Organisation · organisation
Youdall Construction Company
An organisation in 34 Board decisions, 1926–1931.
34Board decisions about it
1926–1931first and last decision
In short
- 19 Jul 1926Youdall Construction allowed blasting for the Sunset Tunnel linked by the name only, not checked
- 8 Aug 1927Youdall Construction given 90 more days on the Duboce Tunnel linked by the name only, not checked
- 1 Mar 1928Youdall Construction given sixty more days on the Sunset Tunnel linked by the name only, not checked
Who appears together
Lines show who appears in the same decisions. It doesn't mean they made a deal.
Organisations
Places
- Duboce Avenamed in 12
- Bay Shore Blvdnamed in 4
- Franklin Stnamed in 4
Left out: Recorder Printing and Publishing Company, San Francisco News Company, paid to print the Board's legal notices, not a party.
More from the records
Who was paid · 76 organisations
| Leonard F Youdall and R G Clifford Youdall Construction Company | 12 decisions |
| Ingersoll Rand Company of California | 7 decisions |
| American Building Maintenance Company | 7 decisions |
| Santa Cruz Portland Cement Company | 6 decisions |
| Gaffney & Luce | 5 decisions |
| Standard Oil Company | 4 decisions |
How many decisions pay each one; amounts are not shown until a person checks them.
Votes · 8 roll calls
yes 101no 0absent 40
8 printed roll calls; 8 were unanimous.
Decisions, by type
| resolution | 25 |
| claim | 9 |
Decisions, by outcome
| passed | 6 |
| passed first reading | 4 |
24 decisions have no outcome read yet.
All 34 decisions · in date order
- Youdall Construction allowed blasting for the Sunset Tunnel linked by the name only, not checked
- Youdall Construction allowed blasting for the Sunset Tunnel linked by the name only, not checked
- Youdall Construction allowed to blast for the Sunset tunnel linked by the name only, not checked
- Youdall Construction allowed to blast for the Sunset tunnel linked by the name only, not checked
- Youdall Construction Co. was paid $34,801.05 as the fourth payment on the Duboce-Sunset Tunnel. linked by the name only, not checked
- Sixth payment of $56,515.50 to Youdall Construction Co. for building a tunnel under Buena Vista Park.
- Youdall Construction given 90 more days on the Duboce Tunnel linked by the name only, not checked
- A claim of $88,676.70 was listed for the 14th payment to Youdall Construction Co. for the Duboce avenue-Sunset Tunnel.
- A claim of $3,070.12 was listed for payment to Youdall Construction Co. for extra work on the Duboce avenue-Sunset Tunnel.
- Youdall Construction Co. was paid $3,070.12 for extra work on the Duboce avenue-Sunset Tunnel.
- Youdall Construction Co. was paid $88,676.70, its fourteenth payment for building the Duboce avenue-Sunset Tunnel.
- Youdall Construction given 45 more days on the Buena Vista tunnel linked by the name only, not checked
Pages that mention it
Printed pages of the decisions on this page.
Journal 1926
Journal 1927
Journal 1929
Journal 1931