- Payments for playground fences and Board of Public Works office rent are proposed, in the 1910 General Fund schedule. linked by the name only, not checked
- Passed for printing: $35,860.75 from school bond funds to contractors on several San Francisco schools. linked by the name only, not checked
- Payments approved for bleachers at the South of Market children's playground and grading of a Police Department lot. linked by the name only, not checked
- Passed for printing a resolution authorizing $38,968.00 in school construction payments to Grant Fee and Ahlbach & Mayer.
- First installment to Ahlbach & Mayer for plumbing at Newton J. Tharp Commercial High School proposed. linked by the name only, not checked
- Payments totaling $35,860.75 to five contractors for work on several San Francisco schools were authorized from bond funds. linked by the name only, not checked
- Payments totaling $7,413.33 for a South of Market playground and a Police Department lot were approved.
- McSheehy Bros. and Ahlbach & Mayer were granted extensions to finish school building contracts; passed for printing. linked by the name only, not checked
- McSheehy Bros. and Ahlbach & Mayer were each granted extra time to finish their school building contracts; advertising fees were waived. linked by the name only, not checked
- Proposed twenty-day extension for Ahlbach & Mayer to finish plumbing at Newton J. Tharp Commercial School. linked by the name only, not checked
- Ahlbach & Mayer was granted twenty more days to finish plumbing work on the Newton J. Tharp Commercial School Building. linked by the name only, not checked
- Payments totalling $38,968 approved for construction of the Newton J. Tharp Commercial School. linked by the name only, not checked
- Payments of $582 to Ahlbach & Mayer and $1,711 to John G. Sutton Co. for extra work at two schools. linked by the name only, not checked
- Payments totaling $2,293.00 approved for extra work at the Tharp Commercial School and Sheridan Primary School.
- Proposed resolution authorizes school construction payments for heating, plumbing and steel work at four San Francisco schools. linked by the name only, not checked
- Payments of $17,885.60 approved for heating, plumbing and steel work at four public school buildings. linked by the name only, not checked
- Payments totalling $9,763.75 from the School Construction Account for work on several city school buildings were passed for printing.
- Resolution authorizing $12,647.75 in payments to contractors for work on Denman and Harrison Primary Schools was passed for printing. linked by the name only, not checked
- Payments on school plumbing and heating contracts at four San Francisco schools authorized from the school construction account.
- Four contractors were paid $7,425 in total for plumbing and heating work at four city schools.
- Three contractors were paid a total of $12,647.75 for work on the Denman and Harrison Primary schools.
- Caldwell & Company paid $15,972.75 for building the Spring Valley School
- Six school construction payments to contractors were authorized from the 1908 bond fund, with the final vote on the next page. linked by the name only, not checked
- Oil tank permits granted to Mercantile Trust and many other owners linked by the name only, not checked
- Oil tank permits granted across the city, plus Acme Junk's boiler linked by the name only, not checked