In short
- 13 Jan 1930Finance Committee's resolution authorizes payment of claims to contractors and suppliers, including school construction work at Roosevelt, Park-Presidio and Geary Street schools.
Who appears together
Lines show who appears in the same decisions. It doesn't mean they made a deal.
Organisations
- Santa Cruz Portland Cement Companynamed in 5
- Scott Companynamed in 5
- Jacks & Irvinenamed in 5
Places
- Arguello Blvdnamed in 2
- Bay Shore Blvdnamed in 2
- Grove Stnamed in 2
More from the records
Who was paid · 41 organisations
| Santa Cruz Portland Cement Company | 5 decisions |
| Scott Company | 5 decisions |
| Jacks & Irvine | 5 decisions |
| Pacific Gas and Electric Company | 4 decisions |
| Ingersoll Rand Company of California | 4 decisions |
| Del Monte Meat Company | 3 decisions |
How many decisions pay each one; amounts are not shown until a person checks them.
Votes · 2 roll calls
yes 28no 0absent 4
2 printed roll calls; 2 were unanimous.
Decisions, by type
| resolution | 9 |
| claim | 3 |
All 12 decisions · in date order
- $480,675 set aside to build Roosevelt Junior High School at Arguello Boulevard
- $480,675 set aside to build Roosevelt Junior High School at Arguello Boulevard
- Finance Committee's resolution authorizes payment of claims to contractors and suppliers, including school construction work at Roosevelt, Park-Presidio and Geary Street schools.
- Larsen & Larsen is paid $5,256.31 for brick, tile and stone work at Roosevelt Junior High School. linked by the name only, not checked
- Resolution authorizes payment of many city claims from various funds, including Municipal Railway track material and an injury settlement.
- Resolution authorizes payments to suppliers and contractors for Hetch Hetchy water supply work, including the San Miguel Reservoir land.
- Larsen & Larsen is paid $17,908.88 for third brick work payment at Roosevelt Junior High School. linked by the name only, not checked
- Expense claims for school construction and supplies, including Park-Presidio and Roosevelt Junior High payments, are authorized for payment; the vote continues.
- Resolution authorizes payments to several claimants, including $4,037.96 to the California Academy of Sciences for Steinhart Aquarium.
- Larsen & Larsen was paid $14,155.61 as final payment for brickwork at Roosevelt Junior High School. linked by the name only, not checked
- Larsen & Larsen paid $16,100 for Health Center terra cotta work
- Larsen & Larsen paid $16,100 for Health Center terra cotta work