All decisions
16 Board decisions about Davies Symphony Hall, in date order. Each links to its printed page.
- Agreement between the Performing Arts Center sponsors and War Memorial for interim operation of [name withheld] Hall approved.
- Streets closed for parking at the [name withheld] Symphony Hall gala
- Streets closed for parking at the [name withheld] Symphony Hall gala
- Molinari proposed a letter asking the War Memorial why [name withheld] Symphony Hall has no flag poles.
- Resolution amends the 1921 War Memorial Trust to move the San Francisco Symphony's rights to [name withheld] Symphony Hall, adopted.
- A declaration of emergency to replace a glass window at [name withheld] Hall was put before the Board.
- Emergency approval of $35,000 to replace a glass window at [name withheld] Hall, adopted.
- Taxi zones adopted on Grove Street for [name withheld] Symphony Hall performances
- Taxicab stands established and rescinded on several streets, including near [name withheld] Symphony Hall on Grove Street, adopted.
- Taxi zone on Grove Street only during [name withheld] Symphony Hall shows
- Revenue bonds for an acoustical renovation of [name withheld] Symphony Hall for the San Francisco Symphony were sent to Finance Committee.
- Board authorizes up to $10M in revenue bonds to fund an acoustical renovation of [name withheld] Symphony Hall for the San Francisco Symphony.
- A long-term PG&E solar interconnection agreement for [name withheld] Symphony Hall at 201 Van Ness Avenue was sent to the Budget Committee.
- Public Utilities Commission may sign a long-term solar interconnection agreement with PG&E for a solar project at [name withheld] Symphony Hall.
- Solar panels at [name withheld] Symphony Hall to connect to PG&E
- Public Utilities Commission proposes a long-term power agreement with PG&E for a solar project at [name withheld] Symphony Hall, 201 Van Ness Avenue; sent to committee.