  • Board of Public Works recommended a 45-day extension for Robert Dalziel Jr. Co. to install heating at Bay View School Building; referred to committee.
    15 Jun 1908referredJournal 1908, p. 564 ↗
  • Robert Dalziel Jr. Co. was granted forty-five more days to finish heating and ventilation work at the Bay View School building.
    22 Jun 1908passedJournal 1908, p. 593 ↗
  • Robert Dalziel given forty-five more days on Bay View School heating
    29 Jun 1908passedJournal 1908, p. 603 ↗
  • Payment of $8,647 proposed to Robert Dalziel, Jr. Co. for a heating and ventilating system at Bay View School. linked by the name only, not checked
    28 Sep 1908outcome not readJournal 1908, p. 861 ↗
  • Board approved $8,047 paid to Robert Dalziel, Jr. Co. for a heating and ventilating system at Bay View School. linked by the name only, not checked
    12 Oct 1908passedJournal 1908, p. 898 ↗
  • Board authorized payment from the School Construction Account for extra work on a school building; outcome continues on next page. linked by the name only, not checked
    2 Aug 1909outcome not readJournal 1909, p. 756 ↗
  • Robert Dalziel Jr. Co. approved for $6,040 as first installment on heating work at Bryant Cosmopolitan School. linked by the name only, not checked
    15 Nov 1909passedJournal 1909, p. 1018 ↗
  • A first payment of $6,543 is proposed to Robert Dalziel Jr. Co. for heating and ventilating at Bryant Cosmopolitan School. linked by the name only, not checked
    15 Nov 1909outcome not readJournal 1909, p. 1012 ↗
  • Board approved $17,964.41 in payments to contractors for heating, steel, flooring and blackboards at several city schools. linked by the name only, not checked
  • Extra plumbing work at Mission Grammar School and extra work at Sutro Grammar School were authorized for payment from bond funds.
  • Final payments for plumbing at Mission Grammar School and yard work at Washington Grammar School were authorized from the school bond fund.
  • School building contractors would be paid $17,004.41 for work at several San Francisco schools, passed for printing.
    1910passed first readingJournal 1910, p. 700 ↗
  • Payments totalling $33,957.25 from the school construction account to four contractors for school buildings were passed for printing.
    21 Feb 1910passed first readingJournal 1910, p. 213 ↗
  • Board approved $33,957.25 in payments to four contractors for work on San Francisco school buildings. linked by the name only, not checked
    7 Mar 1910passedJournal 1910, p. 238 ↗
  • F. Leffler to be paid $6,249.15 for the Parkside sewer
    9 Mar 1910outcome not readJournal 1910, p. 262 ↗
  • Board approved $592.00 and $1,032.55 in extra school building work at Mission and Sutro Grammar Schools.
    15 Mar 1910passedJournal 1910, p. 274 ↗
  • School building construction payments from the 1908 bond issue proposed for contractors; the vote is on the next page.
    15 Mar 1910outcome not readJournal 1910, p. 271 ↗
  • Payments for heating, plastering and cornice work at Bryant Cosmopolitan and Frank McCoppin schools were passed for printing.
    11 Apr 1910passed first readingJournal 1910, p. 368 ↗
  • A payment for repairs to the boiler plant at the city Infirmary and Relief Home is proposed in a resolution.
    11 Apr 1910outcome not readJournal 1910, p. 364 ↗
  • Robert Dalziel Jr. Co. was authorized $3900 as a first installment for boiler plant repairs at the Relief Home Infirmary.
    13 Apr 1910outcome not readJournal 1910, p. 351 ↗
  • Four contractors were paid $14,811.85 for heating, ventilating and plastering work at three San Francisco schools.
    18 Apr 1910passedJournal 1910, p. 386 ↗
  • Payment of $2,625 approved to Robert Dalziel Jr. Co. for the first installment on Portola School's heating system. linked by the name only, not checked
    9 May 1910outcome not readJournal 1910, p. 465 ↗
  • Board proposed an expenditure of $2,625 for a heating and ventilating system at Portola School. linked by the name only, not checked
    16 May 1910outcome not readJournal 1910, p. 481 ↗
  • Resolution introduced to pay three contractors $17,072.50 for heating, floors and construction at San Francisco schools. linked by the name only, not checked
    20 Jun 1910passed first readingJournal 1910, p. 636 ↗
  • City approved $17,072.50 in bond-fund payments to three contractors for heating, floors and construction at three San Francisco schools. linked by the name only, not checked
    27 Jun 1910passedJournal 1910, p. 641 ↗
  • Payments for plastering and heating at several schools
    15 Jul 1910passedJournal 1910, p. 751 ↗
  • Four contractors were paid a total of $20,132.40 for plastering and heating work at San Francisco schools.
    1 Aug 1910passedJournal 1910, p. 766 ↗
  • Hospital construction payments totalling $6,103.50 to Robert Dalziel Jr. Co. and V. J. Belknap were passed for printing. linked by the name only, not checked
    8 Aug 1910passed first readingJournal 1910, p. 807 ↗
  • Board approved payments to Robert Dalziel Jr. Co. and V. J. Belknap for work at the Infirmary and San Francisco Hospital. linked by the name only, not checked
    15 Aug 1910passedJournal 1910, p. 821 ↗
  • Proposes $524.25 third progress payment to Robert Dalziel Jr. Co. for boiler and engine repairs at the Infirmary.
    19 Sep 1910outcome not readJournal 1910, p. 922 ↗
  • Robert Dalziel Jr. Co. was paid $524.25 as a progress payment for boiler and engine repairs at the Infirmary.
    26 Sep 1910passedJournal 1910, p. 942 ↗
  • School building payments totalling $59,595.25 to several contractors were passed for printing.
    17 Oct 1910passed first readingJournal 1910, p. 988 ↗
  • Payments approved for the Denman, McKinley and Adams school contracts linked by the name only, not checked
    24 Oct 1910outcome not readJournal 1910, p. 1020 ↗
  • Resolution authorizes $17,581.10 from school construction bonds to pay seven contractors for school building work. linked by the name only, not checked
    24 Oct 1910outcome not readJournal 1910, p. 1037 ↗
  • Seven payments totaling $17,581.10 for school building work at Hancock, Holly Park, McKinley and other schools approved.
    31 Oct 1910passedJournal 1910, p. 1053 ↗
  • City approves school construction payments totalling $14,020.02 to contractors for heating, floors, blackboards, steel, and plumbing at several schools. linked by the name only, not checked
    12 Dec 1910passedJournal 1910, p. 1185 ↗
  • Progress payments of $4,490.50 for boiler repairs at the Infirmary and millwork at San Francisco Hospital were approved. linked by the name only, not checked
  • Board of Public Works authorized fire-protection water system payments to Healy-Tibbitts and other contractors, including for the Twin Peaks Reservoir. linked by the name only, not checked
    1911outcome not readJournal 1911 ↗
  • Approved $9,819.76 in payments for auxiliary fire protection water system work at Twin Peaks and Townsend Street. linked by the name only, not checked
  • Payments totaling $4,490.50 for boiler repairs and millwork at the San Francisco Hospital were passed for printing. linked by the name only, not checked
    1911passed first readingJournal 1911 ↗
  • Payments totalling $2,193.01 to Robert Dalziel Jr. Co. and Enterprise Foundry Co. for the auxiliary fire water system.
    1911outcome not readJournal 1911 ↗
  • Board approved $2,193.01 from the Fire Protection Account for pumping station plumbing and cast-iron pipe fittings for the auxiliary water system.
    22 May 1911passedJournal 1911 ↗
  • Payments totalling $9,819.76 for Twin Peaks reservoir and Townsend Street pumping station work were passed for printing.
    14 Aug 1911passed first readingJournal 1911 ↗