China Basin ballpark
Named in the records1989–2034
197 records of San Francisco tie this place, 1989–2034: 33 decisions of the Board of Supervisors and 164 facts read from city reports. Open the full list, with filters for years, kind and outcome.
- Kind
- Named in the records
- Records
- 197: 33 Board decisions, 164 facts from city reports
- Years
- 1989–2034
What the records say
The 60 most telling of its 197 records, in date order: the ones an editor picked first, then the highest scored. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1989 | [name withheld] ballpark · other: Giants average 24,000 tickets sold over 79 dates, or 1.94 million per year | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark (worst case scenario) · other: Tickets sold assumed to average 1.58 million a year (20,000 per game) | alternative | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark site demolition · cost usd: $1.8 million for the whole ballpark site, assuming the existing deck is not totally demolished | measure | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | Municipal Railway extension to [name withheld] ballpark · other: Funded through a combination of federal, State, and City funds already identified | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | Caltrans property acquisition for [name withheld] ballpark · cost usd: up to $11.0 million (1989 estimate) | measure | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1989 | Parking facility for [name withheld] ballpark · other: 1500 parking stalls, up to 1000 available to the Giants on game day | building | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark sewer hookup · other: Cost of hooking up the ballpark to the City's sewer system will be minimal | finding | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark · cost usd: $95.8 million estimated construction cost | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark · cost usd: $115.8 million total cost with possible overruns | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark · cost usd: City share of cost overruns capped at $10 million | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark · other: City agreed to waive or refund possessory interest taxes due by Spectacor | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark · cost usd: Possessory interest tax reimbursement over 40 years estimated at $14.7 million | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark · other: approximately $77.6 million in new revenues over forty years | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark · other: direct and indirect tax revenues of approximately $734.7 million | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark · cost usd: Ballpark Land Assembly ($1,300,000) present value ($973,000) | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark · other: Indirect City Revenues from New Ballpark $252,393,000 nominal, $17,198,000 present value | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark · other: Total Benefits $822,971,000 nominal, $57,993,000 present value | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1989 | [name withheld] ballpark · finding: [name withheld]/Benefit of New Ballpark $760,126,000 nominal, $31,495,000 present value | finding | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 1996 | Ballpark site redevelopment designation · other: ballpark site to be designated a Redevelopment Survey Area | recommendation | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996 | Construction of new [name withheld] ballpark · jobs: 3,655 construction jobs, average duration four months | finding | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996 | Giants ballpark proposal · finding: Port faces the greatest level of financial risk under this proposal | finding | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996 | Giants ballpark proposal · finding: Expected high level toxic waste; environmental remediation could range from low cost encapsulation to very expensive or prohibitive | finding | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996 | Port · finding: Port does not have the resources to fund pre-construction costs for the ballpark site | finding | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996 | Giants ballpark proposal · cost usd: Tax increment bonds to contribute $10 million to the project | finding | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996 | [name withheld] bridge transit service · other: six additional Muni Metro trains and up to ten additional buses | action | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996 | Muni operating costs for [name withheld] · cost usd: approximate $800,000 annually (net of cash revenue) | finding | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996 | Port of San Francisco · finding: Port faces the greatest financial risk, or possibility of financial gain, under the Giants proposal | finding | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996 | Port of San Francisco · finding: Port does not have sufficient funds to pay for the initial investment to deliver the site to the Giants | finding | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996 | Regional Water Quality Control Board · other: Approval of the level of toxic cleanup likely required at the ballpark site | agency | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996 | [name withheld] service · other: six additional Muni Metro trains and up to ten additional buses for bridge service | action | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1996-01-08 | Budget Analyst ordered to report on city costs of the proposed [name withheld] ballpark before the March 26, 1996 vote. | passed | Board decision scanned page ↗ |
| 1996-02-12 | The Board directed the Budget Analyst to report on city benefits of the proposed [name withheld] ballpark, with top priority. | passed | Board decision scanned page ↗ |
| 1997 | Street closures for North China Basin ballpark area · proposes: close Berry, Second, Embarcadero, Main and Fremont segments completely | action | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1997-06-30 | The Board adopted, as amended, environmental findings for the [name withheld] ballpark and Rincon Point-South Beach redevelopment plan changes. | passed | Board decision scanned page ↗ |
| 1997-06-30 | Environmental findings for the [name withheld] ballpark and Rincon Point-South Beach plan changes were endorsed, as amended. | passed | Board decision scanned page ↗ |
| 1997-06-30 | Public hearing held on amending the Rincon Point-South Beach redevelopment plan for a 42,000-seat [name withheld] ballpark. | hearing | Board decision scanned page ↗ |
| 1997-07-28 | Environmental report certification for the [name withheld] endorsed; Kaufman and Newsom excused from voting. | passed | Board decision scanned page ↗ |
| 1997-08-25 | An ordinance proposed to appropriate $686,163 (≈ $1.4 million in 2026 dollars) in Port revenues for construction of the [name withheld] was referred to Finance Committee. | referred | Board decision scanned page ↗ |
| 1997-10-20 | Port Commission's $686,163 (≈ $1.4 million in 2026 dollars) appropriation for [name withheld] construction passed on second reading. | passed first reading | Board decision scanned page ↗ |
| 1997-10-27 | Port Commission appropriates $685,163 (≈ $1.4 million in 2026 dollars) in port revenues for construction of the [name withheld] for fiscal 1997-98; ordinance finally passed. | passed | Board decision scanned page ↗ |
| 1998 | China Basin Ballpark Project · adopted: Planning Commission Resolutions No. 14399 and 14417 adopting Ballpark Findings | action | City report: San Francisco general plan : amendments to the general plan : adopted between August 1997 and June 1998 scanned page ↗ |
| 1998 | China Basin Ballpark Project · other: Port Commission Resolution No. 97-53 and Board of Supervisors Resolution No. 701-97, File No. 262-97-1 | action | City report: San Francisco general plan : amendments to the general plan : adopted between August 1997 and June 1998 scanned page ↗ |
| 1999-07-19 | China Basin Ballpark Company leases parking lots near the new ballpark | passed | Board decision scanned page ↗ |
| 2005 | Proposed China Basin ballpark · cost usd: Total expenses 2005: $13,737,901 | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 2005 | Proposed China Basin ballpark · other: Total income 2005: $15,954,619 | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 2006 | Proposed China Basin ballpark · cost usd: Total expenses 2006: $14,026,196 | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 2006 | Proposed China Basin ballpark · other: Total income 2006: $16,359,035 | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 2006 | City finally passed an ordinance approving settlement of its tax lawsuit with the Assessment Appeals Board over the Giants' China Basin ballpark assessment. | passed | Board decision scanned page ↗ |
| 2006-09-26 | Board considers settling the city's property tax challenge over the Giants' China Basin ballpark assessments for three tax years. | ordinance | Board decision scanned page ↗ |
| 2006-09-26 | Ordinance proposed to settle the city's tax challenge over the Giants' China Basin ballpark property assessments. | ordinance | Board decision scanned page ↗ |
| 2006-10-03 | City settles its tax writ over Giants' China Basin ballpark assessments, contingent on reduced roll values and payment. | passed | Board decision scanned page ↗ |
| 2006-10-03 | Authorizes settling the City's writ petition against the Assessment Appeals Board over the Giants' China Basin ballpark tax assessment. | passed | Board decision scanned page ↗ |
| 2007 | Proposed China Basin ballpark · cost usd: Total expenses 2007: $14,328,906 | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 2014 | Proposed China Basin ballpark · other: Total income 2014: $20,413,944 | project | City report: Building a new home for the San Francisco Giants : a cost-benefit analysis of the proposed China Basin ballpark scanned page ↗ |
| 2018-02-13 | Pier 48 lease to ballpark company approved | passed | Board decision scanned page ↗ |
| 2026-09-29 | Oracle Park venue gift of $45,500 accepted for police recruitment testing | resolution | Board decision scanned page ↗ |
| 27 | [name withheld] stabilized attendance · other: stabilized attendance projection direct economic impact $60.1 million; total impact $116.6 million | finding | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
| 1997 | Ballpark Final Environmental Impact Report · event: Final EIR certified by Resolution No. 14398 | event | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1997 | Ballpark Draft Environmental Impact Report File No. 96.176E · event: Draft EIR issued on the ballpark and required actions to implement Proposition B | event | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1996 | Giants ballpark proposal · other: Additional General Fund revenue from increased Possessory Interest Taxes | finding | City report: Review of the projected costs and economic benefits associated with the San Francisco Giants' proposed ballpark at China Basin scanned page ↗ |
All 197 records, with filters · this place's data as JSON · release v0.7.1 · CC0 1.0