Moscone Convention Center (1982)

Moscone Convention Center : first year anniversary

A staff review by the city's Chief Administrative Officer's office, one year after the Moscone Convention Center opened, on its use, costs and finances.The Board finally adopted a resolution putting Moscone Convention Center additions, financed by a Redevelopment Agency lease, to voters in July 1986. Scan on the Internet Archive ↗

Cost
$128.3 millionScan 4 ↗
Jobs
4,000 jobsScan 14 ↗
Owed
approximately $13.2 millionScan 12 ↗
Bookings
319 calendar days, 87%Scan 0 ↗
Findings
  • The Convention Center was booked 319 calendar days, or 87% of the time available, from December 1, 1981 through November 30, 1982.Scan 0 ↗
  • The expected deficit for the first twelve months was approximately $2.6 million (≈ $9.1 million in 2026 dollars).Scan 2 ↗
Report recommendations
  • The CAO's office aims to bring the Convention Center to break-even by 1985/86 at the latest.Scan 2 ↗
Board decisions
  • Proposed lease-financed parking facility of up to 800 stalls near Moscone Convention Center ordered submitted to voters.Record · Journal page ↗
  • 1982 · This reportCity and County of San Francisco, Office of Chief Administrative Officer
  • Board urged a study, funded from hotel tax revenue, of extra meeting space at the Moscone Convention Center; the resolution was adopted.Record · Journal page ↗
  • Controller's $125,000 (≈ $422,866 in 2026 dollars) appropriation adds a meeting room to the George R. Moscone Convention Center; finally passed.Record · Journal page ↗
  • Renne asked the Mayor and Chief Administrative Officer whether adding a floor to the Moscone Convention Center is desirable and feasible.Record · Journal page ↗
  • A resolution to put Moscone Convention Center additions, financed by a Redevelopment Agency lease, to voters was adopted.Record · Journal page ↗
13 quotes from the scan

Printed words Quoted from the page as read from the scan.

Findings-5d542939bbb7

“For the period December 1, 1981 through November 30, 1982, 319 calendar days were sold, or 87% of the time available.”

Scan 0

Report recommendations-86f210f04358

“The goal of my office is to bring the Convention Center to a breakeven by 1985/86 at the latest.”

Scan 2

Findings-c03a3e864cb8

“The rent we are asking is below that of most western cities. Only Las Vegas and Reno are lower than ours.”

Scan 2

Findings-4111a6f7a6b7

“The estimated final cost is $128.3 million, an increase of 6.4% over our initial estimate.”

Scan 4

Findings-085953056982

“The waterproofing contractor has undertaken to correct this, at his expense, and the problem appears to be resolved.”

Scan 8

Findings-2abcf5e8f2c3

“This has been rectified along with the addition of energy saving devices at a cost of $70,009.”

Scan 8

Backgrounds-5b72cf637999

“Because the people voted to build the Convention Center underground in an area having a great deal of water, water seepage will be present throughout the life of the facility.”

Scan 8

Findings-55b6d54b850f

“We provided offices for the caterer and an office for the visiting convention association executives (a sales tool) at a cost of $75,000.”

Scan 10

Findings-a6df4f8353f9

“Because our very attractive chairs were being stolen, we have built storage rooms at a cost of $50,000.”

Scan 10

Findings-9b7551bf11a0

“We have paid all of our construction bills promptly and in full, for items covered in the construction contracts.”

Scan 12

Findings-7fa46b3b33a7

“The only complaint, which comes from the larger users (9,000 delegates or more) is that the Convention Center does not have enough meeting rooms.”

Scan 14