All decisions
18 Board decisions about Commary Peterson, in date order. Each links to its printed page.
- $40,000 set aside for December street paving and repairs linked by the name only, not checked
- Caldwell & Co. proposed to receive $10,018.49 for the eighth payment on Pumping Station No. 2. linked by the name only, not checked
- Board authorizes a long list of payments to contractors and claimants for police, school, transit and street work. linked by the name only, not checked
- $1,100 more for test borings at the proposed Twin Peaks Tunnel
- F. Rolandi paid $11,044 for the Geary Street car barn linked by the name only, not checked
- City approved payment of claims for paving, police station work, utilities, supplies and Civic Center land, including $198,977 to G. G. Burnett Estate Co.
- Resolution authorizing 1913 payments from bond funds for sewers, a police station, street lighting and Civic Center land was passed for printing.
- Resolution authorizes payments to several contractors and claimants for library books, school work, water mains and a pumping station. linked by the name only, not checked
- Resolution proposes authorizing expenditures from named accounts to named claimants; the outcome continues on the next page.
- Proposed resolution authorizes Library Fund payment to Emporium for San Francisco Public Library books; outcome continues on next page.
- Bakewell & Brown paid $874.27 for models in stone
- The Emporium paid $904.90 for books for the Public Library linked by the name only, not checked
- Commary-Peterson paid $8,293 to finish the North End Police Station linked by the name only, not checked
- $12,000 set aside to restore surveys in the Excelsior and Mission
- Final passage of Resolution 10288 authorizing city payments to contractors, suppliers and claimants from bond and general funds.
- Contra Costa Construction paid $2,549.87 for sewer pipes on Fulton Street linked by the name only, not checked
- Carnahan & Mulford paid $8,520 for the Glen Park School linked by the name only, not checked
- Commary-Peterson paid $8,995 for building Engine House No. 24 linked by the name only, not checked