  • Funds were appropriated for High School of Commerce, Edison School, City Hall water, sewers and street paving, approved 12 to 5. linked by the name only, not checked
    30 Mar 1914passedJournal 1914, p. 368 ↗
  • A resolution setting aside funds for appropriation was passed for printing, with its details on the next page.
    30 Mar 1914outcome not readJournal 1914, p. 346 ↗
  • Authorization of street railway construction payments, including contract instalments, proposed and passed for printing.
    10 Aug 1914passed first readingJournal 1914, p. 893 ↗
  • Mahoney Bros. paid $33,906.82 for the Van Ness Avenue railway line linked by the name only, not checked
    17 Aug 1914passedJournal 1914, p. 908 ↗
  • $1,751.22 to buy land from William Ulfelder for San Bruno Avenue linked by the name only, not checked
    2 Nov 1914outcome not readJournal 1914, p. 1272 ↗
  • Board adopted appropriations for Polytechnic High School, Municipal Railway, San Francisco Hospital, the fire alarm station, and November repairs.
    16 Nov 1914passedJournal 1914, p. 1311 ↗
  • Proposed resolution authorizing bond-fund payments to contractors for hospitals, schools, sewers, transit and Civic Center work.
    1915passed first readingJournal 1915, p. 189 ↗
  • Greenebaum, Weil & Michaels paid $3,556.50 for hospital equipment
    16 Feb 1915passedJournal 1915, p. 242 ↗
  • Resolution proposed authorizing payments from school, water, transit and general funds to contractors, charities and utilities, passed for printing.
    15 Mar 1915passed first readingJournal 1915, p. 338 ↗
  • Pacific Gas and Electric paid $17,593 for the railway's electricity
    29 Mar 1915outcome not readJournal 1915, p. 363 ↗
  • Supervisor Jennings proposed appropriating funds for Civic Center trees, City Hall carpentry, sewers, and Relief Home repairs.
    5 Apr 1915outcome not readJournal 1915, p. 370 ↗
  • $960 set aside for trees in the Civic Center
    5 Apr 1915outcome not readJournal 1915, p. 387 ↗
  • Scott Company given ninety more days on City Hall's water system
    20 Apr 1915outcome not readJournal 1915, p. 259 ↗
  • Payments from the City Hall Civic Center bond fund to eight contractors were authorized, with the list continuing on the next page.
    10 May 1915outcome not readJournal 1915, p. 521 ↗
  • Resolution 11759 authorizes twelve City Hall construction payments from the Civic Center bond fund to contractors and suppliers. linked by the name only, not checked
    17 May 1915outcome not readJournal 1915, p. 538 ↗
  • City approved 32 payments totaling $66,954.62 to vendors and charities for books, water, school work and hospital supplies. linked by the name only, not checked
    24 May 1915passedJournal 1915, p. 564 ↗
  • Scott Company was granted a third 90-day extension to finish the City Hall water supply system work.
    28 Jun 1915passedJournal 1915, p. 763 ↗
  • Progress Laundry Company allowed a laundry at 3080 Seventeenth Street linked by the name only, not checked
    12 Jul 1915outcome not readJournal 1915, p. 809 ↗
  • Resolution approves payments to many contractors and suppliers for library books, hospitals, schools, paving and City Hall work.
    19 Jul 1915passedJournal 1915, p. 833 ↗
  • Scott Company granted a third ninety-day extension to complete the City Hall water supply system.
    27 Sep 1915passedJournal 1915, p. 1056 ↗
  • Scott Co. was paid $2,410 as final payment for heating and ventilating at Polytechnic High School. linked by the name only, not checked
    27 Sep 1915passedJournal 1915, p. 1052 ↗
  • Board finally passed a resolution authorizing dozens of city payments to contractors and suppliers for hospitals, fire stations, schools, streets and water. linked by the name only, not checked
  • The Board approved payment of 29 city claims, including Pacific Gas and Electric lighting and work on City Hall and San Francisco Hospital.
    22 Nov 1915passedJournal 1915, p. 1235 ↗
  • A ninety-day extension for the Scott Company's heating and ventilating work at the San Francisco Hospital was proposed.
    29 Nov 1915outcome not readJournal 1915, p. 1364 ↗
  • A resolution authorizing twenty payments to firms and individuals for Hetch Hetchy, fire, hospital and relief home work was passed for printing.
    20 Dec 1915passed first readingJournal 1915, p. 1432 ↗
  • Board authorized payments to contractors and utilities, including $2,864.28 to Chas. B. Dunham for Hetch Hetchy work. linked by the name only, not checked
    27 Dec 1915outcome not readJournal 1915, p. 1457 ↗
  • Jennings moved payments to contractors for sewer, railway, hospital, Hetch Hetchy and firehouse work, passed for printing. linked by the name only, not checked
    27 Dec 1915passed first readingJournal 1915, p. 1449 ↗
  • $5,000 more for Hetch Hetchy aqueduct rights of way
    4 Jan 1916passedJournal 1916, p. 7 ↗
  • $530 for new sidewalks in front of Alamo Square
    7 Feb 1916outcome not readJournal 1916, p. 160 ↗
  • Board proposed appropriations for Relief Home boiler and foundations, school, fire and police building repairs, and City Hall moves.
    14 Feb 1916outcome not readJournal 1916, p. 167 ↗
  • New boiler for the Relief Home costing $5,720 approved linked by the name only, not checked
    21 Feb 1916passedJournal 1916, p. 182 ↗
  • Bakewell & Brown paid $15,526 for City Hall architectural work linked by the name only, not checked
    8 May 1916passed first readingJournal 1916, p. 444 ↗
  • R. C. Storrie paid $92,000 for the Twin Peaks tunnel linked by the name only, not checked
    15 May 1916passedJournal 1916, p. 490 ↗
  • Supervisor Power moved appropriations of $2,307.50 for City Hall clock, $3,960 for Redding School heating, and $675 for lockers.
    19 Jun 1916outcome not readJournal 1916, p. 667 ↗
  • A $62,713 resolution would fund construction of the Daniel Webster School through several city contracts. linked by the name only, not checked
    19 Jun 1916outcome not readJournal 1916, p. 668 ↗
  • Supervisors finally passed appropriations of $2,307.50 for the City Hall clock, $3,960 for Redding School heating and $675 for lockers.
    26 Jun 1916passedJournal 1916, p. 665 ↗
  • Board appropriated $62,713 from the Daniel Webster School budget to pay construction contracts and architect's fee.
    26 Jun 1916passedJournal 1916, p. 666 ↗
  • City bills paid, including $6,750 for the Juvenile Detention Home linked by the name only, not checked
    21 Aug 1916passed first readingJournal 1916, p. 885 ↗
  • City bills paid, including $6,750 for the Juvenile Detention Home
    28 Aug 1916passedJournal 1916, p. 891 ↗
  • $109,500 paid to R. C. Storrie for the Twin Peaks Tunnel linked by the name only, not checked
    18 Sep 1916passedJournal 1916, p. 947 ↗
  • $1,800 to finish the raised sidewalk on Buena Vista Avenue
    18 Sep 1916outcome not readJournal 1916, p. 958 ↗
  • Expenditures authorised for hospital heating and plumbing work by Scott Company and maintenance payments to several children's charities.
    25 Sep 1916outcome not readJournal 1916, p. 990 ↗
  • Resolution proposed to authorize payments to city contractors and suppliers for hospitals, Relief Home, fire, police and parks.
    2 Oct 1916outcome not readJournal 1916, p. 1056 ↗
  • Payments approved, including $5,720 to Scott Company for the Relief Home
    9 Oct 1916outcome not readJournal 1916, p. 1066 ↗
  • Board authorized payments to contractors and suppliers for parks, City Hall, hospital, railways and fire department.
    16 Oct 1916outcome not readJournal 1916, p. 1087 ↗
  • City authorizes payments to contractors and suppliers for sewers, hospitals, schools, library books, and other public works. linked by the name only, not checked
    16 Oct 1916outcome not readJournal 1916, p. 1094 ↗
  • The Board authorized payments from city funds to five firms, including for City Hall work and San Francisco Hospital plumbing. linked by the name only, not checked
    23 Oct 1916passedJournal 1916, p. 1093 ↗
  • Board authorized payment of claims to suppliers and contractors, including Pacific Gas & Electric street lighting and Hetch Hetchy railroad construction. linked by the name only, not checked
    23 Oct 1916passedJournal 1916, p. 1094 ↗
  • R. C. Storrie paid $128,500 for Twin Peaks tunnel work
    20 Nov 1916outcome not readJournal 1916, p. 1182 ↗
  • Otis Elevator paid $2,885 for the Juvenile Court elevators
    11 Dec 1916outcome not readJournal 1916, p. 1251 ↗
  • A resolution authorizing fourteen city payments, including Redding School, Paul Revere School and San Francisco Hospital work, was passed for printing on Supervisor Power's motion.
    11 Dec 1916passed first readingJournal 1916, p. 1251 ↗
  • Otis Elevator paid $2,885 for the Juvenile Court elevators
    18 Dec 1916outcome not readJournal 1916, p. 1261 ↗
  • Board authorized dozens of city payments to contractors, suppliers and institutions, including a library granite contract and Hetch Hetchy work; list continues.
    15 Jan 1917outcome not readJournal 1917, p. 82 ↗
  • Flinn & Treacy paid $593.85 for work on Clarendon Avenue linked by the name only, not checked
    22 Jan 1917outcome not readJournal 1917, p. 107 ↗
  • $6,200 set aside to extend Lippard Street south from Joost Avenue linked by the name only, not checked
    5 Feb 1917outcome not readJournal 1917, p. 160 ↗
  • $8,185 set aside for sterilizers at San Francisco Hospital
    13 Feb 1917outcome not readJournal 1917, p. 178 ↗
  • The Board authorized payments from city bond and general funds to contractors for Hetch Hetchy, Daniel Webster School, Sanchez Street and San Francisco Hospital work.
    13 Feb 1917outcome not readJournal 1917, p. 184 ↗
  • Proposed payment from the Water Construction Fund of insurance premiums for city workers building the Hetch Hetchy water system. linked by the name only, not checked
    20 Feb 1917outcome not readJournal 1917, p. 222 ↗
  • Supervisor Power presented a resolution authorizing many city payments to contractors and utilities, including Hetch Hetchy and hospital work; the vote is not on this page.
    12 Mar 1917outcome not readJournal 1917, p. 299 ↗
  • Resolution authorizing dozens of city payments to contractors, utilities and pensions, including hospital, school, library and sewer work, pending final passage. linked by the name only, not checked
    19 Mar 1917outcome not readJournal 1917, p. 324 ↗
  • The Board authorized payments totalling tens of thousands of dollars for schools, hospitals, water works, sewers and charities, passed for printing.
    16 Apr 1917passed first readingJournal 1917, p. 490 ↗
  • Expenditures totalling $60,174.68 were authorized for 20 payments to contractors and suppliers for schools, hospitals, water and parks.
    23 Apr 1917passedJournal 1917, p. 508 ↗
  • Power's resolution authorises city payments to contractors and suppliers, including $85,000 to R. C. Storrie & Co. for the Twin Peaks tunnel. linked by the name only, not checked
    7 May 1917passed first readingJournal 1917, p. 576 ↗
  • Board authorizes payments on dozens of city claims for water, transit, hospital, school and street work.
    14 May 1917outcome not readJournal 1917, p. 589 ↗
  • Proposed appropriations of small sums from the City Hall Civic Center fund for architects, metalwork, flooring, heating and furniture.
    14 May 1917outcome not readJournal 1917, p. 589 ↗
  • Supervisor McLeran proposed extending time for named contractors to finish work on the southeast wing of San Francisco Hospital.
    14 May 1917outcome not readJournal 1917, p. 593 ↗
  • Resolution 14338 authorizes 1917 city spending on fire, schools, libraries and parks; the final vote is on the next page. linked by the name only, not checked
    14 May 1917outcome not readJournal 1917, p. 581 ↗
  • Authorizes about thirty city payments to contractors, suppliers and pensioners for transit, hospital, school and water works. linked by the name only, not checked
    21 May 1917passedJournal 1917, p. 604 ↗
  • Proposes setting aside City Hall Civic Center bond funds for architectural services by Bakewell & Brown.
    21 May 1917outcome not readJournal 1917, p. 604 ↗
  • Board granted 90-day extensions to four contractors finishing the northeast wing of San Francisco Hospital.
    18 Jun 1917passedJournal 1917, p. 836 ↗
  • Bills paid, including $564.01 for ice cream in Golden Gate Park
    25 Jun 1917passedJournal 1917 ↗
  • Payment of listed claims for minors' maintenance, furniture and school heating work approved by 16 supervisors. linked by the name only, not checked
    25 Jun 1917passedJournal 1917 ↗
  • $37,540.88 paid to United States Steel Products for Municipal Railway rails
    30 Jul 1917outcome not readJournal 1917, p. 996 ↗
  • Resolution authorising about 30 city claims, including hospital, water and fire supplies, was passed for printing on Power's motion.
    13 Aug 1917passed first readingJournal 1917, p. 1039 ↗
  • $1,896.30 final payment to Scott Company for Daniel Webster School heating
    20 Aug 1917outcome not readJournal 1917, p. 1055 ↗
  • Resolution authorizing $58,732.59 in payments to fifteen contractors and suppliers for schools, hospital, water and transit was passed for printing. linked by the name only, not checked
    24 Sep 1917passed first readingJournal 1917, p. 1212 ↗
  • Newsom & Henning paid $1,338.50 for the Fairmount School yard
  • Board authorized payments from city funds to contractors and suppliers for schools, hospital work, railways, water, police and pensions, with the list continuing. linked by the name only, not checked
    9 Oct 1917passed first readingJournal 1917, p. 1274 ↗
  • Supervisors finally passed Resolution 14921 authorizing payments to contractors and suppliers for schools, hospitals, railways, libraries and police.
    22 Oct 1917passedJournal 1917, p. 1316 ↗
  • Proposed extensions of time for contractors O. Monson and W. & J. Sloane on the San Francisco Hospital northeast wing. linked by the name only, not checked
    19 Nov 1917outcome not readJournal 1917, p. 1401 ↗
  • $4,497 set aside for plumbing at the San Francisco Hospital
    10 Dec 1917passedJournal 1917, p. 1461 ↗
  • Extensions of time were granted to contractors on San Francisco Hospital construction work on Board of Public Works recommendation.
    17 Dec 1917outcome not readJournal 1917, p. 1504 ↗
  • Resolution authorizing payments to many claimants, including library book dealers, hospital contractors and Spring Valley Water; passed for printing.
    14 Jan 1918outcome not readJournal 1918, p. 30 ↗
  • Ninety-day time extension proposed for Scott Company on the east wing of San Francisco Hospital, on Board of Public Works recommendation.
    21 Jan 1918outcome not readJournal 1918, p. 56 ↗
  • Board passed resolution authorizing 29 city payments, nearly $100,000 total, to contractors, charities, utilities and suppliers.
    21 Jan 1918outcome not readJournal 1918, p. 48 ↗
  • Sixteen payments from city funds were authorized to claimants and contractors for hospital, Hetch Hetchy, transit, and Fire Department work.
    4 Feb 1918passed first readingJournal 1918, p. 108 ↗
  • Scott Company paid $9,300 for plumbing at San Francisco Hospital
    11 Feb 1918passedJournal 1918, p. 123 ↗
  • H. S. Crocker paid $661.85 for books for the Public Library
    11 Mar 1918outcome not readJournal 1918, p. 209 ↗
  • H. S. Crocker paid $661.85 for books for the Public Library
    18 Mar 1918outcome not readJournal 1918, p. 222 ↗
  • $177,725 set aside to build Monroe School on Excelsior Avenue
    30 Sep 1918passedJournal 1918, p. 843 ↗
  • Joshua Hendy Iron Works to build $17,775 of dump cars
    21 Oct 1918outcome not readJournal 1918, p. 882 ↗
  • Payments approved for library books and Hetch Hetchy supplies
    19 May 1919passedJournal 1919, p. 378 ↗
  • Board passed resolution authorizing dozens of city claims, including Municipal Railway repairs, library books and Great Highway paving payments.
    18 Aug 1919passedJournal 1919, p. 684 ↗
  • Board of Public Works extended 40-day contract deadlines for four firms building the Monroe School. linked by the name only, not checked
    18 Aug 1919passedJournal 1919, p. 691 ↗
  • A schedule of city payments to contractors and suppliers was passed for printing, covering Hetch Hetchy, school, library and Muni work. linked by the name only, not checked
    15 Sep 1919passed first readingJournal 1919, p. 760 ↗
  • Payments of $10,050.38 to General Electric and $1,646.06 to Wm. Cluff Co. for Hetch Hetchy work were proposed.
    22 Sep 1919outcome not readJournal 1919, p. 775 ↗
  • Resolution authorizes payment of city claims to suppliers and contractors for Hetch Hetchy, Jefferson School, Municipal Railways and police. linked by the name only, not checked
    17 Jan 1921outcome not readJournal 1921, p. 51 ↗
  • Payments authorized to contractors and suppliers for Hetch Hetchy, Jefferson School, Municipal Railways and city departments. linked by the name only, not checked
    24 Jan 1921outcome not readJournal 1921, p. 71 ↗
  • Scott Company's $3,327.52 claim for delays on San Francisco Hospital plumbing was laid over one week.
    7 Feb 1921continuedJournal 1921, p. 109 ↗
  • Resolution proposed to disallow Scott Company's $3,327.52 claim for delay damages on San Francisco Hospital plumbing. linked by the name only, not checked
    14 Feb 1921outcome not readJournal 1921, p. 122 ↗
  • Municipal Railway power, printing, and Jefferson School heating payments authorized for Pacific Gas & Electric, United Railroads, Hancock Bros. and Scott Company.
    21 Feb 1921passed first readingJournal 1921, p. 140 ↗
  • Scott Company receives $2,196.74 in full settlement of its plumbing-contract damages claim at San Francisco Hospital.
    21 Feb 1921passedJournal 1921, p. 137 ↗
  • Resolution authorizes city payments to utilities, suppliers and contractors for transit, Hetch Hetchy and public works; final vote is on the next page.
    7 Mar 1921outcome not readJournal 1921, p. 155 ↗
  • Resolution authorizes payments to eight firms and individuals, including school architect fees and Hetch Hetchy supplies and services.
    25 Apr 1921outcome not readJournal 1921, p. 294 ↗
  • $130,818.83 more set aside to build the Emerson School linked by the name only, not checked
    25 Jul 1921outcome not readJournal 1921, p. 652 ↗
  • $130,818.83 more set aside to build the Emerson School
    1 Aug 1921outcome not readJournal 1921, p. 666 ↗
  • A resolution authorizing dozens of payments from school, Hetch Hetchy, park, police and hospital funds was passed for printing.
    15 Aug 1921passed first readingJournal 1921, p. 699 ↗
  • Payments authorized to suppliers and contractors for Jefferson School and Hetch Hetchy work, pending final passage.
    22 Aug 1921outcome not readJournal 1921, p. 706 ↗
  • $287,851 to be spent on the Mission High School addition linked by the name only, not checked
    21 Nov 1921outcome not readJournal 1921, p. 985 ↗
  • $287,851 set aside for the Mission High School addition
    5 Dec 1921outcome not readJournal 1921, p. 1012 ↗
  • $60,054 set aside to build an addition to the Adams School
    27 Dec 1921outcome not readJournal 1921, p. 1073 ↗
  • $60,054 set aside for an addition to the Adams School
    9 Jan 1922outcome not readJournal 1922 ↗
  • Proposed payments from city funds to contractors and claimants for school construction, transit, parks and other work.
    22 May 1922outcome not readJournal 1922 ↗
  • Board authorized dozens of city payments to contractors, utilities and suppliers for schools, streets, water and departments.
    31 May 1922passedJournal 1922 ↗
  • Board authorizes several payments to contractors for school construction and a Municipal Railway accident judgment to Vera Mann.
    31 May 1922passedJournal 1922 ↗
  • Payments authorized from city funds to contractors and claimants for school building, Taraval transit line and Hetch Hetchy dam work. linked by the name only, not checked
    12 Jun 1922outcome not readJournal 1922 ↗
  • Proposed appropriations of $150,979 and $94,100 for new school buildings, plus repairs and temporary classrooms, are pending. linked by the name only, not checked
    19 Jun 1922outcome not readJournal 1922 ↗
  • $150,979.25 set aside to build the Andrew Jackson School
    26 Jun 1922outcome not readJournal 1922 ↗
  • The Scott Co. was paid $3,176.70 for plumbing on the Mission High School addition. linked by the name only, not checked
    14 Aug 1922passedJournal 1922 ↗
  • Payments from the School Construction Fund for Mission High School and Adams School work were authorized to several contractors.
    11 Sep 1922outcome not readJournal 1922 ↗
  • Board authorized payments from school construction and water bond funds for Mission, Adams, Columbus and North Beach school work and Hetch Hetchy supplies.
    18 Sep 1922outcome not readJournal 1922 ↗
  • The Board authorized many payments to contractors and suppliers for school buildings, Municipal Railway, Hetch Hetchy water works, and fire facilities.
    9 Oct 1922passed first readingJournal 1922 ↗
  • Spring Valley Water Company paid $6,006.24 for Lake Merced links
    9 Oct 1922outcome not readJournal 1922 ↗
  • Spring Valley Water Company paid $6,006.24 for Lake Merced links
    23 Oct 1922outcome not readJournal 1922 ↗
  • Supervisor Scott presented a resolution on extensions of time for school buildings; its outcome appears on the next page.
    20 Nov 1922outcome not readJournal 1922 ↗
  • Board granted contractors ninety or thirty day extensions to finish additions to Spring Valley and Adams Schools. linked by the name only, not checked
    20 Dec 1922passedJournal 1922 ↗
  • Board passed for printing a resolution authorizing dozens of city payments to contractors, schools, hospitals and suppliers. linked by the name only, not checked
    8 Jan 1923passed first readingJournal 1923, p. 26 ↗
  • Board authorizes payments from city funds to many contractors and suppliers, including school construction, Golden Gate Park and Municipal Railway work. linked by the name only, not checked
    15 Jan 1923outcome not readJournal 1923, p. 39 ↗
  • Proposed payments of city funds to many claimants, including PG&E power, school construction and hospital food; the final vote is not shown here. linked by the name only, not checked
    26 Feb 1923outcome not readJournal 1923, p. 175 ↗
  • Pacific Gas and Electric paid $34,912.09 for Municipal Railway power linked by the name only, not checked
    5 Mar 1923outcome not readJournal 1923, p. 190 ↗
  • City bills paid to Pacific Gas and Electric and Westinghouse
    23 Apr 1923passed first readingJournal 1923, p. 386 ↗
  • Payments approved to John Morton, orphanages and the Fire Department linked by the name only, not checked
    23 Apr 1923outcome not readJournal 1923, p. 381 ↗
  • City bills paid to Pacific Gas and Electric and Westinghouse linked by the name only, not checked
    30 Apr 1923outcome not readJournal 1923, p. 412 ↗
  • The Scott Co. was authorized to be paid $4,473.50 for heating and ventilating at Andrew Jackson School. linked by the name only, not checked
    20 Aug 1923passedJournal 1923, p. 888 ↗
  • The Scott Co. was authorized to be paid $6,159.75 for plumbing work at Mission High School. linked by the name only, not checked
    20 Aug 1923passedJournal 1923, p. 888 ↗
  • Board authorizes payments to dozens of claimants for water, school, street and general city work, totalling tens of thousands of dollars. linked by the name only, not checked
    10 Mar 1924outcome not readJournal 1924, p. 259 ↗
  • $762.32 for auditorium chairs at the Pacific Heights School linked by the name only, not checked
    17 Mar 1924passedJournal 1924, p. 275 ↗
  • Supervisor McLeran moved to authorize payment of many city claims, including PG&E, orphanages and a Funston Playground contractor; passed for printing. linked by the name only, not checked
    14 Apr 1924passed first readingJournal 1924, p. 389 ↗
  • Resolution authorizes payment of listed claims to city suppliers and utilities, including $47,407.44 to PG&E for street lighting. linked by the name only, not checked
    21 Apr 1924outcome not readJournal 1924, p. 433 ↗
  • The Scott Company to redo the Hall of Justice heating, $2,896
    18 May 1925outcome not readJournal 1925, p. 697 ↗
  • Scott Company paid $2,896 to redo Hall of Justice heating
    25 May 1925outcome not readJournal 1925, p. 730 ↗
  • Barrett & Hilp to build the Douglass-Everett School on Sanchez Street linked by the name only, not checked
    8 Jun 1925outcome not readJournal 1925, p. 836 ↗
  • Barrett & Hilp to build the Douglass-Everett School on Sanchez Street linked by the name only, not checked
    15 Jun 1925outcome not readJournal 1925, p. 860 ↗
  • New gym and athletic field for Galileo High School, $155,881
    14 Sep 1925outcome not readJournal 1925, p. 1324 ↗
  • New gym and athletic field for Galileo High School, $155,881
    21 Sep 1925outcome not readJournal 1925, p. 1350 ↗
  • $16,200 set aside to rebuild Fillmore Street between Chestnut and Bay linked by the name only, not checked
    23 Nov 1925outcome not readJournal 1925, p. 1612 ↗
  • Board appropriates $14,800 for painting San Francisco Hospital, repairing a Relief Home engine and heating the Central Fire Alarm Station. linked by the name only, not checked
    21 Dec 1925outcome not readJournal 1925, p. 1795 ↗
  • Board adopted $14,800 for painting San Francisco Hospital, repairing an engine at the Relief Home, and heating the Central Fire Alarm Station. linked by the name only, not checked
    30 Dec 1925passedJournal 1925, p. 1833 ↗
  • Resolution authorizing payments to suppliers, contractors and a land seller from Hetch Hetchy, school and relief home funds was passed for printing. linked by the name only, not checked
    8 Feb 1926passed first readingJournal 1926, p. 203 ↗
  • MacDonald & Kahn paid $36,531.82 for the New Mission High School
    15 Feb 1926passed first readingJournal 1926, p. 236 ↗
  • The Scott Company was paid $860.50 as final payment for remodeling the Hall of Justice heating system.
    23 Feb 1926passedJournal 1926, p. 254 ↗
  • Payments for school construction, Hetch Hetchy water works and park work were sent to print for authorization.
    8 Mar 1926passed first readingJournal 1926, p. 349 ↗
  • Scott Co. listed for $2,770 final payment for heating at Central Fire Alarm Station. linked by the name only, not checked
    15 Mar 1926outcome not readJournal 1926, p. 385 ↗
  • Parkside School annex to cost $63,816.60, built by Carl H. Peterson
    15 Mar 1926outcome not readJournal 1926, p. 387 ↗
  • Board authorized dozens of payments to contractors and suppliers for school buildings, a San Jose avenue bridge, and Hetch Hetchy works. linked by the name only, not checked
    15 Mar 1926outcome not readJournal 1926, p. 374 ↗
  • Musical Association paid $2,000 for a San Francisco Symphony concert linked by the name only, not checked
    15 Mar 1926outcome not readJournal 1926, p. 384 ↗
  • Parkside School annex to cost $63,816.60, built by Carl H. Peterson
    22 Mar 1926outcome not readJournal 1926, p. 419 ↗
  • Board authorized dozens of city payments to contractors, suppliers and charities for schools, libraries, a hospital and street repairs. linked by the name only, not checked
    22 Mar 1926passedJournal 1926, p. 417 ↗
  • Edison School to be built on Dolores Street for $341,803.42
    22 Mar 1926outcome not readJournal 1926, p. 419 ↗
  • The Scott Co. listed for a $1,027.50 first payment on the Parkside School annex heating system.
    21 Jun 1926outcome not readJournal 1926, p. 1050 ↗
  • A resolution authorizing 33 payments for school construction, fire land and park supplies was passed for printing. linked by the name only, not checked
    12 Jul 1926passed first readingJournal 1926, p. 1182 ↗
  • Board authorizes payments from city funds to contractors for school construction, parks, a sanitarium and the Hetch Hetchy aqueduct, July 1926. linked by the name only, not checked
    19 Jul 1926outcome not readJournal 1926, p. 1204 ↗
  • Appropriation of $922,760.30 for building Mission Junior High School; the resolution continues on the next page. linked by the name only, not checked
    9 Aug 1926outcome not readJournal 1926, p. 1310 ↗
  • Resolution authorizing dozens of claim payments for parks, school construction, a tuberculosis sanitarium and Municipal Railway equipment, passed for printing. linked by the name only, not checked
    9 Aug 1926outcome not readJournal 1926, p. 1309 ↗
  • Youdall and Clifford paid $49,162.50 for the Buena Vista Park tunnel linked by the name only, not checked
    23 Aug 1926outcome not readJournal 1926, p. 1330 ↗
  • Resolution 26067 proposes $922,760.30 from the school bond fund to construct Mission Junior High School. linked by the name only, not checked
    23 Aug 1926outcome not readJournal 1926, p. 1332 ↗
  • Frank Labrucherie's land bought for $11,500 to extend Park Street linked by the name only, not checked
    7 Sep 1926outcome not readJournal 1926, p. 1426 ↗
  • Board authorized payments from school and other funds to contractors and suppliers for schools including Le Conte and Edison. linked by the name only, not checked
    20 Sep 1926passedJournal 1926, p. 1479 ↗
  • $125,224 to build additions to the Commodore Sloat School linked by the name only, not checked
    27 Sep 1926outcome not readJournal 1926, p. 1531 ↗
  • $125,224 to build additions to the Commodore Sloat School linked by the name only, not checked
    4 Oct 1926outcome not readJournal 1926, p. 1566 ↗
  • Resolution authorizing payments to contractors and suppliers for fire, hospital, school and Hetch Hetchy work was passed for printing.
    11 Oct 1926passed first readingJournal 1926, p. 1621 ↗
  • Authorizes many payments to contractors for schools, Hetch Hetchy works, Relief Home buildings, a hospital ward and a firehouse. linked by the name only, not checked
    25 Oct 1926outcome not readJournal 1926, p. 1670 ↗
  • Scott Company was paid $747.37 in final payment for heating installation at Parkside School annex. linked by the name only, not checked
    8 Nov 1926outcome not readJournal 1926, p. 1751 ↗
  • Scott Company was paid $747.37 as final payment for heating installation at the Parkside School annex. linked by the name only, not checked
    22 Nov 1926outcome not readJournal 1926, p. 1805 ↗
  • A $307,037 appropriation for general construction of Sherman School is proposed on this page.
    13 Dec 1926outcome not readJournal 1926, p. 1936 ↗
  • Sherman School on Union Street to cost $307,037
    20 Dec 1926outcome not readJournal 1926, p. 1960 ↗
  • Resolution proposed to authorize about thirty city payments to contractors and suppliers for libraries, schools, Hetch Hetchy and Municipal Railways. linked by the name only, not checked
    14 Feb 1927outcome not readJournal 1927, p. 262 ↗
  • Resolution authorizes payments to named contractors for library books, Municipal Railways equipment, school work and Hetch Hetchy aqueduct tunnels; vote continues on next page. linked by the name only, not checked
    21 Feb 1927outcome not readJournal 1927, p. 279 ↗
  • Payments from the School Construction Fund for several San Francisco school buildings were authorized, passed for printing on motion of McSheehy. linked by the name only, not checked
    7 Mar 1927passed first readingJournal 1927, p. 372 ↗
  • Payments to builders, architects and suppliers for city school construction and a municipal concert are authorized from school and auditorium funds. linked by the name only, not checked
    14 Mar 1927outcome not readJournal 1927, p. 410 ↗
  • The Board finally passed a resolution authorizing payments from Hetch Hetchy, Municipal Railway and school funds to contractors and suppliers. linked by the name only, not checked
    11 Apr 1927passedJournal 1927, p. 590 ↗
  • Appropriation of $450,562 from the school construction fund proposed for building the Portola Junior High School. linked by the name only, not checked
    11 Apr 1927outcome not readJournal 1927, p. 603 ↗
  • $450,562 appropriated from school bond funds to build the Portola Junior High School, with contracts to several firms. linked by the name only, not checked
    18 Apr 1927passedJournal 1927, p. 646 ↗
  • Scott Company is paid $1,531.88 for mechanical equipment at Edison School. linked by the name only, not checked
    9 May 1927outcome not readJournal 1927, p. 779 ↗
  • Scott Company is paid $1,684.50 for mechanical equipment at Mission (Everett) Junior High School. linked by the name only, not checked
    9 May 1927outcome not readJournal 1927, p. 779 ↗
  • Resolution lists payments to contractors and suppliers for park, school, fire station and sanitarium work; outcome continues on next page. linked by the name only, not checked
    9 May 1927outcome not readJournal 1927, p. 778 ↗
  • Board passed payments to contractors and suppliers for schools, parks, a fire house, a sanitarium and the Sunset tunnel. linked by the name only, not checked
    16 May 1927passedJournal 1927, p. 841 ↗
  • Scott Company is paid $1,531.88 for a fourth payment on mechanical equipment at Edison School. linked by the name only, not checked
    16 May 1927outcome not readJournal 1927, p. 842 ↗
  • Board authorizes payments to contractors and suppliers for school, Hetch Hetchy, transit, park and fire projects; the list continues. linked by the name only, not checked
    6 Jun 1927outcome not readJournal 1927, p. 1135 ↗
  • Scott Company was owed $911.24 for mechanical equipment at Edison School, fifth payment. linked by the name only, not checked
    13 Jun 1927outcome not readJournal 1927, p. 1165 ↗
  • A resolution authorizing expenditure of listed amounts came up for final passage; the outcome is not printed on this page. linked by the name only, not checked
    13 Jun 1927outcome not readJournal 1927, p. 1163 ↗
  • Final payment of $1,760.80 to Scott Co. for mechanical equipment at Commodore Sloat School.
    1 Aug 1927outcome not readJournal 1927, p. 1424 ↗
  • Final payment of $4,398.13 to The Scott Company for mechanical equipment at Edison School.
    1 Aug 1927outcome not readJournal 1927, p. 1424 ↗
  • City bills paid for playgrounds, golf balls and Third Street repairs linked by the name only, not checked
    8 Aug 1927outcome not readJournal 1927, p. 1471 ↗
  • Resolution authorising sixteen payments to contractors and claimants for school, park, fire and aquarium work, passed for printing.
    6 Sep 1927passed first readingJournal 1927, p. 1681 ↗
  • Board authorized payments to contractors and suppliers for school construction, park materials, a fire engine house and museum costs. linked by the name only, not checked
    19 Sep 1927passedJournal 1927, p. 1730 ↗
  • Youdall Construction paid $42,313.50 for the tunnel under Buena Vista Park linked by the name only, not checked
    24 Oct 1927outcome not readJournal 1927, p. 2013 ↗
  • A resolution authorizes payment of numbered claims for school, fire, park, tunnel and Municipal Railway work; the final vote is not printed here.
    7 Nov 1927outcome not readJournal 1927, p. 2144 ↗
  • The Board passed for printing a resolution authorizing dozens of city payments for parks, schools, fire houses, Municipal Railway supplies and street repairs. linked by the name only, not checked
    5 Dec 1927passed first readingJournal 1927, p. 2253 ↗
  • City pays $3,659.73 to maintain Steinhart Aquarium in November linked by the name only, not checked
    12 Dec 1927passedJournal 1927, p. 2276 ↗
  • The Board passed for printing a resolution authorizing payments for school, fire and playground work, including Sherman School and Portola Junior High School. linked by the name only, not checked
    9 Jan 1928passed first readingJournal 1928, p. 45 ↗
  • Payments proposed to contractors and suppliers for Galileo and Mission High Schools, Mission Junior High, and Fire Engine House 18; vote continues next page. linked by the name only, not checked
    16 Jan 1928outcome not readJournal 1928, p. 65 ↗
  • City pays $4,960 for Galileo High School chairs linked by the name only, not checked
    16 Jan 1928passedJournal 1928, p. 64 ↗
  • Battista Boeto paid for land taken for Bay Shore Boulevard linked by the name only, not checked
    6 Feb 1928outcome not readJournal 1928, p. 199 ↗
  • Bills paid for Engine House No. 18 and the Steinhart Aquarium linked by the name only, not checked
    14 Feb 1928outcome not readJournal 1928, p. 246 ↗
  • Resolution authorises payments to contractors and suppliers for parks, playgrounds, Hetch Hetchy and the Municipal Railway, passed for printing. linked by the name only, not checked
    1 Mar 1928passed first readingJournal 1928, p. 353 ↗
  • E. H. McManus paid for school land on Thirty-second Avenue linked by the name only, not checked
    5 Mar 1928outcome not readJournal 1928, p. 377 ↗
  • Claims for aquarium upkeep, fire house construction, and school equipment and electrical work were passed for printing. linked by the name only, not checked
    5 Mar 1928passed first readingJournal 1928, p. 375 ↗
  • Board finally passed authorization of about 28 payments to suppliers and utilities for parks, playgrounds and Hetch Hetchy works. linked by the name only, not checked
    12 Mar 1928passedJournal 1928, p. 404 ↗
  • Scott Co. to be paid $757.50 for mechanical equipment at Sherman School.
    12 Mar 1928outcome not readJournal 1928, p. 406 ↗
  • Scott Co. to be paid $1,245 for mechanical equipment at Mission (Everett) Jr. High School.
    12 Mar 1928outcome not readJournal 1928, p. 406 ↗
  • Finance Committee recommended authorizing payments for the United States Fleet reception, with the outcome continuing to the next page. linked by the name only, not checked
    14 May 1928outcome not readJournal 1928, p. 795 ↗
  • Board approved a batch of May 1928 payment claims for street repair, playgrounds, schools, election costs and Fire Department supplies.
    28 May 1928passedJournal 1928, p. 1051 ↗
  • Payments approved for the Sunset-Duboce tunnel and Mission Junior High School linked by the name only, not checked
    28 May 1928outcome not readJournal 1928, p. 868 ↗
  • $89,434 set aside to enlarge the Jefferson School on Nineteenth Avenue
    4 Jun 1928outcome not readJournal 1928, p. 1134 ↗
  • $89,434 set aside to enlarge the Jefferson School on Nineteenth Avenue
    11 Jun 1928outcome not readJournal 1928, p. 1189 ↗
  • First payment of $3,296.25 to Scott Co. for mechanical equipment at the Jefferson School is listed. linked by the name only, not checked
    6 Aug 1928outcome not readJournal 1928, p. 1601 ↗
  • Payment of $1,210.14 to Scott Company for mechanical equipment at Jefferson School approved.
  • A second payment of $1,210.14 to Scott Company for mechanical equipment at Jefferson School was listed.
    22 Oct 1928outcome not readJournal 1928, p. 2274 ↗
  • Mission Concrete gets the $270,624 contract for Balboa High School
    29 Oct 1928outcome not readJournal 1928, p. 2332 ↗
  • The Scott Co. was paid $1,209.76 as a third payment for mechanical equipment at Jefferson School additions.
    5 Nov 1928outcome not readJournal 1928, p. 2386 ↗
  • Mission Concrete gets the $270,624 contract for Balboa High School
    5 Nov 1928outcome not readJournal 1928, p. 2372 ↗
  • The Scott Co. was paid $1,209.76 for mechanical equipment at Jefferson School additions.
    19 Nov 1928outcome not readJournal 1928, p. 2455 ↗
  • Resolution proposed to fund $139,581 for a Polytechnic High School addition and $71,281 for a Harrison Street school warehouse, passed for printing.
    10 Dec 1928passed first readingJournal 1928, p. 2603 ↗
  • Mahoney Bros to build the Polytechnic High School addition
    17 Dec 1928outcome not readJournal 1928, p. 2644 ↗
  • Board authorized about 28 routine claim payments for roads, Municipal Railways, Hetch Hetchy water works and schools; outcome printed on previous page.
    21 Jan 1929outcome not readJournal 1929, p. 116 ↗
  • The Scott Co. was listed for $10,164.83 as a first payment for equipment at Balboa High School.
    28 Jan 1929outcome not readJournal 1929, p. 149 ↗
  • Scott Co. was paid $1,783.27 as second payment for mechanical equipment at South Side (Balboa) High School.
    4 Feb 1929outcome not readJournal 1929, p. 246 ↗
  • Scott Co. was paid $1,783.27 as second payment for mechanical equipment at South Side (Balboa) High School.
    11 Feb 1929outcome not readJournal 1929, p. 265 ↗
  • Claim of $2,618.85 listed as final payment to Scott Company for Jefferson School mechanical equipment.
    11 Mar 1929outcome not readJournal 1929, p. 474 ↗
  • Final payment of $2,618.85 to Scott Company for mechanical equipment at Jefferson School is listed.
    18 Mar 1929outcome not readJournal 1929 ↗
  • $480,675 set aside to build Roosevelt Junior High School at Arguello Boulevard
    15 Apr 1929outcome not readJournal 1929, p. 717 ↗
  • $480,675 set aside to build Roosevelt Junior High School at Arguello Boulevard
    22 Apr 1929outcome not readJournal 1929, p. 740 ↗
  • $62,060.30 more for wiring and plumbing at Roosevelt Junior High School
    6 May 1929outcome not readJournal 1929, p. 901 ↗
  • $62,060.30 more for wiring and plumbing at Roosevelt Junior High School
    13 May 1929outcome not readJournal 1929, p. 923 ↗
  • $123,997.32 to build the Geary Street School beside Laurel Hill Cemetery
    13 May 1929outcome not readJournal 1929, p. 931 ↗
  • A resolution authorizing dozens of payments to contractors and suppliers for school, boulevard and water work was passed for printing.
    13 May 1929outcome not readJournal 1929, p. 927 ↗
  • $123,997.32 set aside to build the Geary Street School
    20 May 1929outcome not readJournal 1929, p. 958 ↗
  • Louis J. Conn paid $24,450 for Bayshore Boulevard work
    20 May 1929passedJournal 1929, p. 954 ↗
  • Scott Co. was paid $980.78 as fourth payment for mechanical equipment at South Side High School.
    10 Jun 1929outcome not readJournal 1929, p. 1166 ↗
  • Scott Co. was paid $960 as second payment for mechanical equipment at Polytechnic High School additions.
    10 Jun 1929outcome not readJournal 1929, p. 1166 ↗
  • Scott Co. is listed for a $960 second payment on Polytechnic High School mechanical equipment.
    17 Jun 1929outcome not readJournal 1929, p. 1227 ↗
  • Scott Co. is listed for a $980.78 fourth payment on South Side High School mechanical equipment.
    17 Jun 1929outcome not readJournal 1929, p. 1227 ↗
  • Payment of $1,873.50 to Scott Co. listed for plumbing at Roosevelt Junior High School.
    8 Jul 1929outcome not readJournal 1929, p. 1361 ↗
  • Payment of $555 to Scott Co. listed for mechanical equipment at Polytechnic High School additions. linked by the name only, not checked
    8 Jul 1929outcome not readJournal 1929, p. 1361 ↗
  • Fifth payment of $1,221.64 to Scott Company for mechanical equipment at South Side (Balboa) High School is authorized.
    8 Jul 1929outcome not readJournal 1929, p. 1360 ↗
  • Scott Co. is paid $555 for mechanical equipment for additions to Polytechnic High School. linked by the name only, not checked
    15 Jul 1929outcome not readJournal 1929, p. 1386 ↗
  • $758,580.22 set aside for the Park-Presidio Junior High School
    15 Jul 1929outcome not readJournal 1929, p. 1396 ↗
  • Scott Company is paid $1,221.64 for mechanical equipment at the South Side (Balboa) High School. linked by the name only, not checked
    15 Jul 1929outcome not readJournal 1929, p. 1386 ↗
  • Scott Co. is paid $1,873.50 for plumbing at Roosevelt Junior High School.
    15 Jul 1929outcome not readJournal 1929, p. 1386 ↗
  • $758,580.22 set aside to build the Park-Presidio Junior High School
    22 Jul 1929outcome not readJournal 1929, p. 1457 ↗
  • Sixth payment of $2,145 to Scott Co. for mechanical equipment at South Side High School listed for payment.
    19 Aug 1929outcome not readJournal 1929, p. 1618 ↗
  • Payments totalling $123,062.71 to contractors and suppliers for schools, playgrounds and boulevard work are authorized.
    10 Sep 1929outcome not readJournal 1929, p. 1749 ↗
  • Payment of $2,534.25 to Scott Co. for mechanical equipment at Park-Presidio Junior High School is listed for approval. linked by the name only, not checked
    7 Oct 1929outcome not readJournal 1929, p. 1946 ↗
  • Payment of $1,454.70 to Scott Co. for plumbing at Roosevelt Junior High School is listed for approval.
    7 Oct 1929outcome not readJournal 1929, p. 1946 ↗
  • Payment of $1,006.02 to Scott Co. for plumbing at Park-Presidio Junior High School is listed for approval. linked by the name only, not checked
    7 Oct 1929outcome not readJournal 1929, p. 1946 ↗
  • Payment of $4,703.70 to Scott Co. for mechanical equipment at Roosevelt Junior High School is listed for approval. linked by the name only, not checked
    7 Oct 1929outcome not readJournal 1929, p. 1946 ↗
  • Payment of $2,638.20 to Scott Co. for mechanical equipment at Geary Street School is listed for approval.
    7 Oct 1929outcome not readJournal 1929, p. 1946 ↗
  • Payment of $693.75 to Scott Co. for mechanical equipment at Polytechnic High School additions is listed for approval.
    7 Oct 1929outcome not readJournal 1929, p. 1946 ↗
  • Scott Co. was listed for $2,638.20, first payment on mechanical equipment at Geary Street School.
    21 Oct 1929outcome not readJournal 1929, p. 2017 ↗
  • Scott Co. was paid $1,006.02, first payment on plumbing at Park-Presidio Junior High School. linked by the name only, not checked
    21 Oct 1929outcome not readJournal 1929, p. 2016 ↗
  • Scott Co. was paid $2,534.25, second payment on mechanical equipment at Park-Presidio Junior High School. linked by the name only, not checked
    21 Oct 1929outcome not readJournal 1929, p. 2016 ↗
  • Scott Co. was paid $1,454.70, second payment on plumbing at Roosevelt Junior High School.
    21 Oct 1929outcome not readJournal 1929, p. 2016 ↗
  • Scott Co. was listed for $693.75, fourth payment on mechanical equipment at Polytechnic High School additions.
    21 Oct 1929outcome not readJournal 1929, p. 2017 ↗
  • Scott Co. was paid $4,703.70, third payment on mechanical equipment at Roosevelt Junior High School. linked by the name only, not checked
    21 Oct 1929outcome not readJournal 1929, p. 2016 ↗
  • $13,000 for additions to the Sunshine School on Dolores Street
    4 Nov 1929outcome not readJournal 1929, p. 2094 ↗
  • A $3,768.75 third payment to Scott Co. for equipment at Park-Presidio Junior High School is listed; approval not printed here. linked by the name only, not checked
    4 Nov 1929outcome not readJournal 1929, p. 2092 ↗
  • A $2,414.70 third payment to Scott Co. for plumbing at Roosevelt Junior High School is listed; approval not printed here.
    4 Nov 1929outcome not readJournal 1929, p. 2092 ↗
  • A $1,011.30 fourth payment to Scott Co. for mechanical equipment at Roosevelt Junior High School is listed; approval not printed here.
    4 Nov 1929outcome not readJournal 1929, p. 2092 ↗
  • A $2,931.63 seventh payment to Scott Co. for equipment at Balboa High School is listed; approval not printed here.
    4 Nov 1929outcome not readJournal 1929, p. 2092 ↗
  • A $1,816.04 second payment to Scott Co. for plumbing at Park-Presidio Junior High School is listed; approval not printed here. linked by the name only, not checked
    4 Nov 1929outcome not readJournal 1929, p. 2092 ↗
  • Resolution proposed appropriating $185,474.98 from Special School Tax to build an addition to Francisco Junior High School.
    18 Nov 1929outcome not readJournal 1929, p. 2141 ↗
  • Scott Co. was paid $2,414.70 for plumbing and gas-fitting at Roosevelt Junior High School.
    18 Nov 1929outcome not readJournal 1929, p. 2130 ↗
  • Scott Co. was paid $1,816.04 for plumbing and gas fitting at Park-Presidio Junior High School.
    18 Nov 1929outcome not readJournal 1929, p. 2130 ↗
  • $13,000 for additions to the Sunshine School on Dolores Street
    18 Nov 1929outcome not readJournal 1929, p. 2132 ↗
  • The Board appropriated $185,474.98 from the Special School Tax to build an addition to Francisco Junior High School.
    25 Nov 1929passedJournal 1929, p. 2189 ↗
  • Payments authorised to contractors and suppliers for school buildings, street reconstruction, Bernal Cut work and municipal concerts; resolution continues from previous page.
    9 Dec 1929outcome not readJournal 1929, p. 2290 ↗
  • Scott Co.'s fourth payment of $1,357.50 for plumbing at Roosevelt Jr. High School is listed for payment.
    16 Dec 1929outcome not readJournal 1929, p. 2341 ↗
  • Scott Co.'s second payment of $1,288.65 for mechanical equipment at Geary Street School is listed for payment.
    16 Dec 1929outcome not readJournal 1929, p. 2341 ↗
  • Scott Co.'s fourth payment of $5,325.75 for mechanical equipment at Park-Presidio Jr. High School is listed for payment. linked by the name only, not checked
    16 Dec 1929outcome not readJournal 1929, p. 2341 ↗
  • Scott Co.'s third payment of $5,470.96 for plumbing at Park-Presidio Jr. High School is listed for payment.
    16 Dec 1929outcome not readJournal 1929, p. 2341 ↗
  • Finance Committee's resolution authorizes payment of claims to contractors and suppliers, including school construction work at Roosevelt, Park-Presidio and Geary Street schools.
    13 Jan 1930outcome not readJournal 1930, p. 125 ↗
  • Scott Co. is paid $2,746.20 for mechanical equipment at Roosevelt Junior High School. linked by the name only, not checked
    20 Jan 1930outcome not readJournal 1930, p. 150 ↗
  • Scott Co. is paid $2,373.60 for mechanical equipment for an addition to the Sunshine School. linked by the name only, not checked
    20 Jan 1930outcome not readJournal 1930, p. 150 ↗
  • Scott Co. is paid $2,529.75 for mechanical equipment at Park-Presidio Junior High School. linked by the name only, not checked
    20 Jan 1930outcome not readJournal 1930, p. 150 ↗
  • Scott Co. is paid $1,660.50 for mechanical equipment at Geary Street School.
    20 Jan 1930outcome not readJournal 1930, p. 150 ↗
  • Scott Co. is paid $3,735.75 for plumbing and gas-fitting at Roosevelt Junior High School. linked by the name only, not checked
    20 Jan 1930outcome not readJournal 1930, p. 150 ↗
  • Scott Co. is paid $5,648.52 for plumbing and gas-fitting at Park-Presidio Junior High School. linked by the name only, not checked
    20 Jan 1930outcome not readJournal 1930, p. 150 ↗
  • Scott Co. is paid $1,946.25 for mechanical equipment for an addition to Francisco Junior High School. linked by the name only, not checked
    20 Jan 1930outcome not readJournal 1930, p. 150 ↗
  • Finance Committee's payments for library books, school supplies and South Side High School work were passed for printing.
    20 Jan 1930passed first readingJournal 1930, p. 157 ↗
  • Payments to suppliers and contractors for public libraries and South Side High School were authorized and finally passed.
    27 Jan 1930passedJournal 1930, p. 200 ↗
  • A sixth payment of $4,075.39 to Scott Company for mechanical equipment at Roosevelt Junior High School is listed.
    10 Feb 1930outcome not readJournal 1930, p. 275 ↗
  • A sixth payment of $1,197.30 to Scott Company for plumbing at Roosevelt Junior High School is listed.
    10 Feb 1930outcome not readJournal 1930, p. 275 ↗
  • Board authorized payments to contractors and suppliers for school construction, a concert, and the Bernal Cut improvement.
    24 Feb 1930passedJournal 1930, p. 569 ↗
  • Final payment of $2,699.65 to Scott Company for mechanical equipment at Geary Street School was approved. linked by the name only, not checked
    3 Mar 1930outcome not readJournal 1930, p. 750 ↗
  • Resolution 32118 would fund construction of Ward Building F at the Relief Home Tract, totaling $132,008.42, from Hospital Bond funds.
    3 Mar 1930outcome not readJournal 1930, p. 735 ↗
  • Payment of $13,118.25 to Scott Company for mechanical equipment at Park-Presidio Junior High School. linked by the name only, not checked
    10 Mar 1930outcome not readJournal 1930, p. 802 ↗
  • Payment of $2,808.53 to Scott Company for plumbing at Park-Presidio Junior High School.
    10 Mar 1930outcome not readJournal 1930, p. 802 ↗
  • Scott Co. is paid $5,007.38 for seventh mechanical equipment payment at Roosevelt Junior High School. linked by the name only, not checked
    10 Mar 1930outcome not readJournal 1930, p. 803 ↗
  • Scott Company received final payment of $2,699.65 for mechanical equipment at Geary Street School. linked by the name only, not checked
    10 Mar 1930passedJournal 1930, p. 788 ↗
  • Scott Co. is paid $1,804.80 for seventh plumbing and gas-fitting payment at Roosevelt Junior High School. linked by the name only, not checked
    10 Mar 1930outcome not readJournal 1930, p. 803 ↗
  • Payment of $823.73 to Scott Co. for plumbing at Ward F building, Relief Home.
    7 Apr 1930outcome not readJournal 1930, p. 968 ↗
  • Expense claims for school construction and supplies, including Park-Presidio and Roosevelt Junior High payments, are authorized for payment; the vote continues.
    7 Apr 1930outcome not readJournal 1930, p. 967 ↗
  • Resolution authorizes payments to several claimants, including $4,037.96 to the California Academy of Sciences for Steinhart Aquarium.
    14 Apr 1930outcome not readJournal 1930, p. 991 ↗
  • First payment of $823.73 to Scott Co. for plumbing at Ward F of the Relief Home is listed. linked by the name only, not checked
    14 Apr 1930outcome not readJournal 1930, p. 993 ↗
  • Scott Co. claim of $595.80 for plumbing at Park-Presidio Junior High School listed for payment.
    12 May 1930outcome not readJournal 1930, p. 1180 ↗
  • Scott Co. claim of $1,008.94 for mechanical equipment at Roosevelt Junior High School listed for payment.
    12 May 1930outcome not readJournal 1930, p. 1180 ↗
  • Resolution proposed to authorize payment of many supply, school and water department claims, passed for printing.
    12 May 1930passed first readingJournal 1930, p. 1179 ↗
  • Scott Co. was paid $595.80 for plumbing and gas-fitting at Park-Presidio Junior High School.
    19 May 1930outcome not readJournal 1930, p. 1248 ↗
  • Scott Co. was paid $763.13 for mechanical equipment at Park-Presidio Junior High School. linked by the name only, not checked
    19 May 1930outcome not readJournal 1930, p. 1248 ↗
  • Scott Co. was paid $1,008.94 for mechanical equipment at Roosevelt Junior High School. linked by the name only, not checked
    19 May 1930outcome not readJournal 1930, p. 1248 ↗
  • Resolution to spend $585,295.62 from the special school tax on the third unit of Balboa High School was passed for printing.
    26 May 1930passed first readingJournal 1930, p. 1333 ↗
  • Scott Co. was paid $2,250 for the first payment of mechanical equipment at Relief Home. linked by the name only, not checked
    9 Jun 1930outcome not readJournal 1930, p. 1480 ↗
  • Scott Co. is paid $2,377.50 for plumbing and gasfitting at Roosevelt Junior High School.
    9 Jun 1930outcome not readJournal 1930, p. 1481 ↗
  • Approved $585,295.62 from the Special School Tax for the third unit of Balboa High School construction.
  • Scott Co. was paid $2,438.40 for the second payment of plumbing work at Relief Home. linked by the name only, not checked
    9 Jun 1930outcome not readJournal 1930, p. 1480 ↗
  • Scott Co. was paid $2,031.04 for the ninth payment of plumbing work at Park-Presidio Junior High School.
    9 Jun 1930outcome not readJournal 1930, p. 1480 ↗
  • Scott Co. was paid $3,699.57 for the tenth payment of mechanical equipment at Park-Presidio Junior High School.
    9 Jun 1930outcome not readJournal 1930, p. 1480 ↗
  • Scott Co. was paid $2,186.40 for the tenth payment of mechanical equipment at Roosevelt Junior High School.
    9 Jun 1930outcome not readJournal 1930, p. 1480 ↗
  • Scott Co. is paid $940.43 for plumbing on the addition to Francisco Junior High School. linked by the name only, not checked
    9 Jun 1930outcome not readJournal 1930, p. 1481 ↗
  • Scott Co. is paid $3,694.50 for mechanical equipment in the Francisco Junior High School addition. linked by the name only, not checked
    9 Jun 1930outcome not readJournal 1930, p. 1481 ↗
  • Scott Co. was paid $2,250 for mechanical equipment in ward building F at the Relief Home. linked by the name only, not checked
    16 Jun 1930outcome not readJournal 1930, p. 1517 ↗
  • Scott Co. was paid $2,031.04 for plumbing at Park-Presidio Junior High School.
    16 Jun 1930outcome not readJournal 1930, p. 1517 ↗
  • Scott Co. was paid $3,099.37 for mechanical equipment at Park-Presidio Junior High School. linked by the name only, not checked
    16 Jun 1930outcome not readJournal 1930, p. 1517 ↗
  • Scott Co. was paid $2,438.40 for plumbing and gasfitting in ward building F at the Relief Home. linked by the name only, not checked
    16 Jun 1930outcome not readJournal 1930, p. 1517 ↗
  • Oil tanks allowed for Scott Company at 19th and Treat Avenue
    16 Jun 1930outcome not readJournal 1930, p. 1540 ↗
  • Oil tanks allowed for Scott Company at 19th and Treat Avenue linked by the name only, not checked
    23 Jun 1930passedJournal 1930, p. 1567 ↗
  • Final payment of $1,343.40 to Scott Co. for equipment at Sunshine School is listed in the claims schedule. linked by the name only, not checked
    30 Jun 1930outcome not readJournal 1930, p. 1600 ↗
  • Payment of $1,086.19 to Scott Co. for plumbing at Ward F of Laguna Honda Home is listed. linked by the name only, not checked
    7 Jul 1930outcome not readJournal 1930, p. 1658 ↗
  • Claim of $3,825.00 to Scott Co. for plumbing at Roosevelt Junior High School is listed for payment. linked by the name only, not checked
    7 Jul 1930outcome not readJournal 1930, p. 1657 ↗
  • Claim of $4,942.31 to Scott Co. for plumbing at Park-Presidio Junior High School is listed for payment.
    7 Jul 1930outcome not readJournal 1930, p. 1657 ↗
  • Claim of $1,410.00 to Scott Co. for mechanical equipment at Park-Presidio Junior High School is listed for payment.
    7 Jul 1930outcome not readJournal 1930, p. 1657 ↗
  • Claim of $2,750.21 to Scott Co. for plumbing on the Francisco Junior High School addition is listed for payment.
    7 Jul 1930outcome not readJournal 1930, p. 1657 ↗
  • Claim of $1,447.05 to Scott Co. for mechanical equipment at Roosevelt Junior High School is listed for payment.
    7 Jul 1930outcome not readJournal 1930, p. 1657 ↗
  • Claim of $873.34 to Scott Co., Inc. for extra plumbing work at Park-Presidio Junior High School is listed for payment.
    7 Jul 1930outcome not readJournal 1930, p. 1657 ↗
  • Payment of $4,942.31 to Scott Co. for plumbing and gasfitting at Park-Presidio Junior High School.
    15 Jul 1930outcome not readJournal 1930, p. 1753 ↗
  • Payment of $1,410.00 to Scott Co. for mechanical equipment at Park-Presidio Junior High School.
    15 Jul 1930outcome not readJournal 1930, p. 1753 ↗
  • Scott Co. is listed for a final payment on mechanical equipment at Sunshine School; the outcome is not printed here. linked by the name only, not checked
    15 Jul 1930outcome not readJournal 1930, p. 1750 ↗
  • Payment of $2,750.21 to Scott Co. for plumbing and gasfitting at Francisco Junior High School addition. linked by the name only, not checked
    15 Jul 1930outcome not readJournal 1930, p. 1753 ↗
  • Payment of $3,825.00 to Scott Co. for plumbing and gasfitting at Roosevelt Junior High School. linked by the name only, not checked
    15 Jul 1930outcome not readJournal 1930, p. 1753 ↗
  • Payment of $1,447.05 to Scott Co. for mechanical equipment at Roosevelt Junior High School.
    15 Jul 1930outcome not readJournal 1930, p. 1753 ↗
  • Payment of $873.34 to Scott Co., Inc. for extra plumbing work at Park-Presidio Junior High School.
    15 Jul 1930outcome not readJournal 1930, p. 1753 ↗
  • Payment of $1,086.19 to Scott Co. for plumbing and gasfitting in Ward F of Laguna Honda Home.
    15 Jul 1930outcome not readJournal 1930, p. 1753 ↗
  • Proposed appropriation of $690,949.14 for construction of the Aptos Elementary Junior High School.
    21 Jul 1930outcome not readJournal 1930, p. 1810 ↗
  • Board appropriated $690,949.14 from the Special School Tax to pay construction contracts for Aptos Elementary Junior High School.
    28 Jul 1930passedJournal 1930, p. 1840 ↗
  • Passed for printing: a resolution authorizing city claims paid to suppliers and contractors, including $49,008.60 to MacDonald & Kahn for Balboa High School.
    4 Aug 1930passed first readingJournal 1930, p. 1913 ↗
  • Finance Committee resolution authorizes $3,866.04 to the California Academy of Sciences for July aquarium maintenance. linked by the name only, not checked
    11 Aug 1930outcome not readJournal 1930 ↗
  • Scott Company's eleventh payment of $1,401.52 for plumbing at Park-Presidio Junior High School is listed for payment. linked by the name only, not checked
    11 Aug 1930outcome not readJournal 1930, p. 1957 ↗
  • Scott Company's fourth payment of $3,947.10 for mechanical equipment at Francisco Junior High School is listed for payment.
    11 Aug 1930outcome not readJournal 1930, p. 1957 ↗
  • Scott Company's twelfth payment of $1,533.75 for mechanical equipment at Park-Presidio Junior High School is listed for payment.
    11 Aug 1930outcome not readJournal 1930, p. 1957 ↗
  • Scott Company's third payment of $1,605.08 for plumbing at Francisco Junior High School is listed for payment. linked by the name only, not checked
    11 Aug 1930outcome not readJournal 1930, p. 1957 ↗
  • A $1,533.75 twelfth payment was approved to Scott Company for mechanical equipment at Park-Presidio Junior High School.
    18 Aug 1930outcome not readJournal 1930, p. 1973 ↗
  • A $1,605.08 third payment was approved to Scott Company for plumbing at Francisco Junior High School. linked by the name only, not checked
    18 Aug 1930outcome not readJournal 1930, p. 1973 ↗
  • A $3,947.10 fourth payment was approved to Scott Company for mechanical equipment at Francisco Junior High School.
    18 Aug 1930outcome not readJournal 1930, p. 1973 ↗
  • A $1,401.52 eleventh payment was approved to Scott Company for plumbing at Park-Presidio Junior High School. linked by the name only, not checked
    18 Aug 1930outcome not readJournal 1930, p. 1973 ↗
  • Scott Co. received a final payment of $7,403 for plumbing and gasfitting work at Roosevelt Junior High School.
    25 Aug 1930outcome not readJournal 1930, p. 2018 ↗
  • Claim of $3,909.60 to Scott Co. for fifth payment on Francisco Junior High School equipment. linked by the name only, not checked
    8 Sep 1930outcome not readJournal 1930, p. 2103 ↗
  • Scott Co. was paid $502.15, fourth payment, for plumbing at ward F, Laguna Honda Home.
    8 Sep 1930outcome not readJournal 1930, p. 2104 ↗
  • Scott Co. was paid $1,616.25, second payment, for mechanical equipment at ward F, Laguna Honda Home.
    8 Sep 1930outcome not readJournal 1930, p. 2104 ↗
  • Scott Co. was paid $7,403 as the final payment for plumbing and gasfitting at Roosevelt Junior High School.
    8 Sep 1930outcome not readJournal 1930, p. 2085 ↗
  • Finance Committee recommends authorizing dozens of city payments to contractors, suppliers and funds for streets, sewers, schools and parks.
    15 Sep 1930outcome not readJournal 1930, p. 2154 ↗
  • Resolution 33121 authorizes payments to suppliers and contractors for school, street, sewer, water and Hetch Hetchy work.
    22 Sep 1930outcome not readJournal 1930, p. 2204 ↗
  • Final payment of $15,312.50 to Scott Co. for mechanical equipment at Park-Presidio Junior High School was listed. linked by the name only, not checked
    29 Sep 1930outcome not readJournal 1930, p. 2271 ↗
  • Final payment of $10,138.93 to Scott Co. for plumbing at Park-Presidio Junior High School was listed. linked by the name only, not checked
    29 Sep 1930outcome not readJournal 1930, p. 2271 ↗
  • Final payment of $13,081.98 to Scott Co. for mechanical equipment at Roosevelt Junior High School was listed.
    29 Sep 1930outcome not readJournal 1930, p. 2271 ↗
  • Scott Co. was paid $2,918.81 for second-stage plumbing work at Aptos School.
  • Scott Co. was paid $2,792.85 for third-stage mechanical equipment on the South Side High School third unit. linked by the name only, not checked
  • Scott Co. was paid $15,312.50 as final payment for mechanical equipment at Park-Presidio Junior High School. linked by the name only, not checked
    6 Oct 1930outcome not readJournal 1930, p. 2297 ↗
  • Scott Co. was paid $13,081.98 as final payment for mechanical equipment at Roosevelt Junior High School.
    6 Oct 1930outcome not readJournal 1930, p. 2297 ↗
  • Scott Co. was paid $1,710.75 for mechanical equipment in Ward Building F of the Relief Home.
  • Scott Co. was paid $2,733.90 for sixth-stage mechanical equipment at the Francisco Junior High addition. linked by the name only, not checked
  • Scott Co. was paid $10,138.93 as final payment for plumbing at Park-Presidio Junior High School. linked by the name only, not checked
    6 Oct 1930outcome not readJournal 1930, p. 2297 ↗
  • Scott Co. was paid $2,733.90 for the sixth payment on mechanical equipment at Francisco Junior High School. linked by the name only, not checked
    14 Oct 1930outcome not readJournal 1930, p. 2351 ↗
  • Scott Co. was paid $1,710.75 for mechanical equipment in Ward Building F at the Relief Home.
    14 Oct 1930outcome not readJournal 1930, p. 2351 ↗
  • Scott Co. was paid $2,918.81 for the second payment on plumbing at Aptos School.
    14 Oct 1930outcome not readJournal 1930, p. 2351 ↗
  • Scott Co. was paid $2,792.85 for the third payment on mechanical equipment at South Side Balboa High School. linked by the name only, not checked
    14 Oct 1930outcome not readJournal 1930, p. 2351 ↗
  • Final payment of $6,686.53 to Scott Company for plumbing at the Ward F Relief Home is listed in the claims schedule. linked by the name only, not checked
    3 Nov 1930outcome not readJournal 1930, p. 2477 ↗
  • Final payment of $2,583.00 to Scott Company for mechanical equipment at the Ward F Relief Home is listed in the claims schedule. linked by the name only, not checked
    3 Nov 1930outcome not readJournal 1930, p. 2477 ↗
  • Scott Company was paid $1,807.65 for mechanical equipment at Balboa High School.
    10 Nov 1930outcome not readJournal 1930, p. 2504 ↗
  • Claim of $2,583.00 listed for final payment to Scott Company for mechanical equipment at the Relief Home.
    12 Nov 1930outcome not readJournal 1930, p. 2541 ↗
  • Claim of $6,686.53 listed for final payment to Scott Company for plumbing at the Relief Home. linked by the name only, not checked
    12 Nov 1930outcome not readJournal 1930, p. 2541 ↗
  • $84,147.82 set aside for a city warehouse at Fifteenth and Harrison
    1 Dec 1930outcome not readJournal 1930, p. 2658 ↗
  • $84,147.82 set aside for a city warehouse at Fifteenth and Harrison
    8 Dec 1930outcome not readJournal 1930, p. 2685 ↗
  • Scott Company was listed for a fourth plumbing payment of $4,374.44 on Aptos Junior High School. linked by the name only, not checked
    8 Dec 1930outcome not readJournal 1930, p. 2701 ↗
  • Scott Company was listed for a fifth plumbing payment of $1,883.95 for Francisco Junior High School.
    8 Dec 1930outcome not readJournal 1930, p. 2701 ↗
  • Scott Company was listed for an eighth payment of $960.45 for mechanical equipment at Francisco Junior High School.
    8 Dec 1930outcome not readJournal 1930, p. 2701 ↗
  • Fifth payment of $1,487.55 to Scott Company for mechanical equipment at Balboa High School.
    22 Dec 1930outcome not readJournal 1930, p. 2777 ↗
  • A fifth payment of $1,834.10 to Scott Company for plumbing work at Aptos School was listed for payment. linked by the name only, not checked
    12 Jan 1931outcome not readJournal 1931, p. 75 ↗
  • A sixth payment of $5,415.00 to Scott Company for mechanical equipment at Balboa High School's third unit was listed for payment.
    12 Jan 1931outcome not readJournal 1931, p. 75 ↗
  • A $7,731.70 final payment went to Scott Company for mechanical equipment at Francisco Junior High School.
    19 Jan 1931outcome not readJournal 1931, p. 140 ↗
  • Claim of Scott Company for $5,415.00 for mechanical equipment at Balboa High School listed for payment.
    19 Jan 1931outcome not readJournal 1931, p. 127 ↗
  • A $4,285.05 final payment went to Scott Company for plumbing at Francisco Junior High School.
    19 Jan 1931outcome not readJournal 1931, p. 140 ↗
  • Fifth payment of $1,834.10 to Scott Company for plumbing work at Aptos School listed for payment.
    19 Jan 1931outcome not readJournal 1931, p. 126 ↗
  • Final payment of $7,731.70 to Scott Company for mechanical equipment at Francisco Junior High School.
    26 Jan 1931outcome not readJournal 1931, p. 193 ↗
  • Final payment of $4,285.05 to Scott Company for plumbing at Francisco Junior High School.
    26 Jan 1931outcome not readJournal 1931, p. 193 ↗
  • Sixth payment of $3,214.90 to Scott Company for plumbing at Aptos Junior High School is listed.
    9 Feb 1931outcome not readJournal 1931, p. 314 ↗
  • Payment of $3,214.90 to Scott Company for plumbing at Aptos Junior High School is listed on this claim schedule.
    24 Feb 1931outcome not readJournal 1931, p. 442 ↗
  • Scott Company was paid $2,122.50 for mechanical equipment at South Side (Balboa) High School. linked by the name only, not checked
    24 Feb 1931outcome not readJournal 1931, p. 443 ↗
  • Resolution adopted appropriating $417,200.72 from the 1929 Hospital Bond Fund to build Wards K and L at Laguna Honda Home.
    2 Mar 1931passedJournal 1931, p. 520 ↗
  • Scott Company was paid $1,009.81 for plumbing at Aptos Junior High School. linked by the name only, not checked
    9 Mar 1931outcome not readJournal 1931, p. 574 ↗
  • Scott Company was paid $1,661.25 for mechanical equipment at South Side (Balboa) High School.
    9 Mar 1931outcome not readJournal 1931, p. 574 ↗
  • $417,200 approved to build new wards at Laguna Honda Home
    9 Mar 1931passedJournal 1931, p. 567 ↗
  • Scott Company received $1,897.50 for mechanical equipment at the South Side (Balboa) High School.
    6 Apr 1931outcome not readJournal 1931, p. 748 ↗
  • Scott Company received $922.27 for plumbing work at Aptos Elementary (Junior High) School. linked by the name only, not checked
    6 Apr 1931outcome not readJournal 1931, p. 748 ↗
  • Scott Company was paid $1,897.50 for ninth-stage mechanical equipment at South Side (Balboa) High School.
    13 Apr 1931outcome not readJournal 1931, p. 772 ↗
  • Scott Company was paid $922.27 for eighth-stage plumbing at Aptos Elementary (Junior High) School. linked by the name only, not checked
    13 Apr 1931outcome not readJournal 1931, p. 772 ↗
  • Scott Co. is listed for $1,252.12 for plumbing and gas fitting at Aptos Junior High School.
    18 May 1931outcome not readJournal 1931, p. 999 ↗
  • Scott Company received a final payment of $15,023.05 for mechanical equipment at South Side High School. linked by the name only, not checked
  • Scott Company was paid $15,023.05 as final payment for equipment at South Side (Balboa) High School.
    8 Jun 1931outcome not readJournal 1931, p. 2159 ↗
  • Scott Company was paid $1,498.80 as a first payment for plumbing in wards K and L at Laguna Honda Home.
    8 Jun 1931outcome not readJournal 1931, p. 2176 ↗
  • Scott Company is listed for a $5,008.50 tenth payment on plumbing and gasfitting at Aptos School. linked by the name only, not checked
    22 Jun 1931outcome not readJournal 1931, p. 2218 ↗
  • Scott Company is listed for a $1,498.80 first payment on plumbing for wards at Laguna Honda Home.
    22 Jun 1931outcome not readJournal 1931, p. 2218 ↗
  • Scott Company's final payment of $9,164.13 for plumbing at Aptos Elementary Junior High School is listed for payment.
    20 Jul 1931outcome not readJournal 1931, p. 2463 ↗
  • Finance Committee resolution authorizes payments to fifteen suppliers and contractors for Hetch Hetchy construction work.
    27 Jul 1931outcome not readJournal 1931, p. 2517 ↗
  • A payment of $932.40 to Scott Company, Inc. for mechanical equipment at Laguna Honda Home is listed. linked by the name only, not checked
    10 Aug 1931outcome not readJournal 1931, p. 2605 ↗
  • Scott Company, Inc. was paid $932.40 for mechanical equipment in wards K and L at Laguna Honda Home. linked by the name only, not checked
    17 Aug 1931outcome not readJournal 1931, p. 2632 ↗
  • Third payment of $3,033.30 to Scott Company for mechanical equipment at Laguna Honda Home wards.
    10 Sep 1931outcome not readJournal 1931, p. 2767 ↗
  • A payment of $3,033.30 to Scott Company is for mechanical equipment at Laguna Honda Home wards K and L.
    21 Sep 1931outcome not readJournal 1931, p. 2803 ↗
  • Final payment of $1,809.25 to The Scott Company for plumbing work at the Central Warehouse was approved. linked by the name only, not checked
    28 Sep 1931passedJournal 1931, p. 2859 ↗
  • The city ordered payment of many construction and equipment claims for Laguna Honda Home, James Lick Junior High School, West Portal School and water works.
    13 Oct 1931outcome not readJournal 1931, p. 2958 ↗
  • Scott Company was paid $2,732.40 for mechanical equipment in wards K and L at Laguna Honda Home.
    26 Oct 1931outcome not readJournal 1931, p. 3004 ↗
  • A $1,778.70 fifth payment to Scott Company for mechanical equipment in wards K and L at Laguna Honda Home was listed on the schedule.
    16 Nov 1931outcome not readJournal 1931, p. 3101 ↗
  • $187,141 for the Health Center Building at Polk and Grove
    23 Nov 1931outcome not readJournal 1931, p. 3160 ↗
  • Board proposed appropriating $52,694.44 from the 1929 hospital bond fund for a second Tuberculosis Preventorium unit at Pulgas tunnel.
    23 Nov 1931outcome not readJournal 1931, p. 3160 ↗
  • Claim of $1,778.70 to Scott Company for fifth payment on mechanical equipment at Laguna Honda Home.
    23 Nov 1931outcome not readJournal 1931, p. 3148 ↗
  • Money set aside for the Health Center at Polk and Grove
    7 Dec 1931outcome not readJournal 1931, p. 3249 ↗
  • Scott Company gets an oil tank at Pacific Avenue and Fillmore Street linked by the name only, not checked
    7 Dec 1931outcome not readJournal 1931, p. 3281 ↗
  • Approved $52,694.44 from 1929 hospital bond funds for a second Tuberculosis Preventorium unit at Pulgas tunnel.
  • Scott Company gets an oil tank at Pacific Avenue and Fillmore Street
    14 Dec 1931passedJournal 1931, p. 3346 ↗
  • Adopted a resolution approving a $13,889.56 settlement of a claim by Scott Company of California against the City.
    5 Apr 1965passedJournal 1965, p. 175 ↗