- Board approved award of supply contracts to several food and goods firms, with Supervisor McSheehy recorded as opposing the bread contract. linked by the name only, not checked
- The Board adopted a resolution awarding foodstuff contracts to several San Francisco vendors, with the bread contract removed. linked by the name only, not checked
- Several food vendors were proposed for city foodstuff supply contracts covering January through March 1925; the vote is not yet printed.
- Supervisors proposed awarding city contracts for meat, fish and produce to suppliers including Del Monte Meat Co. and Miller & Lux, Inc. linked by the name only, not checked
- Payment of $756.20 to S. H. Tyler & Son for groceries for the Relief Home was approved. linked by the name only, not checked
- S. H. Tyler and Son was paid $620.85 for coffee and tea for San Francisco Hospital. linked by the name only, not checked
- S. H. Tyler & Son was paid $683.85 for coffee and tea supplied to the Relief Home.
- S. H. Tyler & Son listed for $891.10 payment for coffee and tea supplied to Relief Home. linked by the name only, not checked
- Supervisor Badaracco presented a resolution to award four-month food contracts for dressed meats to three meat suppliers.
- Pays S. H. Tyler & Son $891.10 for coffee and tea supplied to the Relief Home.
- Foodstuff supply contracts for July to October 1926 proposed, awarded to lowest bidders such as Del Monte Meat Co. and Morris & Co. linked by the name only, not checked
- Board awarded four-month foodstuffs supply contracts to about twenty vendors, with bond amounts from $100 to $1,000.
- Foodstuff supply contracts for March through June 1927 were awarded to many bidders, mostly to the lowest bidder.
- S. H. Tyler & Son was owed $795 for tea and coffee supplied to the Relief Home. linked by the name only, not checked
- Claim of S. H. Tyler & Son for $538.80 for coffee at Laguna Honda Home approved.
- Youdall Construction paid $42,313.50 for the tunnel under Buena Vista Park linked by the name only, not checked
- Resolution awards foodstuffs supply contracts for November 1927 to February 1928 to four bidders.
- Contracts for foodstuffs for March through June 1928 awarded to two dozen food suppliers and meat companies.
- Supplies Committee awards foodstuff contracts for July to October 1928 to nine bidders, including Armour & Co. and Morris & Co.
- Food supply contracts for March through June 1929 awarded to about two dozen food companies on lowest bids.
- Contracts for foodstuffs for July through October 1929 were awarded to suppliers including Swift & Company and Cudahy Packing Co.
- Foodstuffs contracts for November 1929 to February 1930 awarded to many suppliers; coffee bids rejected for open-market buying.
- S. H. Tyler & Son was paid $565.30 for coffee and supplies for Laguna Honda Home. linked by the name only, not checked
- Approved a $565.30 payment to S. H. Tyler & Son for coffee for Laguna Honda Home. linked by the name only, not checked
- Foodstuff contracts for November 1930 to February 1931 awarded to about a dozen lowest bidders.
- Foodstuff supply contracts for March through June 1931 were awarded to listed food firms on February 2, 1931 bids.