All decisions
26 Board decisions about Chinatown Branch Library, in date order. Each links to its printed page.
- Board accepts a $204,500 gift from the Library Foundation to relocate the Chinatown Branch Library during renovation.
- Lease proposed at 445 Grant Avenue for the Chinatown Branch Library
- 445 Grant Avenue leased for the Chinatown Branch Library
- Supervisor Kennedy's hearing on the Chinatown Branch Library project was referred to the Economic Vitality committee for December 13, 1994.
- Longer lease for the Chinatown Branch Library sent to committee
- City to extend the Chinatown Branch Library's lease on Grant Avenue
- A resolution commending the reopening of the Chinatown Branch Library was referred to the Board for adoption on June 3, 1996.
- A resolution commending [name withheld] for her work for the Chinatown Branch Library was referred to the Board for June 3, 1996.
- Resolution commending [name withheld] for fundraising and years of service to the Chinatown Branch Library, adopted as amended.
- Resolution commending the reopening of the Chinatown Branch Library and declaring a Chinatown Branch Library Day, adopted.
- Proposed ordinance would spend $205,537 of library bond earnings to air-condition the Chinatown Branch Library; sent to committee.
- Newsom proposed appropriating $205,537 of library bond interest for Chinatown Branch Library air conditioning, sent to committee.
- Proposed amendment to settlement of Commercial Interiors lawsuit over Chinatown Branch Library, $285,016.13, sent to Audit committee.
- Proposed amendment to a $285,016.13 settlement with Commercial Interiors Construction over the Chinatown Branch Library project; sent to committee.
- Proposed $205,537 appropriation would install air conditioning at the Chinatown Branch Library; passed on first reading.
- Board passed on first reading $205,537 for air conditioning and renovations at the Chinatown Branch Library.
- Public Library receives $205,537 in bond interest to air-condition the Chinatown Branch Library, ordinance finally passed.
- Public Library funds of $205,537 were appropriated to air-condition the Chinatown Branch Library, and the ordinance was finally passed.
- Chinatown Branch Library settlement pulled from the consent agenda
- Tabling of an amendment to the Commercial Interiors lawsuit settlement over the Chinatown Branch Library project.
- City Attorney proposed amending a 1998 settlement of $285,016.13 with Commercial Interiors Construction over Chinatown Branch Library work; sent to committee.
- Proposed amendment to Ordinance 262-98 settling Commercial Interiors' Chinatown Branch Library lawsuit for $285,016.13, referred to committee.
- Settlement of Commercial Interiors' lawsuit over the Chinatown Branch Library project, $285,016.13, passed on first reading.
- Proposed ordinance amends a $285,016.13 settlement with Commercial Interiors Construction over the Chinatown Branch Library project; passed on first reading.
- Ordinance passed amending a settlement with Commercial Interiors Construction, Inc. over the Chinatown Branch Library, paying $285,016.13 and releasing retention claims.
- Ordinance amends earlier settlement with Commercial Interiors Construction, Inc. over Chinatown Branch Library work, for $285,016.13; passed final.