Qipudata
San Francisco · v0.7.1
qipu data›San Francisco›Projects›Calaveras Dam
Project

Calaveras Dam

A project in 46 Board decisions, 1971–2019.

46Board decisions about it
1971–2019first and last decision

In short

  • 16 Mar 2010
    Proposed limit on a consultant's indemnification liability for the Calaveras Dam Replacement Project was sent to committee.

Who appears together

PeopleOrganisationsSean Elsberndproposed 5John Avalosproposed 2URS Corporationnamed in 8Public UtilitiesCommissionnamed in 1together in 2Calaveras Dam

Lines show who appears in the same decisions. It doesn't mean they made a deal.

People

Organisations

More from the records

Who was paid · 2 organisations
URS Corporation8 decisions
Public Utilities Commission1 decision

How many decisions pay each one; amounts are not shown until a person checks them.

Votes · 18 roll calls
yes 164no 0absent 33

18 printed roll calls; 18 were unanimous.

Decisions, by type
resolution20
ordinance5
contract5
motion4
hearing2
claim2
Decisions, by outcome
passed23
pending11
referred9

3 decisions have no outcome read yet.

All 46 decisions · in date order
  • $428,000 to rebuild Market Street water mains, $95,000 for
    6 Jul 1971outcome not readJournal 1971, p. 487 ↗
  • Water money for [name withheld] and Sunol plant
    6 Nov 1973passedJournal 1973, p. 787 ↗
  • Proposed resolution would let the Public Utilities Commission sign a $12M engineering contract with URS Corporation for [name withheld] replacement.
  • Public Utilities Commission may pay URS Corporation up to $12,000,000 for engineering on the [name withheld] replacement.
  • Up to $12M for engineers on [name withheld]; not yet decided.
    9 Aug 2005pendingBoard minutes 2005 ↗
  • Public Utilities Commission may sign a $2,000,000 engineering services agreement with URS Corporation for [name withheld] replacement.
  • The Public Utilities Commission's engineering contract with URS Corporation for [name withheld] rose by $9,689,663 to $24,000,000.
  • Proposed limit on a consultant's indemnification liability for the Calaveras Dam Replacement Project was sent to committee.
  • Resolution proposed to let [name withheld] a construction management contract for up to $38,000,000 on the [name withheld] replacement; sent to Budget Committee.
  • Up to $38 million hired to oversee [name withheld] rebuild
  • [name withheld] replacement environmental sign-off sent to committee.
  • Hearing sought on releasing $330.5 million for [name withheld].

Open the full list of 46

Pages that mention it · 9

Scanned pages whose text has the name: 9 Board journal pages.