  • Payments for blackboards and heating work at Mission Grammar and Commercial High schools passed for printing. linked by the name only, not checked
    1910passed first readingJournal 1910, p. 306 ↗
  • Board approved $17,964.41 in payments to contractors for heating, steel, flooring and blackboards at several city schools. linked by the name only, not checked
  • School building contractors would be paid $17,004.41 for work at several San Francisco schools, passed for printing.
    1910passed first readingJournal 1910, p. 700 ↗
  • Payments of about $2,544 for furniture for Mission Grammar School were authorized, pending final action on the next page. linked by the name only, not checked
    10 Feb 1910outcome not readJournal 1910, p. 164 ↗
  • Payments totalling $19,461.25 from the school bond fund for school building work and desks were proposed for printing.
    28 Mar 1910passed first readingJournal 1910, p. 322 ↗
  • School bond funds of $15,947.40 paid for blackboards and heating work at Mission Grammar and Commercial High schools. linked by the name only, not checked
    28 Mar 1910passedJournal 1910, p. 318 ↗
  • Payments totalling $19,461.25 from the school construction bond fund to contractors for work at several schools were passed. linked by the name only, not checked
    13 Apr 1910passedJournal 1910, p. 345 ↗
  • Payments of $1,075.18 and $2,325 authorized for desks at Sutro School and wood floors at Sheridan School. linked by the name only, not checked
    27 Jun 1910outcome not readJournal 1910, p. 649 ↗
  • Payments to contractors for school building work, including J. J. Connolly and Hansbrough Bros. Co., were listed from the School Construction Account. linked by the name only, not checked
    8 Aug 1910outcome not readJournal 1910, p. 794 ↗
  • Payments totaling $4,080.20 from the school construction account for furniture at Garfield and Clement Schools. linked by the name only, not checked
    29 Aug 1910passedJournal 1910, p. 855 ↗
  • Payments of about $4,080 for furniture for Garfield and Clement Schools were finally passed. linked by the name only, not checked
    6 Sep 1910passedJournal 1910, p. 874 ↗
  • Proposed payments to contractors for work and supplies at several San Francisco schools, including Spring Valley School.
    12 Sep 1910outcome not readJournal 1910, p. 786 ↗
  • Payments for school furniture from the School Construction Account were proposed; the outcome is on the next page.
    21 Nov 1910outcome not readJournal 1910, p. 1123 ↗
  • A resolution proposed paying five contractors and suppliers a total of $13,122.10 for work on several San Francisco schools.
    12 Dec 1910outcome not readJournal 1910, p. 1193 ↗
  • Payments made for school desks and building work
    19 Dec 1910passedJournal 1910, p. 1209 ↗
  • Resolution proposed to pay $4,387.13 to two suppliers for school desks, tables and a blackboard.
    27 Dec 1910outcome not readJournal 1910, p. 1250 ↗
  • Resolution proposed paying $2,093.82 for chairs and desks supplied to Grattan School. linked by the name only, not checked
    1911outcome not readJournal 1911 ↗
  • Payments of about $2,476 proposed to C. F. Weber & Co. and Whitaker & Ray Wiggin Co. for chairs and desks for Cleveland and Denman Schools.
    1911outcome not readJournal 1911 ↗
  • Resolution proposed to pay $1,422.66 to Whitaker & Ray-Wiggin Co. for desks at Hancock Grammar School. linked by the name only, not checked
    1911outcome not readJournal 1911 ↗
  • Payments totalling $2,158.50 to Whitaker & Ray-Wiggin Co. and Joost Bros. for blackboards and hardware at two schools.
    1911outcome not readJournal 1911 ↗
  • A resolution to pay Whitaker & Ray-Wiggin Co. $1,198.50 for blackboards at Jean Parker School was passed for printing.
    1911passed first readingJournal 1911 ↗
  • Board paid Whitaker & Ray-Wiggin Co. a total of $2,659.73 for chairs and desks at two schools.
  • Proposed payments totalling $8,108.71 from the school construction account for equipment and fees at several city schools.
    1911outcome not readJournal 1911 ↗
  • City approved $2,462.76 from the school construction account for furniture at Hancock Grammar and Lakeview Schools. linked by the name only, not checked
  • Proposed $1,133.88 payment to Whitaker & Ray-Wiggin Co. for desks at Peabody School, passed for printing.
    1911passed first readingJournal 1911 ↗
  • Payments of $4,863 approved for desks and heating systems at four San Francisco schools, paid from the school construction account.
    1911passed first readingJournal 1911 ↗
  • Payments from the school construction account went to suppliers of furniture and typewriters for several city schools. linked by the name only, not checked
    1911outcome not readJournal 1911 ↗
  • Board approved $4,387.13 in school furniture and equipment payments to two suppliers.
    9 Jan 1911passedJournal 1911 ↗
  • City paid $8,121.98 to four suppliers for desks, clocks and typewriters for three city schools. linked by the name only, not checked
    23 Jan 1911passedJournal 1911 ↗
  • Payments of $4,863.00 approved for desks and heating systems at four San Francisco schools.
    17 Apr 1911passedJournal 1911 ↗
  • Resolution paying $2,158.50 for school blackboards and hardware was recommitted to the Finance Committee.
    22 May 1911referredJournal 1911 ↗
  • Payments totalling $2,158.50 for blackboards and hardware at two schools were indefinitely postponed. linked by the name only, not checked
    29 May 1911outcome not readJournal 1911 ↗
  • Payment of $1,198.50 to Whitaker & Ray-Wiggin Co. for blackboards at the Jean Parker School was approved.
    29 May 1911passedJournal 1911 ↗
  • Payments for chairs and desks for a school building are proposed from the School Construction Account. linked by the name only, not checked
    28 Aug 1911outcome not readJournal 1911 ↗
  • Payments totalling $4,117.72 approved for desks and chairs at Adams Cosmopolitan School and Franklin School construction.
    2 Oct 1911outcome not readJournal 1911 ↗
  • Payments approved for desks at Adams Cosmopolitan School and a progress payment on Franklin School, totalling $4,117.72.
    9 Oct 1911passedJournal 1911 ↗
  • Payments totalling $7,186.58 approved for desks, chairs and tables at Peabody, Jean Parker, Visitacion Valley and Franklin schools.
    6 Nov 1911passedJournal 1911 ↗
  • Two suppliers were paid $2,093.82 in total for chairs and desks for the Grattan School. linked by the name only, not checked
    26 Dec 1911passedJournal 1911 ↗
  • Board passed for printing a resolution authorizing many city payments for schools, the hospital, sewers, fire protection and parks. linked by the name only, not checked
    1912passed first readingJournal 1912, p. 169 ↗
  • Expenditures for plumbing, paving, electrical work and furniture at several named schools were passed for printing.
    13 Feb 1912passed first readingJournal 1912, p. 125 ↗
  • O. C. Holt paid $7,410 for work on John Swett School
    26 Feb 1912outcome not readJournal 1912, p. 148 ↗
  • Resolution 9340 authorizes bond-funded construction payments for Polytechnic, Lincoln, Lowell and other schools, the Hall of Justice and San Francisco Hospital. linked by the name only, not checked
    11 Mar 1912outcome not readJournal 1912, p. 175 ↗
  • City sets aside $2,500 for further Civic Center plans linked by the name only, not checked
    19 Aug 1912passed first readingJournal 1912, p. 683 ↗
  • Proposed payments from bond funds for schools, a hospital, Civic Center land and water works, sent to print.
    1913passed first readingJournal 1913, p. 61 ↗
  • Board passed for printing a resolution authorizing many city payments to contractors, utilities and suppliers.
    6 Jan 1913passed first readingJournal 1913, p. 9 ↗
  • Expenditures from the City Hall-Civic Center Improvement Fund authorized to named plaintiffs; list continues on the next page.
    13 Jan 1913outcome not readJournal 1913, p. 29 ↗
  • Bond-fund payments were authorized to contractors, landowners and suppliers for school, hospital, water and fire work. linked by the name only, not checked
    27 Jan 1913passedJournal 1913, p. 76 ↗
  • Authorizes payments from bond funds to several claimants, including water supply studies, Lowell High School supplies, Geary Street paving and streetcars.
    24 Feb 1913outcome not readJournal 1913, p. 187 ↗
  • G. E. Grunsky paid $1,000 to investigate the water supply
    3 Mar 1913outcome not readJournal 1913, p. 203 ↗
  • Whitaker & Ray-Wiggin Co. was granted a 45-day extension to install slate blackboards at Girls' High School.
    13 May 1913passedJournal 1913, p. 460 ↗
  • $12,000 set aside to restore surveys in the Excelsior and Mission
    14 Jul 1913outcome not readJournal 1913, p. 747 ↗
  • Final passage of Resolution 10288 authorizing city payments to contractors, suppliers and claimants from bond and general funds.
    21 Jul 1913passedJournal 1913, p. 760 ↗
  • Another payment to United States Steel for City Hall steel linked by the name only, not checked
    14 Oct 1913outcome not readJournal 1913, p. 1004 ↗
  • Payments to contractors, utilities and suppliers for City Hall, schools, fire and water work were finally approved from city funds.
    27 Oct 1913passedJournal 1913, p. 1083 ↗
  • Board authorizes payment of many city claims from bond and general funds, covering schools, street paving, sewers and water.
    1914outcome not readJournal 1914, p. 743 ↗
  • Carnahan & Mulford paid $9,909 for building the Columbus School
    12 Jan 1914outcome not readJournal 1914, p. 40 ↗
  • Many city claims were authorized, including sewer, school, library juror and street repair payments to contractors and suppliers.
    9 Jul 1914passedJournal 1914, p. 768 ↗
  • Southern Pacific paid $23,590.85 to haul City Hall's stone linked by the name only, not checked
    21 Dec 1914outcome not readJournal 1914, p. 1463 ↗
  • The Board authorized payments for Marshall School furnishings and electric work, Geary Street Car Barn extension, and United Railroads and Pacific Gas and Electric current bills.
    4 Jan 1915outcome not readJournal 1915 ↗
  • Decker Electric paid $859 for electrical work at Marshall School linked by the name only, not checked
    4 Jan 1915outcome not readJournal 1915 ↗
  • Federal Construction paid $2,469.32 for the Foerster Street storm sewer linked by the name only, not checked
    26 Jul 1915passed first readingJournal 1915, p. 856 ↗
  • $2,469.32 paid Federal Construction for the Foerster Street storm sewer linked by the name only, not checked
    2 Aug 1915outcome not readJournal 1915, p. 875 ↗
  • Sunset Construction allowed ninety days of blasting on Kansas Street linked by the name only, not checked
    11 Oct 1915passedJournal 1915, p. 1095 ↗
  • Board authorizes payments to contractors and suppliers for libraries, schools, City Hall, sewers, streets and transit repairs.
    19 Oct 1915outcome not readJournal 1915, p. 1109 ↗
  • The Board passed for printing authorizations for payments to contractors and suppliers for school, Hetch Hetchy water and park work.
    16 Apr 1917passed first readingJournal 1917, p. 489 ↗
  • The Board authorized payments totalling tens of thousands of dollars for schools, hospitals, water works, sewers and charities, passed for printing.
    16 Apr 1917passed first readingJournal 1917, p. 490 ↗
  • Expenditures totalling $60,174.68 were authorized for 20 payments to contractors and suppliers for schools, hospitals, water and parks.
    23 Apr 1917passedJournal 1917, p. 508 ↗