Project

Connector Project

A project in 9 Board decisions, 2020–2024.

9Board decisions about it
2020–2024first and last decision

In short

More from the records

Decisions, by type
resolution9
Decisions, by outcome
passed3

6 decisions have no outcome read yet.

All 9 decisions · in date order
  • Airport project management contract sent to the budget committee
    5 May 2020outcome not readBoard minutes (PDF) ↗
  • $17,250,000 airport project management contract with PGH [name withheld] proposed
    23 Jun 2020outcome not readBoard minutes (PDF) ↗
  • Airport connector management contract raised to $17.25M approved
    23 Jun 2020passedBoard minutes (PDF) ↗
  • $10,600,000 more for PGH [name withheld] on the airport connector project
    10 Jan 2023outcome not readBoard minutes (PDF) ↗
  • Airport connector project-management contract raised to $25 million approved
    7 Feb 2023passedBoard minutes (PDF) ↗
  • $7,750,000 more sought for PGH [name withheld] on the airport connector
    7 Feb 2023outcome not readBoard minutes (PDF) ↗
  • Airport connector project management contract raised to $45,400,000, referred
    30 Jan 2024outcome not readBoard minutes (PDF) ↗
  • $45,400,000 sought for PGH [name withheld] on the airport Courtyard 3 Connector
    2 Apr 2024outcome not readBoard minutes (PDF) ↗
  • Airport project manager PGH [name withheld] contract raised to $45.4 million
    2 Apr 2024passedBoard minutes (PDF) ↗