All decisions
42 Board decisions about Sunset Scavenger, in date order. Each links to its printed page.
- Sunset Scavenger allowed a stable for 50 horses on Mariposa Street linked by the name only, not checked
- Sunset Scavenger allowed a stable for 50 horses on Mariposa Street linked by the name only, not checked
- Scavenger service contract for the School Department was awarded to three firms at $699 monthly.
- Fire Committee recommended revocable permits for seven oil tanks and one boiler; the resolutions were passed for printing.
- Sunset Scavenger gets a garage on Hampshire Street near Mariposa linked by the name only, not checked
- Traung Label gets a 90 horsepower boiler at 640 Battery Street
- Board accepted, at no cost, a sewer easement from the Sunset Scavenger Company.
- The city bought sewer easements from Sunset Scavenger Company for $8,400 for the Candlestick Point sewer tunnel, and adopted it.
- Sunset Scavenger land for Candlestick Park roads sent to committee
- City buys $147,075 land from Sunset Scavenger for Candlestick roads
- Lease sought from Sunset Scavenger for park land at Lathrop Avenue linked by the name only, not checked
- $100,000 paid to Sunset Scavenger for open space near Tocoloma Avenue linked by the name only, not checked
- Motion for a Budget Analyst audit of four garbage collection companies was tabled.
- Budget Analyst to review garbage companies' audits and the 2001 residential rate increase, approved as amended.
- Supervisor Yee requested a hearing on the 2001 garbage rate increase proposal from three collection companies, sent to the Rules Committee. linked by the name only, not checked
- Supervisor Yee requested a hearing on 2001 garbage rate increases proposed by three haulers, sent to Rules Committee.
- Proposed fourth amendment to Sunset Scavenger's hauling contract, up to $10.48M total, sent to Budget and Finance Committee.
- Sunset Scavenger's hauling contract amended a fifth time, capped at $10,650,000, adopted.
- A fourth amendment to the Sunset Scavenger hauling contract, up to $10,480,000, was sent to Budget and Finance Committee.
- Fourth amendment to Sunset Scavenger Company's hauling contract, up to $10.5M, was sent to the Budget and Finance Committee.
- Sunset Scavenger Company's hauling contract amended, total pay capped at $10.65M, was adopted.
- Board adopted a resolution approving a fourth amendment to Sunset Scavenger's hauling contract, up to $10.5M.
- Sunset Scavenger hauling contract raised to $10.5M
- Sunset Scavenger Company's hauling contract was amended by a Fourth Amendment, with total compensation capped at $10,480,000, and adopted.
- Sunset Scavenger's hauling contract is raised to a maximum of $10,650,000 and was adopted. linked by the name only, not checked
- Eighth amendment adding $1.3 million to Sunset Scavenger Company's sludge hauling contract was sent to Budget and Finance Committee. linked by the name only, not checked
- Sunset Scavenger Company's sludge hauling contract with the city was increased by $1.3 million to $12,415,000.
- Sunset Scavenger Company's sludge hauling contract with the city rises by $1.3M to $12,415,000; sent to committee.
- Sunset Scavenger sludge hauling contract would rise to $12.4M
- Proposed: higher fees for taxi and limo permits. linked by the name only, not checked
- A proposed resolution would amend a contract; its outcome is not shown on this page.
- Eleventh amendment extending Sunset Scavenger Company's sludge hauling contract to May 2009 with $3 million more was sent to committee.
- Sunset Scavenger Company's sludge hauling contract extended three months to May 31, 2008, adding $750,000 in compensation.
- Sunset Scavenger Company's sludge hauling contract was extended to April 2009 and increased by $3 million.
- Proposed resolution would add $750,000 to Sunset Scavenger's sludge hauling contract, raising it to $13,615,000; sent to committee.
- Sunset Scavenger Company's sludge-hauling contract was extended three months and raised by $750,000 to $13,615,000.
- Proposed $3 million increase to Sunset Scavenger's sludge hauling contract, extending it to May 31, 2009; sent to Budget Committee.
- Eleventh amendment to Sunset Scavenger Company's sludge hauling contract adopted, adding $3M and extending the term 11 months.
- Supervisors amended and continued to December 8, 2009 the vacation of part of Channel Street, exchanged with Recology.
- Channel Street closure and Recology land swap taken up
- Channel Street between 7th and Carolina Streets vacated and exchanged with Recology Properties, passed as amended.
- Channel Street portion to be swapped with Sunset Scavenger