about 110 Board decisions about Barber Asphalt Paving, in date order. Each links to its printed page.

  • L. Abrams to be paid for hauling voting machines
    7 Jan 1906passed first readingJournal 1906 ↗
  • Resolution 89 authorizes a street work payment; its outcome is not printed on this page.
    5 Jun 1906outcome not readJournal 1906 ↗
  • $7,000 to Barber Asphalt for paving Mission Street to the county line
    5 Jun 1906outcome not readJournal 1906 ↗
  • Barber Asphalt given 90 more days repaving Kearny Street linked by the name only, not checked
    25 Jul 1906passedJournal 1906 ↗
  • Barber Asphalt given 90 more days repaving Kearny Street linked by the name only, not checked
    30 Jul 1906outcome not readJournal 1906 ↗
  • The Board of Public Works recommended giving Barber Asphalt Paving Company 90 more days to finish repaving Van Ness Avenue; referred to committee. linked by the name only, not checked
    29 Oct 1906referredJournal 1906 ↗
  • Barber Asphalt paid for street repairs, and the Assessor's stationery
    13 Dec 1906outcome not readJournal 1906 ↗
  • A $4,123.08 General Fund payment to Thos. Norton & Sons, Barber Asphalt Paving Co. and Spring Valley Water Co. was passed for printing. linked by the name only, not checked
    17 Dec 1906passed first readingJournal 1906 ↗
  • Four thousand one hundred twenty-three dollars from the General Fund was approved to pay coal, street repair, sprinkling and lumber contractors. linked by the name only, not checked
    31 Dec 1906passedJournal 1906 ↗
  • Passed payment of $500 to Barber Asphalt Paving Company for pavement repairs on Eighth and Montgomery streets.
    14 Jan 1907passedJournal 1907, p. 14 ↗
  • Barber Asphalt and City Street Improvement paid $13,902.74 for street paving linked by the name only, not checked
    27 Jan 1907outcome not readJournal 1907, p. 762 ↗
  • Resolution authorizing paving payment to Barber Asphalt Paving Co. for Van Ness Avenue work was passed for printing. linked by the name only, not checked
    11 Feb 1907passed first readingJournal 1907, p. 74 ↗
  • Barber Asphalt paid $20,552.33 for street work on Van Ness Avenue linked by the name only, not checked
    18 Feb 1907outcome not readJournal 1907 ↗
  • Barber Asphalt Paving allowed an engine at Sixteenth and Carolina linked by the name only, not checked
    1 Apr 1907outcome not readJournal 1907, p. 160 ↗
  • Barber Asphalt given ninety more days to pave Bartlett Alley linked by the name only, not checked
    15 Apr 1907outcome not readJournal 1907, p. 187 ↗
  • Barber Asphalt Paving Company was granted ninety-day extensions to finish paving on Sixteenth, Kearny, Turk and Ellis streets. linked by the name only, not checked
    29 Apr 1907outcome not readJournal 1907, p. 205 ↗
  • The Barber Asphalt Paving Company was granted ninety more days to finish paving Bartlett alley. linked by the name only, not checked
    29 Apr 1907passedJournal 1907, p. 200 ↗
  • Barber Asphalt Paving Company given ninety more days to finish paving
    13 May 1907outcome not readJournal 1907, p. 219 ↗
  • Barber Asphalt Paving Company given ninety more days to finish paving linked by the name only, not checked
    20 May 1907outcome not readJournal 1907, p. 239 ↗
  • Action deferred on resolutions giving Barber Asphalt Paving Company ninety-day extensions to finish three street paving jobs.
    27 May 1907outcome not readJournal 1907, p. 247 ↗
  • Barber Asphalt Paving Company given ninety more days to finish paving
    3 Jun 1907outcome not readJournal 1907 ↗
  • $47,916.93 paid for paving Turk, Sixteenth and Larkin streets linked by the name only, not checked
    1 Jul 1907outcome not readJournal 1907, p. 302 ↗
  • $47,916.93 paid for paving Turk, Sixteenth and Larkin streets linked by the name only, not checked
    9 Jul 1907passedJournal 1907, p. 314 ↗
  • $24,353.41 paid to Barber Asphalt for repaving between Sixth and Ninth linked by the name only, not checked
    27 Aug 1907outcome not readJournal 1907, p. 481 ↗
  • Barber Asphalt Paving Company is to be paid $1,399.20 for repaving Bartlett Alley. linked by the name only, not checked
    16 Sep 1907outcome not readJournal 1907, p. 531 ↗
  • Barber Asphalt Paving paid $1,399.26 for repaving Bartlett Alley linked by the name only, not checked
    16 Sep 1907outcome not readJournal 1907, p. 554 ↗
  • Barber Asphalt Paving Company was granted ninety more days to finish paving Ellis street from Stockton to Larkin streets. linked by the name only, not checked
    16 Sep 1907passedJournal 1907, p. G04 ↗
  • Expenditure proposed for Barber Asphalt Paving Company to repave Mission Street between Sixth and Ninth streets; vote continues on next page. linked by the name only, not checked
    23 Sep 1907outcome not readJournal 1907, p. 522 ↗
  • Barber Asphalt given ninety more days to pave Ellis Street
    21 Oct 1907outcome not readJournal 1907, p. 613 ↗
  • Barber Asphalt paid for repairs on Potrero Avenue and Devisadero
    25 Nov 1907outcome not readJournal 1907, p. 696 ↗
  • Barber Asphalt paid $2,275.46 for repairs on Potrero and Devisadero
    9 Dec 1907outcome not readJournal 1907, p. 720 ↗
  • Recommended that Barber Asphalt Paving Company get ninety more days, from January 2, 1908, to finish Ellis Street work. linked by the name only, not checked
    16 Dec 1907outcome not readJournal 1907, p. 754 ↗
  • Flinn & Treacy paid $2,805.48 for the Stevenson Street sewers linked by the name only, not checked
    16 Dec 1907outcome not readJournal 1907, p. 755 ↗
  • Board approved street repair payments to asphalt paving companies for Howard, Folsom, California and Eighth streets.
    23 Dec 1907passedJournal 1907, p. 776 ↗
  • C. S. Harney paid $1,588.11 for repaving Grove Street linked by the name only, not checked
    13 Jan 1908outcome not readJournal 1908, p. 41 ↗
  • M. Greenberg's Sons paid $2,250 for seventy-five hydrant bodies linked by the name only, not checked
    20 Jan 1908passedJournal 1908, p. 52 ↗
  • City Street Improvement paid for paving Fillmore Street with asphalt linked by the name only, not checked
    3 Feb 1908outcome not readJournal 1908, p. 97 ↗
  • Payments approved for sewer supplies and street paving, including Fillmore Street and Golden Gate Avenue work by city contractors.
    10 Feb 1908passedJournal 1908, p. 110 ↗
  • Public Works asked to cancel the Barber Asphalt Company's Kearny street repaving contract; the request was referred to committees. linked by the name only, not checked
    24 Feb 1908referredJournal 1908, p. 149 ↗
  • Barber Asphalt paid $22,315.05 for repaving Ellis Street
    2 Mar 1908outcome not readJournal 1908, p. 175 ↗
  • Barber Asphalt paid $22,315.05 for repaving Ellis Street
    9 Mar 1908passedJournal 1908, p. 199 ↗
  • Barber Asphalt paid $5,240.47 for patching Market Street linked by the name only, not checked
    27 Apr 1908outcome not readJournal 1908, p. 331 ↗
  • Barber Asphalt Paving paid for repairs on Pacific and Scott streets linked by the name only, not checked
    1 Jun 1908outcome not readJournal 1908, p. 517 ↗
  • Resolution proposed paying Barber Asphalt Paving Co. $5240.47 for asphalt repairs on Market Street, passed for printing. linked by the name only, not checked
    8 Jun 1908passed first readingJournal 1908, p. 316 ↗
  • Barber Asphalt Paving paid for repairs on Pacific and Scott streets linked by the name only, not checked
    8 Jun 1908outcome not readJournal 1908, p. 542 ↗
  • Resolution to pay Barber Asphalt Paving Company $1336.62 for street repairs was passed for printing after being laid over. linked by the name only, not checked
    15 Jun 1908passed first readingJournal 1908, p. 572 ↗
  • Payment of $1,336.62 from the General Fund to Barber Asphalt Paving Company for street asphalt repairs was passed for printing.
    22 Jun 1908passed first readingJournal 1908, p. 594 ↗
  • Barber Asphalt paid $3,221.27 for curbs on Sutter Street linked by the name only, not checked
    29 Jun 1908outcome not readJournal 1908, p. 607 ↗
  • Barber Asphalt Paving Company was paid $1,336.62 from the General Fund for May 1908 asphalt street repairs. linked by the name only, not checked
    29 Jun 1908passedJournal 1908, p. 604 ↗
  • Barber Asphalt paid for repairs on Gough and Octavia streets linked by the name only, not checked
    6 Jul 1908outcome not readJournal 1908, p. 620 ↗
  • City Street Improvement paid $8,287.81 for repairs to city streets linked by the name only, not checked
    15 Jul 1908outcome not readJournal 1908, p. 644 ↗
  • Proposed payments to suppliers, including Hale Bros. Inc. for dry goods furnished the City.
    15 Jul 1908outcome not readJournal 1908, p. 636 ↗
  • Barber Asphalt paid $3,221.27 for curbs on Sutter Street linked by the name only, not checked
    15 Jul 1908outcome not readJournal 1908, p. 635 ↗
  • Barber Asphalt paid a second time for paving Sutter Street
    20 Jul 1908outcome not readJournal 1908, p. 663 ↗
  • Board of Public Works recommended giving Barber Asphalt Paving Co. sixty more days to finish paving Sutter street.
    27 Jul 1908referredJournal 1908, p. 686 ↗
  • Barber Asphalt given sixty more days to pave Sutter Street
    10 Aug 1908outcome not readJournal 1908, p. 731 ↗
  • $10,531.40 paid to Barber Asphalt for paving Sutter Street linked by the name only, not checked
    8 Sep 1908outcome not readJournal 1908, p. 759 ↗
  • Barber Asphalt given sixty more days to pave Sutter Street
    8 Sep 1908outcome not readJournal 1908, p. 756 ↗
  • Barber Asphalt paid $10,531.40 more for paving Sutter Street linked by the name only, not checked
    21 Sep 1908outcome not readJournal 1908, p. 805 ↗
  • Barber Asphalt paid $7,975.05 for August work on Sutter Street
    21 Sep 1908outcome not readJournal 1908, p. 810 ↗
  • Barber Asphalt paid $7,975.05 for August work on Sutter Street
    28 Sep 1908outcome not readJournal 1908, p. 849 ↗
  • Barber Asphalt given sixty more days on Sutter Street paving
    12 Oct 1908passedJournal 1908, p. 914 ↗
  • Spring Valley Water paid $10,000 for water in the fire hydrants
    12 Oct 1908outcome not readJournal 1908, p. 897 ↗
  • Barber Asphalt given sixty more days on Sutter Street paving linked by the name only, not checked
    19 Oct 1908outcome not readJournal 1908, p. 936 ↗
  • Barber Asphalt paid $8,679 more for paving Sutter Street linked by the name only, not checked
    19 Oct 1908outcome not readJournal 1908, p. 941 ↗
  • Barber Asphalt Paving Company paid $8,679 for paving Sutter Street linked by the name only, not checked
    26 Oct 1908outcome not readJournal 1908, p. 958 ↗
  • Proposed payments totalling $6,279.98 for street repairs and food deliveries to the Relief Home and City and County Hospital.
    26 Oct 1908passed first readingJournal 1908, p. 963 ↗
  • Barber Asphalt Paving paid $2,003.01 for repairs to Shotwell Street
    2 Nov 1908outcome not readJournal 1908, p. 985 ↗
  • Street improvement payments approved to C. S. Harney and Barber Asphalt Paving Co. for work on Fourth and Sutter streets. linked by the name only, not checked
    23 Nov 1908passedJournal 1908, p. 1033 ↗
  • Barber Asphalt Paving paid $1,448.22 more for paving Sutter Street
    21 Dec 1908outcome not readJournal 1908, p. 1114 ↗
  • Barber Asphalt Paving given sixty more days on Sutter Street linked by the name only, not checked
    21 Dec 1908outcome not readJournal 1908, p. 1112 ↗
  • Barber Asphalt Paving given sixty more days on Sutter Street
    28 Dec 1908outcome not readJournal 1908, p. 1101 ↗
  • $1448 to Barber Asphalt for paving Sutter Street linked by the name only, not checked
    4 Jan 1909outcome not readJournal 1909, p. 6 ↗
  • Barber Asphalt paid $2,074.62 for repairs on Duboce Avenue
    27 Jan 1909outcome not readJournal 1909, p. 112 ↗
  • Proposed final $18,912.95 payment to Barber Asphalt Paving Company for paving Sutter Street from Van Ness to Sansome. linked by the name only, not checked
    8 Mar 1909passed first readingJournal 1909, p. 231 ↗
  • Barber Asphalt paid $18,912.95, the last for paving Sutter Street linked by the name only, not checked
    11 Mar 1909outcome not readJournal 1909, p. 248 ↗
  • Barber Asphalt Paving Co. paid $2,724.24 for Market Street repairs
    10 Apr 1909outcome not readJournal 1909, p. 376 ↗
  • Barber Asphalt Paving Co. paid $2,724.24 for Market Street repairs
    26 Apr 1909outcome not readJournal 1909, p. 398 ↗
  • Resolution proposed to pay $17,877.38 in General Fund claims for March and April 1909 hospital supplies, asphalt and street repairs.
    26 Apr 1909outcome not readJournal 1909, p. 406 ↗
  • Lange & Bergstrom paid $2,400.75 for the Ashbury Street engine house
    3 May 1909outcome not readJournal 1909, p. 431 ↗
  • Money set aside for December repairs to Folsom and Battery Streets
    29 Nov 1909outcome not readJournal 1909, p. 1087 ↗
  • Spring Valley Water paid $1,666.66 for water in public buildings linked by the name only, not checked
    6 Dec 1909outcome not readJournal 1909, p. 1121 ↗
  • Money set aside for December repairs to Folsom and Battery Streets linked by the name only, not checked
    6 Dec 1909outcome not readJournal 1909, p. 1107 ↗
  • $6,726.50 paid for paving Twenty-fourth Avenue and repairing two bridges linked by the name only, not checked
    13 Dec 1909outcome not readJournal 1909, p. 1142 ↗
  • Board authorizes $8,375.02 in payments, including paving on Lincoln Way and office rents for September 1910. linked by the name only, not checked
    1 Sep 1910passedJournal 1910, p. 964 ↗
  • Resolution authorizes $15,343.00 in General Fund payments to contractors and suppliers for street repairs and paving. linked by the name only, not checked
    24 Oct 1910outcome not readJournal 1910, p. 1037 ↗
  • $7,951.28 to Barber Asphalt Paving Co. for paving Lincoln Way linked by the name only, not checked
    31 Oct 1910outcome not readJournal 1910, p. 1053 ↗
  • Full acceptance of Cortland Avenue roadway was laid over one week after property owners objected to defective paving.
    1911continuedJournal 1911 ↗
  • Board sends to print a resolution authorizing payments from city funds to many suppliers and contractors for hospitals, sewers, schools and streets.
    1912passed first readingJournal 1912, p. 284 ↗
  • Sewer contractors paid, including $24,160.05 to Federal Construction Co.
    8 Apr 1912outcome not readJournal 1912, p. 199 ↗
  • Board authorized payment of many city claims, including hospital supplies, sewer and street work, and Lowell High School construction.
    22 Apr 1912passedJournal 1912, p. 295 ↗
  • Resolution awarding maintenance and subsistence supply contracts to many firms, including Associated Oil Co. and Barber Asphalt Paving Co., was adopted. linked by the name only, not checked
    24 Jun 1912outcome not readJournal 1912, p. 547 ↗
  • Barber Asphalt Paving given sixty more days on Fifteenth Avenue linked by the name only, not checked
    12 Aug 1912outcome not readJournal 1912, p. 662 ↗
  • Barber Asphalt Paving given sixty more days on Fifteenth Avenue linked by the name only, not checked
    19 Aug 1912outcome not readJournal 1912, p. 681 ↗
  • $2,450 paid to Jos. Holle for police motorcycles
    4 Nov 1912passedJournal 1912, p. 993 ↗
  • Board authorizes payment of many city claims to suppliers, contractors and hospitals, including sewer, fire and hospital bills.
    1913outcome not readJournal 1913, p. 368 ↗
  • Barber Asphalt given forty-five more days at Plymouth Avenue linked by the name only, not checked
    6 Jan 1913outcome not readJournal 1913, p. 19 ↗
  • Gorrill Bros. paid $9,924.56 for the Fillmore Street sewer linked by the name only, not checked
    3 Mar 1913outcome not readJournal 1913, p. 393 ↗
  • Pacific Gas and Electric paid $2,277.01 for railway lighting and power linked by the name only, not checked
    10 Mar 1913passedJournal 1913, p. 226 ↗
  • Barber Asphalt Paving Company given 90 more days on Twenty-third Avenue
    7 Apr 1913passedJournal 1913, p. 238 ↗
  • Barber Asphalt Paving Company given ninety more days to finish paving linked by the name only, not checked
    29 Apr 1913outcome not readJournal 1913, p. 423 ↗
  • Barber Asphalt Paving Company was granted a ninety-day extension of time, as proposed in Resolution No. 10167.
    12 May 1913outcome not readJournal 1913, p. 471 ↗
  • Resolution proposed to authorize payment of many city claims to contractors and suppliers, outcome continues on next page.
    1 Jul 1913outcome not readJournal 1913, p. 696 ↗
  • Board authorized payment of many city claims from bond and general funds to contractors, suppliers, and charities.
    14 Jul 1913passedJournal 1913, p. 734 ↗
  • Barber Asphalt given ninety more days on San Jose Avenue
    11 Aug 1913passedJournal 1913, p. 802 ↗
  • Barber Asphalt Paving given ninety more days at Laidley Street linked by the name only, not checked
    24 Feb 1914passedJournal 1914, p. 201 ↗