- A resolution proposed authorizing listed expenditures to named claimants; the outcome continues on the next page. linked by the name only, not checked
- Fifteen payments to contractors and suppliers for street, water, marble and building work were passed for printing. linked by the name only, not checked
- Mysell-Rollins paid $700 to engrave 2,000 Hetch Hetchy bonds
- Eleven city construction payments, totalling about $190,000, were proposed for passage to print for Good Roads, Muni and library works.
- Daniel L. Bienfield paid $1,927.88 for work on Corbett Avenue linked by the name only, not checked
- The Board authorized payments from city funds for construction, supplies, pensions and fire equipment to named claimants, passed for printing.
- R. C. Storrie paid $92,000 for the Twin Peaks tunnel linked by the name only, not checked
- Fifteen claims and payments totalling about $29,000 were authorized for passage to print, including settlements for retaining wall damage on Ord Street.
- $7,194.75 paid to Golden Gate Iron Works for Redding School steel linked by the name only, not checked
- Street levels changed on Franconia Street between Peralta and Wolfe
- $60,000 paid to McGilvray-Raymond for Public Library granite work linked by the name only, not checked
- The Board moved to authorize many city payments to contractors and suppliers, including Hetch Hetchy water, City Hall and hospital work.
- $75,620.25 paid to F. Rolandi for the Hetch Hetchy railroad linked by the name only, not checked