Environmental impact report - San Francisco Airport expansion (1973)

Environmental impact report - San Francisco Airport expansion

A final environmental impact report by the Airports Commission on the proposed expansion of San Francisco International Airport, covering its construction projects and their effects.The Board approved the report, with the delay motion turned down, in December 1973. Scan on the Internet Archive ↗

Cost
$5,600,000 for Passenger Distribution Center workScan 157 ↗
Invested
over $200 million in the airportScan 36 ↗
Passengers
31 million annual passengers by 1985Scan 28 ↗
Parking
about 4,300 added spaces, 7,300 total carsScan 157 ↗
Report recommendations
  • The proposed expansion will take place within existing airport boundaries with no land acquisition or displacing of people programmed.Scan 116 ↗
  • The report proposes a five-level addition to the existing garage adding about 4,300 parking spaces, for a total of 7,300 cars.Scan 157 ↗
  • The report estimates that airport-related vehicles are expected to produce 38 tons per day of pollutants in 1985.Scan 67 ↗
Board decisions
  • $144,000 (≈ $1.1 million in 2026 dollars) for the Highland Avenue bridge and $1.35M (≈ $10.2 million in 2026 dollars) for airport expansionRecord · Journal page ↗
  • Money approved to alter Highland Avenue bridge and plan airport expansionRecord · Journal page ↗
  • 1973 · This reportCity and County of San Francisco, Airports Commission
  • Airport expansion report approved; delay motion turned downRecord · Journal page ↗
  • Airport expansion environmental report approved by six to fourRecord · Journal page ↗
  • Airport expansion environmental report approved by six to four.Record · Journal page ↗
  • Call for federal review of airport expansion; sent to committee.Record · Journal page ↗
  • Resolution urging the Airports Commission to seek $34 million (≈ $232.4 million in 2026 dollars) federal aid for San Francisco International Airport expansion was adopted.Record · Journal page ↗
3 more Board decisions after the report
  • Supervisors Molinari, Feinstein and Kopp asked that the Airport Commission approve no further expansion plans until a select committee reports back.Record · Journal page ↗
  • City urged airport to limit expansion to approved fundingRecord · Journal page ↗
  • Stricter cap on airport expansion voted downRecord · Journal page ↗
12 quotes from the scan

Printed words Quoted from the page as read from the scan.

Backgrounds-976ad97de142

“San Francisco International Airport began operations in 1927 witha 1, 700-ft graded dirt landing strip on 155 acres of leased land.”

Scan 36

Report recommendations-f9faa166c75c

“The expansion program involves a considerable number of projects.”

Scan 36

Backgrounds-436089d7ce0e

“Currently three measures for describing the noise environment in the vicinity of airports are in use within the State of California.”

Scan 42

Findings-2bed4cb0cd77

“Table 2-19 lists the expected changes in ''basic employment'' between 1965 when the airport had 8.7 million total annual passengers and 1985 with 31.0 million annual passengers.”

Scan 84

Findings-2cb33373fb64

“Table 2-19 shows that of the 24,139 total basic employee increase, 13,655 in the Air Transportation, Hotel, and Federal Government categories are due only to air passenger growth.”

Scan 84

Backgrounds-6dbe3f1584ed

“San Francisco International Airport is on the east side of the San Francisco peninsula, some 14 miles south of the city's central business district.”

Scan 97

Report recommendations-8e16a4b2959e

“The development will take place within existing airport boundaries. No land acquisition or displacing of people is programmed.”

Scan 116

Report recommendations-af7ab8810a75

“Provisions for Bay Area Rapid Transit (BART) are being incorporated in the construction plans.”

Scan 116

Findings-15a128667dc3

“Relocation of the air-traffic control remote transmitters off Plot 40 to a new location at the north end of Taxiway P.”

Scan 145

Findings-a429460c6b44

“Reconstruction of the apron around Boarding Area A, because of the new location and design of the structure, to provide adequate pavement and drainage.”

Scan 145

Findings-962c49102e0a

“May require some passenger inconvenience during construction. Will provide increased automobile capacity.”

Scan 157

Findings-b1aa04665c26

“Testimony from the Hollister area stated opposition to a regional airport in their community, because of the expansion it would bring to their rural area, severe air pollution potential, and earthquake hazards.”

Scan 172