  • The Board authorized payments from the General Fund to suppliers for the Relief Home, S. F. Hospital and an engine house.
    1912outcome not readJournal 1912, p. 852 ↗
  • Board authorized payments from city funds to contractors and suppliers for sewers, schools, a hospital, a viaduct and water works.
    1912outcome not readJournal 1912, p. 676 ↗
  • Board accepted State Construction Company's $34,000 bid for ninth series sewer bonds.
    15 Jul 1912passedJournal 1912, p. 601 ↗
  • A resolution on authorizations was moved by Jennings and passed for printing; its text continues on the next page.
    23 Sep 1912outcome not readJournal 1912, p. 829 ↗
  • Board allowed a $6,905.03 third payment to State Construction Co. for sewers on Oak and Stanyon streets.
    21 Oct 1912passedJournal 1912, p. 947 ↗
  • Board authorizes payments from city bond funds to contractors and landowners, including Fire Department engines and San Francisco Hospital work.
    11 Nov 1912outcome not readJournal 1912, p. 1018 ↗
  • Seagrave Company paid $14,562 for fire hose wagons
    20 Nov 1912outcome not readJournal 1912, p. 1053 ↗
  • A resolution authorizing expenditures from named accounts to named claimants was taken up; its outcome continues on the next page.
    20 Jan 1913outcome not readJournal 1913, p. 51 ↗
  • F. Rolandi paid $11,044 for the Geary Street car barn linked by the name only, not checked
    10 Feb 1913outcome not readJournal 1913, p. 144 ↗
  • F. Rolandi paid $11,044 for the Geary Street car barn
    18 Feb 1913outcome not readJournal 1913, p. 169 ↗
  • State Construction Company allowed blasting at the foot of Pierce Street linked by the name only, not checked
    3 Mar 1913outcome not readJournal 1913, p. 399 ↗
  • Resolution authorizing 1913 payments from bond funds for sewers, a police station, street lighting and Civic Center land was passed for printing.
    10 Mar 1913passed first readingJournal 1913, p. 233 ↗
  • Resolution authorizes payments to several contractors and claimants for library books, school work, water mains and a pumping station. linked by the name only, not checked
    17 Mar 1913outcome not readJournal 1913 ↗
  • State Construction Company allowed blasting at the foot of Pierce Street linked by the name only, not checked
    18 Apr 1913outcome not readJournal 1913, p. 377 ↗
  • State Construction Company given ninety more days on Pierce Street linked by the name only, not checked
    18 Apr 1913passedJournal 1913, p. 378 ↗
  • Bausch & Lomb paid $624.50 for microscopes at Lowell High School
    6 Jun 1913outcome not readJournal 1913, p. 523 ↗
  • State Construction given thirty more days on the Pierce Street sewer
    18 Aug 1913outcome not readJournal 1913, p. 834 ↗
  • State Construction Company given 30 more days on Pierce Street sewer
    15 Sep 1913outcome not readJournal 1913, p. 913 ↗
  • Newsom, Wold & Kohn paid $16,725 for Polytechnic High School linked by the name only, not checked
    15 Sep 1913outcome not readJournal 1913, p. 905 ↗
  • Newsom, Wold & Kohn paid $16,725 for Polytechnic High School linked by the name only, not checked
    29 Sep 1913passedJournal 1913, p. 926 ↗
  • State Construction Company given 30 more days on Pierce Street sewer linked by the name only, not checked
    6 Oct 1913passedJournal 1913, p. 987 ↗
  • Commary-Peterson paid $8,995 for building Engine House No. 24 linked by the name only, not checked
    22 Dec 1913passedJournal 1913, p. 1268 ↗
  • Board authorized payments to contractors, suppliers and utilities for street paving, water, sewers, schools and police needs.