Project

Harry Tracy Water Treatment Plant

A project in 10 Board decisions, 1997–2015.

10Board decisions about it
1997–2015first and last decision

Who appears together

OrganisationsHDR Engineering, Inc.named in 3Public UtilitiesCommissionnamed in 3Harry Tracy Water Treatment Plant

Lines show who appears in the same decisions. It doesn't mean they made a deal.

Organisations

More from the records

Who was paid · 2 organisations
HDR Engineering, Inc.3 decisions
Public Utilities Commission3 decisions

How many decisions pay each one; amounts are not shown until a person checks them.

Votes · 3 roll calls
yes 30no 0absent 3

3 printed roll calls; 3 were unanimous.

Decisions, by type
resolution9
contract1
Decisions, by outcome
referred6
passed4
All 10 decisions · in date order
  • Resolution proposed to spend $750,000 on emergency standby power at the [name withheld] Plant; referred to Finance Committee.
    9 Jun 1997referredJournal 1997 ↗
  • Board adopted retroactive approval of a $750,000 emergency standby power project at the [name withheld] Plant.
    14 Jul 1997passedJournal 1997 ↗
  • Resolution to accept and spend a $75,840 California Energy Commission grant at [name withheld] Plant was referred for adoption.
  • Proposal to accept a $75,840 California Energy Commission grant to cut peak power load at [name withheld] Plant was referred.
  • Board adopted a resolution letting the Public Utilities Commission accept and spend a $75,840 state grant to cut peak load at [name withheld] Plant.
  • Emergency $2.5 million slope and drainage repair at the [name withheld] Plant was approved by resolution.
  • Proposed settlement pays Skyline Stables Corporation $650,000 over its ended [name withheld] Plant lease; sent to Budget and Finance Committee.
  • Proposed $2,000,000 increase to HDR Engineering's contract for [name withheld] Plant work; sent to Budget Committee.
  • A resolution to add $2,000,000 to HDR Engineering's contract for construction management at the [name withheld] Plant was sent to committee.
  • PUC approved adding $2M to HDR Engineering's construction management contract for [name withheld] Plant, now $18M.