Report recommendations-37775b46d73b
“The new facilities would have the capacity to accommodate up to about 800 additional students and faculty members for late afternoon and evening classes.”
Scan 12Records › City reports › City College of San Francisco, Mission Campus (1998)
City College of San Francisco, Mission Campus : draft environmental impact report
A draft environmental impact report on City College's plan to build a new Mission Campus on Bartlett Street, consolidating nearby facilities. Scan on the Internet Archive ↗
“[name withheld]” stands for a name the release withholds (Privacy).
Printed words Quoted from the page as read from the scan.
Report recommendations-37775b46d73b
“The new facilities would have the capacity to accommodate up to about 800 additional students and faculty members for late afternoon and evening classes.”
Scan 12Findings-6fa321bb2d39
“Intersections in the vicinity of the project site would continue to operate at acceptable levels of service (LOS D or better) with the addition of project traffic.”
Scan 12
Scan 12Findings-f57e254e6fc2
“Over 80% of the students use transit, walk or carpool to the Campus; about 18% drive to the Campus.”
Scan 12Report recommendations-49f33fd38645
“The parking garage would be about 44,000 sq. ft., the approximate size of the lot, and would require excavation to a depth of about 15 ft.”
Scan 25Report recommendations-b97c8cd7d8cd
“One level of underground parking would provide approximately 110 parking spaces.”
Scan 25Report recommendations-c55f4ecdb67c
“Under Design Scenario 2, the building would be a one-story multi-purpose room with a lower roofline than the adjacent Mission Market building.”
Scan 47Findings-3f00fb416680
“Archival research does not suggest that post-Gold Rush historical archaeological artifacts that may be found upon excavating for a subsurface parking garage would be of particular significance.”
Scan 58Findings-76cae36529b0
“Until the Gold Rush era, archival data supports the assessment that the proposed project site remained in a natural state.”
Scan 58Findings-7e83b3f2327d
“It is therefore unlikely that subsurface cultural resources from the Spanish, Mexican, or Early American eras (1776-1848) would be encountered.”
Scan 58Backgrounds-796f5e0ddc4e
“Mission Street is designated as a primary transit-oriented street, and is on the citywide pedestrian network.”
Scan 60
Scan 60Findings-b4a7d45474c8
“It is not designated in the Transportation Element of the San Francisco General Plan.”
Scan 60Findings-7fb89147d9c9
“Therefore, the project would not cause any significant traffic impacts on neighborhood streets and intersections.”
Scan 70Findings-eecfff5b2958
“As indicated, under both scenarios transit conditions would continue to operate within acceptable Muni and BART peak load thresholds.”
Scan 72Report recommendations-009ea61bfb8d
“Implementation of these mitigation measures is included in the project and would reduce related impacts to less-than-significant levels.”
Scan 82Report recommendations-262cfaa9a7c3
“Cover all trucks hauling soil, sand, and other loose materials or require all trucks to maintain at least two feet of freeboard.”
Scan 82
Scan 82Findings-1e64929dc3c9
“The [name withheld] building is an approximately 45-foot-tall (three-story) industrial building.”
Scan 92Backgrounds-8e0fa1a21510
“According to the San Francisco Zoning Maps, the alternative site is located within an M-1 (light industrial) Zoning District and is in a 50-X Height and Bulk District.”
Scan 92Backgrounds-aeeda5aa6775
“According to City Planning Code section 217 (g), post-secondary educational institutions are permitted within an M-1 zoning district.”
Scan 92
Scan 102Report recommendations-20352dfbb4c1
“The proposed project would demolish the two buildings on the project site, both of which house retail uses.”
Scan 102Findings-07f632727032
“The project site does not contain any state or locally classified mineral resource. Effects related to mineral resources will not be discussed in the EIR.”
Scan 135Report recommendations-c1c29d0877da
“The EIR will discuss the conversion of the existing site land use from neighborhood commercial uses to educational/institutional uses.”
Scan 135Findings-cd06540dc838
“No residents or housing would be displaced by the proposed project. Effects related to population and housing will not be discussed in the EIR.”
Scan 137Findings-d7601c9add37
“The proposed project includes no housing, and would not induce substantial population growth in the area around the project site.”
Scan 137Report recommendations-fa3cc7d397c0
“The project is consolidating current Mission Campus facilities from existing sites within two blocks of the proposed site.”
Scan 137Identifier ia:C101697900