Central freeway alternatives (1997)

Central freeway alternatives

A staff report by the county transportation authority comparing alternatives for replacing or retrofitting the Central Freeway, including costs, timelines and traffic effects.In May 2000 the Board passed a measure for the City to acquire the former Central Freeway land near Market Street. Scan on the Internet Archive ↗

Cost
approximately $67.6 millionScan 3 ↗
Funding gap
$17.5 millionScan 10 ↗
Build time
48 to 58 monthsScan 8 ↗
Federal funds
$45 million not appropriatedScan 6 ↗
Report recommendations
  • The report estimates Alternative 1B at about 67.6 million dollars, the most expensive of the four analyzed.Scan 3 ↗
Findings
  • The report finds that Alternative 1B has the lowest impacts to transit service and the lowest pedestrian and bicycle safety impacts.Scan 4 ↗
  • Total delivery estimates range from 48 to 58 months depending on the alternative.Scan 8 ↗
Board decisions
  • 1997 · This reportSan Francisco County Transportation Authority
  • Voters allowed rebuilding the Central Freeway north of Market StreetRecord · Journal page ↗
  • Supervisors urge the State to transfer the Central Freeway right-of-way between Turk and Market Streets to the City, sent to committee.Record · Journal page ↗
  • State urged to hand over Central Freeway land near Market StreetRecord · Journal page ↗
  • City to acquire the former Central Freeway land near Market StreetRecord · Journal page ↗
4 earlier Board decisions
  • Board adopted, as amended, a resolution opposing new above-ground Central Freeway ramps and seeking surface-level transportation improvements.Record · Journal page ↗
  • Supervisors ask state to wait for traffic study before Central Freeway work.Record · Journal page ↗
  • Traffic study accepted and Caltrans urged to delay Central Freeway retrofit or demolition until alternatives are studied.Record · Journal page ↗
  • Board adopted a resolution letting Parking and Traffic accept up to $400,000 (≈ $884,357 in 2026 dollars) in federal funds to study Central Freeway retrofit alternatives.Record · Journal page ↗
29 quotes from the scan

Printed words Quoted from the page as read from the scan.

Board decision citedPrinted words, misread in placess-146ed0b39234

“Following public hearings on the replacement of the freeway, the Board of Supervisors approved Resolution 541-92 in July 1992, which prohibited the construction of any new freeway ramps above ground north of Fell Street”

Scan 0

Backgrounds-31fb09d50a80

“The Central Freeway was built in 1959 as part of a larger freeway system planned for the City, but much of that network was never built.”

Scan 0

Findings-8d71964ca9fa

“The existing portion of the Central Freeway is not constructed to current seismic standards and requires either retrofit, reconstruction, or demolition.”

Scan 0

Findings-a3bc4a37edbd

“Caltrans closed the freeway between August and November 1996 and demolished the upper deck.”

Scan 0

Findings-4f53e02b934a

“Alternatives 3, 8, and 8A were dropped from consideration because of high cost and property acquisition requirements.”

Scan 2

Report recommendations-3538eb8bbe36

“At approximately $67.6 million, this is the most expensive alternative of the four analyzed.”

Scan 3

Report recommendations-a9d43af3ded9

“Developed by Caltrans, this alternative would retrofit and widen the existing lower deck of the Central Freeway, providing a 4-lane single deck structure from Mission Street to Oak and Fell Streets.”

Scan 3

Findings-672b84632477

“This alternative has the lowest impacts to transit service, and the lowest pedestrian and bicycle safety impacts.”

Scan 4

Report recommendations-7b96eb172e96

“This alternative would not require any additional right of way, it would cost $48.1 million and would require 45 months to complete.”

Scan 5

Report recommendations-9f0109eb2a7b

“The cost of this alternative is $44.9 million and it would require 48 months to complete.”

Scan 5

Findings-0b7e595c6322

“Caltrans had included the Central Freeway project in the proposed list of projects for the State Highway Operations and Protection Program (SHOPP).”

Scan 6

Findings-e29a763fa863

“Our analysis indicates that this alternative would result in an average level of service of between D and E in the key corridors in the study area.”

Scan 6

Findings-facd0bce7735

“The remaining $45 million earmarked for the Central Freeway were never appropriated, pending the selection of a locally preferred alternative.”

Scan 6

Findings-9049d881503d

“Total delivery estimates range from 48 to 58 months depending on the alternative.”

Scan 8

Backgrounds-9ea398ced9b3

“A precedent for this approach is the City’s management of the construction of the Embarcadero Roadway after the Embarcadero Freeway was demolished.”

Scan 8

Report recommendations-fe53f3fcc597

“This raises the question as to whether the City should consider locally managing the project, which would also likely result in some overall cost savings.”

Scan 8

Findings-02317e21bdc7

“Caltrans closes Fell/Oak Streets ramps for demolition of upper deck.”

Scan 12

Report recommendations-065c1989286a

“Retrofit alternative, known as 1B, would rebuild the existing structure including the Fell/Oak ramps.”

Scan 12

Report recommendations-1bac5680408c

“Alternative 8/9 calls for the freeway to touch down at Valencia with a new on ramp on Otis Street and an off ramp on South Van Ness.”

Scan 12

Board decision citeds-3d4d233f4092

“BOS adopts Resolution 869-95, urging Caltrans to advance Alternative 3(2) , Alternative 8, and the retrofit alternative() to the environmental review stage.”

Scan 12

Findings-54ced72a3868

“Caltrans provides interim seismic support on concrete portion from Mission Street to Fell Street.”

Scan 12

Findings-550b94b07034

“Caltrans publishes Environmental Assessment, including Alternatives 1A, 1B, 8B, 10, and a No-Project Alternative.”

Scan 12

Findings-6d10c364963e

“Association to Simplify Traffic and Abate Congestion (ASTAC) introduces Alternative 8/9(4) at Central Freeway public hearing.”

Scan 12

Report recommendations-b779fdf90489

“Alternative 8 calls for the freeway to touch down at Octavia and Market.”

Scan 12

Backgrounds-bb5f9abd7055

“State Senate passes SB 181, prohibiting Caltrans from repairing or replacing US 101 unless the City of San Francisco approves a selected alternative.”

Scan 12

Findings-bdebdb34da71

“Caltrans completes demolition of the upper deck of the Fell/Oak Streets ramps.”

Scan 12

Backgrounds-d17895bdad1d

“Central Freeway Citizens’ Advisory Task Force chooses Alternative 8(!) as the preferred alternative.”

Scan 12

Report recommendations-d97cc41cda87

“Alternative 3 calls for the freeway to cross above Market Street and touch down at Octavia and Haight.”

Scan 12

Board decision citeds-f10f28f43f9c

“BOS adopts Resolution 9-94, requesting the Mayor to urge Caltrans to delay the retrofit process of the Central Freeway until alternatives are studied.”

Scan 12