A project in 9 Board decisions, 2017–2024.
9Board decisions about it
2017–2024first and last decision
In short
- 16 Jul 2024More money for sewage plant construction staff approved
More from the records
Decisions, by type
| resolution | 9 |
Decisions, by outcome
| passed | 3 |
6 decisions have no outcome read yet.
All 9 decisions · in date order
- HDR Engineering's $17,000,000 headworks management contract sent to committee
- HDR Engineering sought for $17,000,000 of Headworks construction management
- $17 million engineering contract to help build new sewage plant approved
- HDR Engineering's $27,000,000 headworks contract sent to committee
- Consultant contract for new sewer headworks raised to $27M, approved
- $10M more for HDR Engineering on the New Headworks project
- $31.7M HDR Engineering headworks contract increase sent to committee
- $31.7M HDR Engineering headworks contract increase put forward
- More money for sewage plant construction staff approved