  • Moliterno's Clay Street building accepted for the Harbor Emergency Hospital
    9 May 1910passedJournal 1910, p. 468 ↗
  • Lease of a Clay Street building for a Harbor Emergency Hospital accepted from P. J. Moliterno at $225 monthly.
    6 Jun 1910passedJournal 1910, p. 575 ↗
  • Resolution appropriates $475 to move Washington Irving School and $277 for a pulmotor at Harbor Emergency Hospital.
  • Paving money spent on Harbor Emergency Hospital and Engine House No. 5
    10 Aug 1914passedJournal 1914, p. 895 ↗
  • Allen & Company sells land for the Harbor Emergency Hospital
    14 Jul 1924outcome not readJournal 1924, p. 841 ↗
  • $4,091.30 paid to Allen & Company for Commercial Street land
    11 Aug 1924passedJournal 1924, p. 933 ↗
  • Harbor Emergency Hospital ordered on Sacramento Street near the Embarcadero
    8 Dec 1924outcome not readJournal 1924, p. 1443 ↗
  • Harbor Emergency Hospital building ordered on north side of Sacramento Street
    15 Dec 1924passedJournal 1924, p. 1468 ↗
  • Harbor emergency hospital on Sacramento Street: $18.8K foundation work
    16 Mar 1925passedJournal 1925 ↗
  • Board appropriated funds for the Harbor Emergency Hospital, Southern Police Station, Civic Center paving and school site borings.
    23 Mar 1925passedJournal 1925, p. 368 ↗
  • The Board proposed appropriations for Harbor Emergency Hospital repairs, a Municipal Railway bus, a Shriner publicity budget and a Lake Merced golf road.
    1 Jun 1925outcome not readJournal 1925, p. 799 ↗
  • $2,695 to Guilfoy Cornice Works for the Harbor Emergency Hospital
    8 Jun 1925passedJournal 1925, p. 825 ↗
  • Alfred H. Vogt received a third payment of $2,662.50 for piling and concrete work at Harbor Emergency Hospital.
    10 Aug 1925passedJournal 1925, p. 1163 ↗
  • The Board granted contractor Alfred H. Vogt ninety more days to finish piling and concrete work at Harbor Emergency Hospital.
  • Money set aside for sewers and the Harbor Emergency Hospital
    5 Oct 1925outcome not readJournal 1925, p. 1427 ↗
  • Money set aside for sewers and the Harbor Emergency Hospital
    13 Oct 1925passedJournal 1925, p. 1449 ↗
  • Guilfoy Cornice Works was granted a 30-day extension to finish ornamental work at the Harbor Emergency Hospital.
    30 Nov 1925passedJournal 1925, p. 1669 ↗
  • Elliot & Grant was paid $3,455.82 for a third construction payment on Harbor Emergency Hospital.
    23 Feb 1926passedJournal 1926, p. 254 ↗
  • Resolution awards contracts for hospital equipment for Harbor Emergency Hospital to Reid Bros. and Travers Surgical Company.
    8 Mar 1926passedJournal 1926, p. 362 ↗
  • Pays Guilfoy Cornice Works $1,517.50, final payment on iron work for Harbor Emergency Hospital.