Ingleside Outlet Sewer
A project in 11 Board decisions, 1910–1912.
11Board decisions about it
1910–1912first and last decision
In short
- 12 Aug 1912Contra Costa Construction Company was granted thirty more days to finish Section C of the Ingleside Outlet Sewer.
Who appears together
Lines show who appears in the same decisions. It doesn't mean they made a deal.
People
- John P. McLaughlinproposed 1 · 1910
- Robert J. Lougheryproposed 1 · 1911
Organisations
- Contra Costa Construction Companynamed in 2
- Board of Public Worksnamed in 1 · city body
Places
- Ingleside Outlet Sewernamed in 1
More from the records
Who was paid · 1 organisations
| Board of Public Works | 1 decision |
How many decisions pay each one; amounts are not shown until a person checks them.
Votes · 6 roll calls
yes 97no 0absent 0
6 printed roll calls; 6 were unanimous.
Decisions, by type
| ordinance | 5 |
| resolution | 5 |
| other | 1 |
Decisions, by outcome
| passed | 7 |
| passed first reading | 2 |
| referred | 1 |
1 decision has no outcome read yet.
All 11 decisions · in date order
- Board of Public Works proposed $34,000 from sewer bonds for sewers in Section A of the Ingleside Outlet Sewer; referred.
- Ordinance ordering construction of Section A of the Ingleside Outlet Sewer, estimated at $34,000, passed for printing.
- Section A of the Ingleside Outlet Sewer ordered built at an estimated $34,000, paid from sewer bonds.
- Proposes setting aside $11,000 from the Sewer Construction Account for cast-iron pipe for the Ingleside Outlet Sewer.
- Ordinance to build a $70,000 sewer section of the Ingleside Outlet Sewer passed for printing.
- Sixth installment of $6,656.62 approved to F. Rolandi for Section A of the Ingleside Outlet Sewer.
- The Board ordered a $35,000 sewer built in Section B of the Ingleside Outlet Sewer.
- The Board set aside $11,000 to buy cast-iron pipe for the Ingleside Outlet Sewer across Lake Merced Rancho.
- The Board finally passed an ordinance for $70,000 of sewer work in Section C of the Ingleside Outlet Sewer.
- Contra Costa Construction Company was granted thirty more days to finish Section C of the Ingleside Outlet Sewer.
- Contra Costa Construction Company granted thirty more days to finish Section C of the Ingleside Outlet Sewer.