23 Board decisions about Transbay Joint Powers Autho…, in date order. Each links to its printed page.

  • Supervisor Daly proposed releasing and reappropriating Planning Department funds, including $237,000 for the Transbay Joint Powers Authority; sent to Finance Committee.
  • Supervisor Daly's ordinance moves Planning funds to a Transbay Terminal study and related costs, referred to the Finance Committee.
  • Up to $171M federal loan from the U.S. Department of Transportation to the Transbay Joint Powers Authority approved for the Transbay Transit Center.
  • A public hearing was scheduled on a $171,000,000 federal loan to the Transbay Joint Powers Authority for the transit center.
    2009outcome not readBoard minutes 2009 ↗
  • Sponsor Daly proposed sitting as a Committee of the Whole on November 24, 2009 to hear the $171,000,000 Transbay loan.
  • The Board approved a motion to sit as a Committee of the Whole on a $171,000,000 loan to the Transbay Joint Powers Authority.
  • Resolution approving a $171M loan from the U.S. Department of Transportation to the Transbay Joint Powers Authority; assigned to the Board.
    17 Nov 2009referredBoard minutes 2009 ↗
  • A loan of up to $171,000,000 from the U.S. Department of Transportation to the Transbay Joint Powers Authority was approved for the Transbay Transit Center.
  • Board sat as a Committee of the Whole and approved a $171M federal transport loan to the Transbay Joint Powers Authority.
  • City seeks $26M in bonds for 121 Golden Gate Avenue
    12 Jul 2011outcome not readBoard minutes 2011, p. 621 ↗
  • Up to $3.3 million for Transbay transit center work; vote not shown.
    2 Aug 2011outcome not readBoard minutes 2011, p. 702 ↗
  • Board approved a first amendment to a contract with the Transbay Joint Powers Authority for up to $3,280,677 in transit center services.
  • Lech Walesa Street proposed to become Dr. Tom Waddell Place
  • Transbay Transit Center management contract raised to $5.4 million
  • Transbay Transit Center program contract raised to $5.4 million.
  • Public Utilities Commission to supply power to Transbay Project linked by the name only, not checked
  • Electric service deal for Transbay project; vote not shown here.
    11 Mar 2014outcome not readBoard minutes 2014, p. 152 ↗
  • City land deal for Transbay parcels linked to $171M loan; still pending.
  • Transbay property deal and $171 million loan hearing proposed for Dec 9.
  • Transbay transit agency may borrow $171 million from [name withheld]; in committee.
  • A motion approved, with no subject on this page
  • Hearing on $171 million Transbay loan from [name withheld]; no vote here.
    8 Jan 2015outcome not readBoard minutes 2014, p. 867 ↗
  • Transbay affordable-housing site deal and transit-center financing approved