Project
West Modernization Project
A project in 9 Board decisions, 2018–2025.
9Board decisions about it
2018–2025first and last decision
In short
- 1 May 2018WCME JV Terminal 3 West management contract put forward
More from the records
Decisions, by type
| resolution | 9 |
Decisions, by outcome
| passed | 3 |
6 decisions have no outcome read yet.
All 9 decisions · in date order
- WCME JV Terminal 3 West management contract put forward
- $14,000,000 Terminal 3 West contract proposed with WCME JV
- $14 million Terminal 3 West project management contract approved
- $50,000,000 Terminal 3 West contract with WCME sent to committee
- Approved: Terminal 3 project-management contract rises to $50 million
- WCME JV Terminal 3 project management contract raised to $50,000,000
- $126.0M Terminal 3 modernization contract with WCME sent to committee
- $126.0M Terminal 3 modernization contract with WCME approved
- Airport Terminal 3 project management deal raised to $126M