An organisation in about 120 Board decisions, 1910–1913.
about 120Board decisions about it
1910–1913first and last decision
In short
- 13 Jun 1910A resolution authorizing an expenditure for construction at the Hall of Justice was taken up; its outcome appears on the next page.
- 1911Contractors granted extensions of time to finish plumbing and construction at San Francisco hospital, schools, jail and Hall of Justice. linked by the name only, not checked
- 22 Apr 1912Board authorized payment of many city claims, including hospital supplies, sewer and street work, and Lowell High School construction.
- 7 Apr 1913The Board granted Caldwell & Company sixty more days to finish Pumping Station No. 2 at Fort Mason.
Who appears together
Lines show who appears in the same decisions. It doesn't mean they made a deal.
People
- Thomas Jenningsproposed 7 · 1912–13
- John A. Kellyproposed 5 · 1910–11
- Charles A. Nelsonproposed 4 · 1910–11
Organisations
- Contra Costa Construction Companynamed in 17
- McSheehy Brothersnamed in 14
- Spring Valley Water Companynamed in 13
Places
- Drumm Stnamed in 8
- Geary Stnamed in 8
- Brannan Stnamed in 7
More from the records
Who was paid · 76 organisations
| Contra Costa Construction Company | 17 decisions |
| McSheehy Brothers | 12 decisions |
| Spring Valley Water Company | 13 decisions |
| John G. Sutton Company | 11 decisions |
| Southern Pacific Company | 8 decisions |
| Lange & Bergstrom | 9 decisions |
How many decisions pay each one; amounts are not shown until a person checks them.
Votes · 52 roll calls
yes 813no 12absent 1
52 printed roll calls; 49 were unanimous.
Decisions, by type
| resolution | about 100 |
| contract | 10 |
| claim | 4 |
| other | 1 |
Decisions, by outcome
| passed | 51 |
| passed first reading | 20 |
| referred | 6 |
39 decisions have no outcome read yet.
All 116 decisions · in date order
- Board proposed paying Caldwell & Co. $32,460 as the first installment on the Hall of Justice construction contract.
- A resolution authorizing an expenditure for construction at the Hall of Justice was taken up; its outcome appears on the next page.
- Progress payments totalling $84,390 to Caldwell & Co. for Hall of Justice construction were approved from bond funds.
- Payments to contractors for school building work, including J. J. Connolly and Hansbrough Bros. Co., were listed from the School Construction Account. linked by the name only, not checked
- Payment of $4,740 from the Hall of Justice bond fund to Caldwell & Co. for repairing steel forms damaged by inspectors. linked by the name only, not checked
- Three contractors were granted extensions of time to finish work at the Hall of Justice and Spring Valley Grammar School. linked by the name only, not checked
- Proposed payments to contractors for work and supplies at several San Francisco schools, including Spring Valley School.
- Payment of $4,740.80 to Caldwell & Co. for repairing damaged forms at the Hall of Justice was recommitted to the Finance Committee. linked by the name only, not checked
- Resolution to pay Caldwell & Co. for window frames and Hall of Justice construction work, with payment details continuing onto the next page.
- Progress payments to Caldwell & Co. for building the Hall of Justice were proposed, including $11,790 and $60,750. linked by the name only, not checked
- City paid Caldwell & Co. $33,381.75 for Hall of Justice construction, and Rudgear-Merle Co. for window frames, finally passed. linked by the name only, not checked
- Caldwell & Co. was paid $4,740 from the Public Building Fund to repair steel forms damaged by inspectors. linked by the name only, not checked
Pages that mention it
Printed pages of the decisions on this page.
Journal 1910
Journal 1910
Journal 1912
Journal 1913