Ben Franklin school
Named in the records1987–1995
9 records of San Francisco tie this place, 1987–1995: 1 decision of the Board of Supervisors and 8 facts read from city reports. Open the full list, with filters for years, kind and outcome.
- Kind
- Named in the records
- Records
- 9: 1 Board decision, 8 facts from city reports
- Years
- 1987–1995
What the records say
All 9 records, in date order. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1987-04-20 | Supervisor Kennedy asked that a letter go to the Tax Collector about residential parking permits near Ben Franklin School. | other | Board decision scanned page ↗ |
| 1988 | [name withheld] school upgrades · event: school received all upgrades it requested | event | City report: San Francisco Unified School District : operational audit, school repair program : 1988 Proposition A, 1990 Proposition B : final report scanned page ↗ |
| 1995 | Arntz Builders contract · cost usd: $3,385,000 low bid out of 3 bids | project | City report: San Francisco Unified School District : operational audit, school repair program : 1988 Proposition A, 1990 Proposition B : final report scanned page ↗ |
| 1995 | Arntz Builders contract · cost usd: approximately $5.0 million final cost after 12 modifications | project | City report: San Francisco Unified School District : operational audit, school repair program : 1988 Proposition A, 1990 Proposition B : final report scanned page ↗ |
| 1995 | Arntz Builders contract · cost usd: $280,000 add for upgraded doors and hardware | project | City report: San Francisco Unified School District : operational audit, school repair program : 1988 Proposition A, 1990 Proposition B : final report scanned page ↗ |
| 1995 | Arntz Builders contract · cost usd: $150,000 add for a new heating system for the Boys' gym | project | City report: San Francisco Unified School District : operational audit, school repair program : 1988 Proposition A, 1990 Proposition B : final report scanned page ↗ |
| 1995 | Arntz Builders contract · cost usd: $100,000 add for fire sprinkler modifications | project | City report: San Francisco Unified School District : operational audit, school repair program : 1988 Proposition A, 1990 Proposition B : final report scanned page ↗ |
| 1995 | [name withheld] school fire alarm system · finding: inadequate testing and checkout of fire alarm system, still being tested | finding | City report: San Francisco Unified School District : operational audit, school repair program : 1988 Proposition A, 1990 Proposition B : final report scanned page ↗ |
| 1995 | [name withheld] school playground · finding: serious undulations from inadequate drainage, repaired in renovation | finding | City report: San Francisco Unified School District : operational audit, school repair program : 1988 Proposition A, 1990 Proposition B : final report scanned page ↗ |
All 9 records, with filters · this place's data as JSON · release v0.7.1 · CC0 1.0