All decisions
48 Board decisions about Eureka Construction, in date order. Each links to its printed page.
- Eureka Construction given 90 more days on the Ocean and California Street sewers
- Board approved $4,705 from the General Fund to Eureka Construction Company for sewer construction work.
- Eureka Construction's $22,986.97 California Street sewer bill passed for printing linked by the name only, not checked
- Eureka Construction's $22,986.97 California Street sewer bill passed for printing linked by the name only, not checked
- $22,986 to Eureka Construction for the California Street sewer
- Board of Public Works recommended giving Eureka Construction Company 90 more days to finish its sewer contract on Seventh Avenue and nearby streets. linked by the name only, not checked
- Eureka Construction given 90 more days, material short after the disaster linked by the name only, not checked
- Eureka Construction given 90 more days, material short after the disaster
- Eureka Construction given 30 more days on the Seventh Avenue sewer linked by the name only, not checked
- Eureka Construction given 90 more days on the Onondaga and San Jose sewers
- Eureka Construction given 30 more days on the Seventh Avenue sewer
- Street levels set on Twentieth Avenue between K and S Streets linked by the name only, not checked
- $24,290 for sewer work on Howard and Haight Streets
- $24,296 for sewer work on Howard and Haight Streets linked by the name only, not checked
- Eureka Construction Company seeks a thirty-day extension to finish its street contract.
- Eureka Construction given thirty more days on the Ocean Avenue sewer linked by the name only, not checked
- Payment taken up for sewers in Ocean and San Jose Avenues
- Board passes Ordinance 1204 by a vote of sixteen
- Eureka Construction Co.'s blasting bond on Ashbury Street, between Sixteenth and Seventeenth, was recommended at $5,000.
- Eureka Construction given thirty more days on Frederick Street sidewalks linked by the name only, not checked
- Blanchard, Brown given ninety more days to grade Thirty-fifth Avenue linked by the name only, not checked
- Payment of $2,721.94 proposed to Eureka Construction Company for part of the Potrero intercepting sewer. linked by the name only, not checked
- Flinn & Treacy given sixty more days on Polk Street linked by the name only, not checked
- Eureka Construction Company was paid $9,799.37 as the first progress payment on the Potrero intercepting sewer. linked by the name only, not checked
- Eureka Construction Company asked permission to blast for the East Potrero sewer work; referred to committee.
- Eureka Construction Co. paid $11,000.87 for the East Potrero sewer linked by the name only, not checked
- Eureka Construction Company allowed to blast rock for the Potrero sewer
- Eureka Construction Company was granted permission to blast rock for the East Potrero sewer, limited to daytime hours.
- Eureka Construction Co. paid $11,000.87 for the East Potrero sewer linked by the name only, not checked
- Sewer construction payments of about $40,441 to contractors for several city street sewers were authorized from the Sewer Construction Account. linked by the name only, not checked
- Board is paying Healy-Tibbitts Construction Co. $8,067.04 first installment for Section 6 of the Division Street sewer.
- Proposed payment of $9,408.72 to Eureka Construction Co. for East Potrero intercepting sewer work, passed for printing. linked by the name only, not checked
- Board approved a $9,408.72 progress payment to Eureka Construction Co. for the southerly East Potrero intercepting sewer. linked by the name only, not checked
- $13,576.39 paid to Eureka Construction for the East Potrero sewer linked by the name only, not checked
- The city paid Eureka Construction Company $13,570.39 for work on the southerly East Potrero sewer. linked by the name only, not checked
- Board of Public Works recommends ninety more days for Eureka Construction Company to finish the East Potrero sewer. linked by the name only, not checked
- Eureka Construction Company was granted ninety more days to finish the southern part of the East Potrero interceptor sewer. linked by the name only, not checked
- Eureka Construction to be paid $11,785.90 for the East Potrero sewer
- Buena Vista Improvement to be paid $911.28 for six fire cisterns
- A resolution to pay $9,673.45 to contractors Heafey and Eureka for sewer construction was passed for printing. linked by the name only, not checked
- Supervisors approved $9,673.45 in progress payments to Wm. Heafey and Eureka Construction Co. for sewer construction work.
- Eureka Construction Company's blasting permit ends, the work finished linked by the name only, not checked
- Eureka Construction paid $10,070.80 for the East Potrero sewer linked by the name only, not checked
- Hansbrough Bros. and others paid $17,072.50 for work on schools linked by the name only, not checked
- Resolution introduced to pay Eureka Construction Co. $2,210.87 as a ninth sewer installment in East Potrero. linked by the name only, not checked
- Final payment of $3,723.01 approved to Eureka Construction Co. for sewers in the East Potrero District. linked by the name only, not checked
- City paid Eureka and Metropolis Construction for sewer work in East Potrero and the Lower Sunset District. linked by the name only, not checked
- Eureka Construction paid $2,249.87 for East Potrero sewers linked by the name only, not checked