  • Board cancels four repair payments totaling $1,659 owed to Union Machine Company for Fourth Street Bridge and returns them to Public Works.
    29 Jun 1908passedJournal 1908, p. 610 ↗
  • United Railroads wrote to accept the conditions of Ordinance 3091 on the Fourth Street Bridge.
    8 Feb 1915outcome not readJournal 1915 ↗
  • Index lists time extensions, the Exposition float and Fourth Street Bridge
    25 Oct 1915outcome not readJournal 1915, p. 1128 ↗
  • Thompson Bridge Company was granted an extension of time to finish the Fourth Street Bridge work.
    20 Mar 1916outcome not readJournal 1916, p. 264 ↗
  • Proposal to prohibit opening of Fourth Street Bridge drawbridges was referred.
    24 Apr 1916referredJournal 1916, p. 391 ↗
  • Board proposes $3,000 from the County Road Fund for electrical repairs to the Fourth Street Bridge.
    19 Oct 1931outcome not readJournal 1931, p. 2975 ↗
  • $20.9M sought to strengthen the Fourth Street Bridge in China Basin
    21 Jan 2003outcome not readBoard minutes 2003, p. 72 ↗
  • Public Works would accept and spend $20.9 million in federal and state grants to retrofit the Fourth Street Bridge; referred for adoption.
    21 Jan 2003referredBoard minutes 2003 ↗
  • Public Works proposed accepting $20.9M in federal and state grants to seismically retrofit the Fourth Street Bridge; referred.
  • Fourth Street Bridge retrofit grant sent to the Finance Committee
    27 Jan 2003outcome not readBoard minutes 2003, p. 99 ↗
  • Board referred a resolution to accept and spend $20,911,134 in federal and state grants to retrofit the Fourth Street Bridge.
    27 Jan 2003referredBoard minutes 2003 ↗
  • Department of Public Works may accept and spend a $20.9M federal and state grant to rehabilitate the Fourth Street Bridge.
    11 Feb 2003passedBoard minutes 2003 ↗
  • Public Works may accept and spend a $20,911,134 grant to seismically retrofit the Fourth Street Bridge, which was adopted.
    11 Feb 2003passedBoard minutes 2003 ↗
  • TRC-Imbsen contract for the Fourth Street Bridge sent to committee
    15 Jan 2008referredBoard minutes 2008 ↗
  • Resolution proposed approving a term over ten years for TRC-Imbsen consultant contract on Fourth Street Bridge; sent to Budget Committee.
  • Public Works approved a term longer than ten years for TRC-Imbsen's design contract on the Fourth Street Bridge retrofit.
    5 Feb 2008passedBoard minutes 2008 ↗
  • TRC-Imbsen hired for Fourth Street Bridge seismic work
    5 Feb 2008outcome not readBoard minutes 2008, p. 80055 ↗
  • $2.8M sought for Fourth Street Bridge lawsuit costs
  • $2.8M for Fourth Street Bridge lawsuit costs passes first reading
    8 Mar 2011passed first readingBoard minutes 2011, p. 220 ↗
  • $2.8M set aside for Fourth Street Bridge lawsuit costs
    15 Mar 2011passed first readingBoard minutes 2011, p. 5 ↗
  • $2.8M voted for Fourth Street Bridge lawsuit costs
  • Ordinance appropriating $2,809,000 from the General Fund Reserve for Fourth Street Bridge litigation expenses was finally passed.