designing, bidding and constructing capital improvement projects.”
Scan 9Records › City reports › San Francisco Public Utilities Infrastructure Task Force (2002)
San Francisco Public Utilities Infrastructure Task Force : final report : June 1, 2000-June 17, 2002
A study by the San Francisco Public Utilities Infrastructure Task Force on the city's water and sewer utility, urging planning, contracting reform and a crisis plan. Scan on the Internet Archive ↗
Printed words Quoted from the page as read from the scan.
Findings-b9f951e32df5
“The PUC had a history of strategic ineptitude when it came to designing, bidding and constructing capital improvement projects.”
Scan 9Report recommendations-9b65cd1b7737
“Efforts should be made to reduce the inefficiencies and delays inherent in the PUC's contracting procedures.”
Scan 17Report recommendations-052c79b22cb8
“Appoint a new SFPU Commission with representatives from the major utility disciplines, plus a representative of the Peninsula customers.”
Scan 28Report recommendations-bc8b780b6028
“Develop a viable long-term strategic plan (LTSP) for the entire SFPUC system. Submit this comprehensive plan for public approval.”
Scan 28Findings-dd04c9d4025c
“The SFPUC did implement one significant TF recommendation -- making SFPUC public power available to private users.”
Scan 28Report recommendations-971d579ca9b3
“A debt of one billion dollars at the proposed interest payment of 6.5 percent over a 30- year period requires an increase in annual revenues of approximately $77,000,000.”
Scan 32Report recommendations-ba726b10ddb5
“Funding the complete CIP of $5.2 billion will mean an increase in revenue requirements through rate hikes of approximately $400,000,000.”
Scan 32
Scan 32Backgrounds-258f7517a6cf
“In 1998 voters of San Francisco passed Proposition H, which froze water and wastewater rates at the level in effect on January 1, 1998 until July 1, 2006.”
Scan 37Report recommendations-c6c251a432ca
“Create a 10 year, $250 million phase-in of solutions identified as part of SOFT.”
Scan 73Identifier ia:C101694962