16 Board decisions about Sewage Treatment Plant, in date order. Each links to its printed page.

  • Proposed salary change moves the Chief Engineer post from the Sewage Pumping Station to the Sewage Treatment Plant; passed for second reading.
    9 Jan 1939passed first readingJournal 1939, p. 86 ↗
  • Proposed salary ordinance would create 18 positions at the Sewage Treatment Plant under Public Works; outcome on next page.
    9 Jan 1939outcome not readJournal 1939, p. 85 ↗
  • Supervisors passed an ordinance moving the Chief Engineer post from the Sewage Pumping Station to the Sewage Treatment Plant.
    23 Jan 1939passedJournal 1939, p. 149 ↗
  • Proposed salary ordinance adds 18 Sewage Treatment Plant positions under the Department of Public Works.
    23 Jan 1939outcome not readJournal 1939, p. 148 ↗
  • Board finally passed an ordinance changing staffing at the Sewage Treatment Plant, adding one pumping attendant and removing a chauffeur.
    11 Sep 1939passedJournal 1939, p. 1813 ↗
  • Proposed salary ordinance reclassifying operating engineer posts at the city's Sewage Treatment Plant; the vote is on the next page.
    25 Oct 1943outcome not readJournal 1943, p. 2368 ↗
  • Appropriated $3,182 for pay of a Sewage Treatment Plant superintendent in Public Works; passed as an emergency ordinance.
  • Sewage Treatment Plant superintendent's monthly pay raised from $350 to $370 by emergency ordinance, passed.
  • Supervisor MacPhee moved approval of the Public Works budget for the Sewage Treatment Plant, approved without objection.
    17 May 1944passedJournal 1944, p. 1044 ↗
  • Board approved the budget for the Sewage Treatment Plant without objection.
    21 May 1945passedJournal 1945, p. 1024 ↗
  • Board approved the Sewage Treatment Plant budget as amended, including a $17,781 increase for enlarging the Richmond-Sunset plant.
    17 May 1946passedJournal 1946, p. 1397 ↗
  • The Sewage Treatment Plant budget was approved as amended.
    19 May 1947passedJournal 1947, p. 1093 ↗
  • Public Works would authorize one water chemist position at the Sewage Treatment Plant on a 5½-day week.
    3 Nov 1947outcome not readJournal 1947, p. 1914 ↗
  • Park Department $2,680 appropriation to fund a chemist position at the Sewage Treatment Plant; outcome continues on next page.
    3 Nov 1947outcome not readJournal 1947, p. 1909 ↗
  • One water chemist position at the Sewage Treatment Plant is authorized to work a non-standard week under the salary ordinance.
    17 Nov 1947passedJournal 1947, p. 1942 ↗
  • Budget for the Sewage Treatment Plant approved with cuts to temporary pay, contracts and materials.
    18 May 1948passedJournal 1948, p. 358 ↗