City report · staff report · 1995

Final status report on CAO projects/departments prior to my retirement (1995)

Final status report on CAO projects/departments prior to my retirement

A final status report by the City's Chief Administrative Officer reviewing city projects and departments before the officer's retirement, covering construction, bonds, budgets and recycling. Scan on the Internet Archive ↗

Operating budget
some $171 millionScan 14 ↗
Civic Center shortfall
about $50 millionScan 8 ↗
Unfunded retrofit
some $12 millionScan 8 ↗
Findings
  • The CAO estimates the shortfall for completing the Civic Center buildings seismic retrofit at about $50 million (≈ $110.5 million in 2026 dollars).Scan 8 ↗
  • The question of how to dispose of treated water now discharged into the Bay from the Southeast Treatment Plant remains unresolved.Scan 10 ↗
Report recommendations
  • The report recommends including these few buildings in the bond issue for the Civic Center seismic retrofit.Scan 8 ↗
14 quotes from the scan

Printed words Quoted from the page as read from the scan.

Findings-64556fc56410

“The Southern Section (Folsom-3rd Street) Roadway and Muni Metro Extension is complete.”

Scan 0

Findings-e0c1240a3c16

“Construction on both interiors and exteriors is proceeding satisfactorily.”

Scan 0

Findings-a60e56aa12a6

“The new Oceanside Plant went "on line" in late 1993 and is operating satisfactorily.”

Scan 2

Backgrounds-9265103e777c

“Both FHWA and Cal Trans have concurred in our Board of Supervisors approved approach to the TSS replacement.”

Scan 4

Findings-b811fd1d2706

“The City Hall construction bid was awarded in February 1995 to Huber, Hunt & Nichols, the low bidder.”

Scan 4

Report recommendations-984ede035c4a

“The project is fully designed and will go to bid in May 1995.”

Scan 6

Findings-b17403e1bf14

“Our current estimate of the shortfall, based on our experience in Civic Auditorium and anticipating some double shifting at the Opera House, is in the area of $50 million.”

Scan 8

Findings-dfa1e0a81100

“The bond issue to convert the 3rd and 4th floor of city Hall to office use and to otherwise bring the building up to code in those areas where no seismic work is being done was narrowly defeated in 1994.”

Scan 8

Findings-f7c7ad6f7f72

“The estimated cost to retrofit these facilities is some $12 million.”

Scan 8

Findings-177a8258c6c3

“The first increment of $35 million of bonds have been sold and we are responding to owners interested in using our loan program.”

Scan 10

Findings-4548ad87ca98

“A major unresolved issue in completing our adopted Water Pollution Control Master Plan is the question of how to dispose treated water which is now being discharged into the Bay from our Southeast Treatment Plant.”

Scan 10

Findings-a827fc6c5eda

“The Fund has been frozen for two years which meant that no cultural organization received an increase and no new organizations could be funded.”

Scan 12