33 Board decisions about Kittle Construction, in date order. Each links to its printed page.

  • Kittle Construction Company granted 100 extra days to finish the Mission Grammar School building contract. linked by the name only, not checked
  • An additional $8,000 was provided for the Auditor's office after the State raised city assessments by 10 per cent. linked by the name only, not checked
    1909outcome not readJournal 1909, p. 1001 ↗
  • Kittle Construction Co. was authorized a fourth progress payment of $1,980 for Mission Grammar School.
    1909outcome not readJournal 1909, p. 1001 ↗
  • Proposed first progress payment of $5,445 to Kittle Construction Co. for the Mission Grammar School building. linked by the name only, not checked
    11 Mar 1909outcome not readJournal 1909, p. 253 ↗
  • First progress payment of $5,445 approved to Kittle Construction Co. for the Mission Grammar School building. linked by the name only, not checked
    22 Mar 1909passedJournal 1909, p. 270 ↗
  • Kittle Construction Company was granted 100 more days to finish the Mission Grammar School building contract. linked by the name only, not checked
    1 Jun 1909passedJournal 1909, p. 531 ↗
  • Kittle Construction Company paid $25,000 for the Mission Grammar School
    24 Jun 1909outcome not readJournal 1909, p. 675 ↗
  • Kittle Construction Company paid $25,000 for the Mission Grammar School linked by the name only, not checked
    19 Jul 1909outcome not readJournal 1909, p. 711 ↗
  • Kittle Construction Co. granted ninety more days to finish the Mission Grammar School building. linked by the name only, not checked
    20 Sep 1909passedJournal 1909, p. 857 ↗
  • Kittle Construction Co. was granted ninety more days to finish building the Mission Grammar School.
    27 Sep 1909outcome not readJournal 1909, p. 869 ↗
  • Pays Kittle Construction Co. $858.00 for extra work at the Mission Grammar School building. linked by the name only, not checked
    4 Oct 1909passedJournal 1909, p. 907 ↗
  • Payments totaling $35,142.50 to three contractors for Mission Grammar, South End and Madison schools were passed for printing. linked by the name only, not checked
    11 Oct 1909passed first readingJournal 1909, p. 927 ↗
  • Kittle Construction paid $858 for extra work at Mission Grammar School linked by the name only, not checked
    11 Oct 1909outcome not readJournal 1909, p. 914 ↗
  • The city paid $35,142.50 to contractors for work on Mission Grammar, South End and Madison Primary schools. linked by the name only, not checked
    25 Oct 1909passedJournal 1909, p. 956 ↗
  • Kittle Construction Co. was paid $1,980 for a progress payment on the Mission Grammar School building. linked by the name only, not checked
    15 Nov 1909passedJournal 1909, p. 1019 ↗
  • Payments totaling $35,523.40 from school construction bond funds for work at several San Francisco schools passed for printing. linked by the name only, not checked
    27 Dec 1909passed first readingJournal 1910, p. 33 ↗
  • A sixth payment of $23,582 to Kittle Construction Company for Mission Grammar School was passed for printing.
    1910passed first readingJournal 1910, p. 110 ↗
  • Kittle Construction asks that a $12 advertising charge on its Mission Grammar School work be remitted; referred to committee. linked by the name only, not checked
  • Kittle Construction Company was granted thirty more days to finish general construction of the Mission Grammar School building. linked by the name only, not checked
  • Board of Public Works recommends giving Kittle Construction Company thirty more days to finish Mission Grammar School work; referred to committee. linked by the name only, not checked
    3 Jan 1910referredJournal 1910, p. 3 ↗
  • Board granted Kittle Construction Company thirty more days to finish the Mission Grammar School building. linked by the name only, not checked
    5 Jan 1910outcome not readJournal 1910, p. 41 ↗
  • Kittle Construction Company was granted thirty more days to finish general construction of the Mission Grammar School. linked by the name only, not checked
    24 Jan 1910outcome not readJournal 1910, p. 107 ↗
  • Sixth construction payment for Mission Grammar School approved to Kittle Construction Company under its contract.
    31 Jan 1910passedJournal 1910, p. 131 ↗
  • Board of Public Works recommended time extensions for three contractors on school and infirmary building contracts; adopted. linked by the name only, not checked
    14 Feb 1910passedJournal 1910, p. 186 ↗
  • Three contractors granted extensions of time to finish public building work, including school buildings and the Infirmary. linked by the name only, not checked
    21 Feb 1910passedJournal 1910, p. 211 ↗
  • The Kittle Construction Company was proposed for a thirty-day extension to finish the Mission Grammar School building.
    28 Mar 1910passed first readingJournal 1910, p. 327 ↗
  • Kittle Construction Company granted a thirty-day extension to finish the Mission Grammar School building contract. linked by the name only, not checked
    13 Apr 1910passedJournal 1910, p. 349 ↗
  • The Board of Public Works recommended giving Kittle Construction Company more time to finish the Mission Grammar School buildings, with its advertising fee waived. linked by the name only, not checked
    25 Apr 1910referredJournal 1910, p. 407 ↗
  • Proposed: thirty more days for Kittle Construction Company to finish the Mission Grammar School building, passed for printing by Nelson.
    2 May 1910outcome not readJournal 1910, p. 444 ↗
  • Extended time for Kittle Construction Company and F. H. Born to finish the Mission Grammar and McKinley school buildings.
    9 May 1910passedJournal 1910, p. 460 ↗
  • Payments totalling $19,076 for Denman, Madison and Mission grammar school construction were passed for printing.
    16 May 1910passed first readingJournal 1910, p. 487 ↗
  • Payments from the school construction account were authorized for work at the Denman Grammar and Madison Primary Schools. linked by the name only, not checked
    23 May 1910outcome not readJournal 1910, p. 503 ↗
  • Payment from the School Construction Account approved to Kittle Construction Co. for extra work at Mission Grammar School.
    13 Jun 1910passedJournal 1910, p. 588 ↗