All decisions
29 Board decisions about Hanrahan, in date order. Each links to its printed page.
- Hanrahan Company to build Alemany Boulevard from Sickles to Orizaba avenues
- Hanrahan Company to build Alemany Boulevard from Sickles to Orizaba avenues
- Hanrahan Company given ninety more days on Alemany Boulevard
- Hanrahan Company given ninety more days on Alemany Boulevard
- Hanrahan Company given ninety more days on Alemany Boulevard linked by the name only, not checked
- Hanrahan Company given ninety more days on Alemany Boulevard
- Hanrahan Co.'s first payment of $4,350 for improving Alemany Boulevard is listed for payment. linked by the name only, not checked
- Hanrahan Company was granted a ninety-day extension to finish its Alemany Boulevard street improvement work. linked by the name only, not checked
- MacDonald & Kahn paid $25,500 for the Bernal Cut work
- MacDonald & Kahn paid $25,500 for the Bernal Cut work
- Hanrahan Company granted ninety more days on Alemany Boulevard
- Payment of $9,150 to Hanrahan Co. for paving Alemany Boulevard between Sickels and Orizaba avenues.
- Third payment of $9,150 to Hanrahan Co. for improving Alemany Boulevard from Sickels to Orizaba is listed. linked by the name only, not checked
- Hanrahan Co. claim of $14,400.00 for improving Alemany Boulevard between Sickles and Orizaba avenues listed for payment.
- Hanrahan Co. was paid $14,400.00 for improving Alemany Boulevard from Sickles to Orizaba Avenues. linked by the name only, not checked
- Seventeen contracts letting Water Department land near Sunol, Colma, Niles Canyon and elsewhere were passed for printing.
- Resolution proposed to approve Board of Public Works contracts for use of San Francisco Water Department lands.
- A resolution on Finance Committee recommendation authorizes payments from named funds to named claimants; the list continues on the next page. linked by the name only, not checked
- Hanrahan Company was paid $7,319.77 as final payment for Alemany boulevard improvements from Sickles to Orizaba avenues. linked by the name only, not checked
- Hanrahan Company received its final payment of $7,319.77 for improving Alemany boulevard between Sickles and Orizaba avenues. linked by the name only, not checked
- Hanrahan Company to build the Van Ness Avenue extension for $36,893.80 linked by the name only, not checked
- $89,000 set aside to improve Section C of Alemany Boulevard
- Hanrahan Company to build the Van Ness Avenue extension for $36,893.80 linked by the name only, not checked
- A $4,050.00 first payment to Hanrahan Company for Alemany boulevard section C was listed on the Boulevard Bond Fund schedule.
- Claim of $4,050 to Hanrahan Company for first payment on Alemany boulevard section C, contract No. 28.
- F. Rynveld & Sons paid $2,690.30 for bulbs for the parks
- Map approved for resubdividing part of Geneva Terraces linked by the name only, not checked
- Resolution proposes a first 45-day time extension for Hanrahan Company's street contract, running from December 5, 1931.
- Hanrahan Company paid $486.60 for land to widen Nineteenth Avenue