Qipudata
San Francisco · v0.7.1

All decisions

17 Board decisions about Roebling Construction, in date order. Each links to its printed page.

  • Payments totalling $9,970.55 for roofing, plumbing and partitions at San Francisco Hospital were adopted.
  • A payment of $5,250 was proposed to Roebling Construction Co. for partitions at San Francisco Hospital.
    1911passed first readingJournal 1911 ↗
  • Payments totalling $9,970.55 proposed to three contractors for work at San Francisco Hospital.
    1911outcome not readJournal 1911 ↗
  • Resolution proposed to pay Roebling Construction Co. a first installment for hospital partitions, passed for printing. linked by the name only, not checked
    1911passed first readingJournal 1911 ↗
  • $12,150 first installment approved to Roebling Construction Co. for partitions at San Francisco Hospital. linked by the name only, not checked
    24 Jul 1911passedJournal 1911 ↗
  • Roebling Construction Co. was paid $5,250 for partitions and furring at San Francisco Hospital, approved by resolution. linked by the name only, not checked
    28 Aug 1911passedJournal 1911 ↗
  • Payments for San Francisco Hospital construction work, totalling $15,148.75, passed for printing.
    16 Oct 1911passed first readingJournal 1911 ↗
  • Payments totalling $15,148.75 to Lange & Bergstrom, Smith & Johnson and Roebling Construction Co. for San Francisco Hospital work were adopted.
    23 Oct 1911passedJournal 1911 ↗
  • Board passed for printing a resolution authorizing many city payments for schools, the hospital, sewers, fire protection and parks. linked by the name only, not checked
    1912passed first readingJournal 1912, p. 169 ↗
  • Resolution authorizes payments totalling $11,753.25 to contractors for work at San Francisco Hospital. linked by the name only, not checked
    2 Jan 1912outcome not readJournal 1912 ↗
  • Board authorized $11,753.25 from the hospital construction fund for contractors' progress payments at San Francisco Hospital.
    15 Jan 1912passedJournal 1912, p. 50 ↗
  • Resolution 9340 authorizes bond-funded construction payments for Polytechnic, Lincoln, Lowell and other schools, the Hall of Justice and San Francisco Hospital. linked by the name only, not checked
    11 Mar 1912outcome not readJournal 1912, p. 175 ↗
  • Contractors on the San Francisco Hospital and Polytechnic shop building were granted extensions of time to finish their work.
    12 Aug 1912passedJournal 1912, p. 660 ↗
  • Time extensions were recommended for contractors building San Francisco Hospital, including F. C. Roberts & Co. and Speck Manufacturing Co.
    19 Aug 1912outcome not readJournal 1912, p. 678 ↗
  • Expenditures authorized for Roebling Construction, Enterprise Foundry and Karl Fhrhart for hospital and sewer work, passed for printing.
    16 Dec 1912passed first readingJournal 1912, p. 1138 ↗
  • Authorizes payments of $1,153.75 to Roebling Construction Co. for San Francisco Hospital work and $1,163.16 to Enterprise Foundry Co. linked by the name only, not checked
    23 Dec 1912outcome not readJournal 1912 ↗
  • A resolution authorizing expenditures from named accounts to named claimants was taken up; its outcome continues on the next page.
    20 Jan 1913outcome not readJournal 1913, p. 51 ↗