404 records of San Francisco tie this place, 1969–2012: 86 decisions of the Board of Supervisors and 318 facts read from city reports. Open the full list, with filters for years, kind and outcome. See the page about Executive Park: what it is, who appears with it.
- Kind
- Named in the records
- Assessor block
- 4991
- Records
- 404: 86 Board decisions, 318 facts from city reports
- Years
- 1969–2012
What the records say
The 60 most telling of its 404 records, in date order: the ones an editor picked first, then the highest scored. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1969 | Executive Park and Candlestick Point State Recreational Area · rezoned: C-2 and P | site | City report: Issues report for the South Bayshore Study Area scanned page ↗ |
| 1979-04-30 | New streets mapped at Executive Park Boulevard and [name withheld] | passed | Board decision scanned page ↗ |
| 1981 | Executive Park office buildings · built year: three office buildings constructed between 1981 and 1986 | property_record | City report: Draft EIR : long range development plan, University of California, San Francisco scanned page ↗ |
| 1985-11-12 | Resolution adopting an environmental report and height reclassification for the Executive Park site was referred to Planning, Housing and Development Committee. | referred | Board decision scanned page ↗ |
| 1985-11-25 | Executive Park height change found to have real environmental impact | passed | Board decision scanned page ↗ |
| 1985-11-25 | New height limits proposed for the San Francisco Executive Park site | passed first reading | Board decision scanned page ↗ |
| 1985-11-25 | Findings adopted for the Executive Park height changes | passed | Board decision scanned page ↗ |
| 1985-12-02 | New height limits proposed for the San Francisco Executive Park site | passed | Board decision scanned page ↗ |
| 1987 | San Francisco Executive Park · use: mixed office/retail/housing development project | project | City report: Issues report for the South Bayshore Study Area scanned page ↗ |
| 1987 | Executive Park · other: remaining redevelopment activity | project | City report: Issues report for the South Bayshore Study Area scanned page ↗ |
| 1987 | Executive Park · proposes: Executive Park (600 Units) | site | City report: Issues report for the South Bayshore Study Area scanned page ↗ |
| 1987 | Executive Park and Candlestick Point Recreational Area rezonings · rezoned: Rezonings brought large tracts of land from industrial to non-industrial uses | event | City report: Issues report for the South Bayshore Study Area scanned page ↗ |
| 1987 | Executive Park · units: Build-out estimate: 550 housing units, population 1100, jobs 6,400 | project | City report: Issues report for the South Bayshore Study Area scanned page ↗ |
| 1995 | San Francisco Executive Park Revised Housing Project · units: approximately 565 residential units | project | City report: Amendments to the master plan adopted between September 1988 and March 1995 scanned page ↗ |
| 1995 | San Francisco Executive Park Revised Housing Project · population: estimated population of about 1200 | project | City report: Amendments to the master plan adopted between September 1988 and March 1995 scanned page ↗ |
| 1995 | Revised Housing Project, San Francisco Executive Park · units: approximately 565 residential units | project | City report: Amendments to the master plan adopted between September 1988 and March 1995 scanned page ↗ |
| 1995 | Revised Housing Project, San Francisco Executive Park · population: estimated population of about 1200 | project | City report: Amendments to the master plan adopted between September 1988 and March 1995 scanned page ↗ |
| 1995 | Subarea Plan for San Francisco Executive Park · approved: Commission deems appropriate the amendments to the Subarea Plan to allow construction of the proposed Project as modified | action | City report: Amendments to the master plan adopted between September 1988 and March 1995 scanned page ↗ |
| 1995 | San Francisco Executive Park Revised Housing Project · other: parking capacity of 1.8 per unit of designated stalls | project | City report: Amendments to the master plan adopted between September 1988 and March 1995 scanned page ↗ |
| 1995 | San Francisco Executive Park Revised Housing Project · other: ten percent of units reserved for households up to 120 percent of median income | project | City report: Amendments to the master plan adopted between September 1988 and March 1995 scanned page ↗ |
| 1995 | Revised Housing Project · units: approximately 56 residential units | project | City report: Amendments to the master plan adopted between September 1988 and March 1995 scanned page ↗ |
| 1995 | Revised Housing Project · finding: site is vacant; no existing industrial or service sector businesses displaced | finding | City report: Amendments to the master plan adopted between September 1988 and March 1995 scanned page ↗ |
| 1995 | Revised Housing Project · finding: no landmarks or historic buildings affected | finding | City report: Amendments to the master plan adopted between September 1988 and March 1995 scanned page ↗ |
| 1996 | Executive Park · other: Served by University Mound Reservoir pressure zone; zone serves buildings up to 135 feet elevation | site | City report: Draft EIR : long range development plan, University of California, San Francisco scanned page ↗ |
| 1996 | Executive Park subarea · proposes: Develop housing units on the eastern portion of the site following the hillside contours, including two-bedroom units and children's play areas | project | City report: South Bayshore : a new beginning : citizen's guide to the South Bayshore plan scanned page ↗ |
| 1996 | Executive Park · units: 600 dwelling units | site | City report: Draft EIR : long range development plan, University of California, San Francisco scanned page ↗ |
| 1996 | Executive Park water supply connection · other: Tuntex Inc. supporting construction of water supply connection to McLaren Reservoir | action | City report: Draft EIR : long range development plan, University of California, San Francisco scanned page ↗ |
| 1996 | Executive Park office buildings · built: Three office buildings totaling 320,000 gsf | building | City report: Draft EIR : long range development plan, University of California, San Francisco scanned page ↗ |
| 1996 | Executive Park office buildings · built: three office buildings totaling 320,000 gsf | building | City report: Draft EIR : long range development plan, University of California, San Francisco scanned page ↗ |
| 1996 | Executive Park amended development plan housing project · units: 600-unit housing project approved | project | City report: Draft EIR : long range development plan, University of California, San Francisco scanned page ↗ |
| 1997 | San Francisco Executive Park Revised Housing Project · other: one Muni route uses the project streets to serve office tenants | project | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1997 | San Francisco Executive Park Revised Housing Project · units: approximately 565 residential units | project | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1997 | San Francisco Executive Park Revised Housing Project · other: estimated population of about 1200 | project | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1997 | San Francisco Executive Park Subarea Plan · approved: amendments to the Subarea Plan for construction of the Project as modified | action | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1997 | San Francisco Executive Park Revised Housing Project · other: vacant land; no existing housing displaced | project | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1997 | San Francisco Executive Park Revised Housing Project · other: ten percent of units reserved for households with incomes up to 120 percent of median income | project | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1997 | San Francisco Executive Park Revised Housing Project · other: 1.8 parking spaces per unit | project | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1997 | Revised Housing Project · other: no landmarks or historic buildings will be affected | finding | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1998 | San Francisco Executive Park · units: approximately 600 units of housing | project | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 2000-05-30 | Board endorsed Planning Commission certification of the Executive Park environmental report, adopting findings with General Plan amendments. | passed | Board decision scanned page ↗ |
| 2000-05-30 | Ordinance amending the General Plan's Executive Park subarea plan passed on first reading by the Board. | passed first reading | Board decision scanned page ↗ |
| 2000-06-05 | Amendments to the Executive Park subarea plan in the South Bayshore area of the General Plan were finally passed as Ordinance 138-00. | passed | Board decision scanned page ↗ |
| 2005 | Proposed General Plan amendment for the Executive Park–Candlestick Cove project passed first reading. | passed first reading | Board decision scanned page ↗ |
| 2005 | The San Francisco General Plan was amended for the proposed Executive Park Candlestick Cove project, passed on first reading. | passed first reading | Board decision scanned page ↗ |
| 2005-09-06 | The Board did not pass on first reading a general plan amendment for the Executive Park Candlestick Cove project. | refused | Board decision scanned page ↗ |
| 2011 | Proposed rezoning of Executive Park parcels from business and light industrial to mixed residential-commercial passed first reading, 11 to 0. | passed first reading | Board decision scanned page ↗ |
| 2011 | Zoning map changes for Executive Park passed on first reading | ordinance | Board decision scanned page ↗ |
| 2011 | Proposed general plan amendments for the Executive Park subarea of Bayview Hunters Point passed first reading, 11 to 0. | passed first reading | Board decision scanned page ↗ |
| 2011 | Proposed Planning Code changes creating the Executive Park Special Use District passed first reading, 11 to 0. | passed first reading | Board decision scanned page ↗ |
| 2011-05-24 | Proposed rezoning of Executive Park parcels from commercial and light industrial to residential-commercial use was sent to committee. | referred | Board decision scanned page ↗ |
| 2011-05-24 | Zoning map changes proposed for Executive Park parcels | ordinance | Board decision scanned page ↗ |
| 2011-05-24 | Proposed rezoning of Executive Park parcels from commercial and light industrial to medium-density residential-commercial; sent to committee. | referred | Board decision scanned page ↗ |
| 2011-06-28 | Proposed rezoning of certain Executive Park parcels from C-2 and M-1 to RC-3 passed on first reading. | passed first reading | Board decision scanned page ↗ |
| 2011-06-28 | Executive Park rezoned for housing on first reading | ordinance | Board decision scanned page ↗ |
| 2011-06-28 | Proposed Planning Code rules creating the Executive Park Special Use District and height provisions passed on first reading. | passed first reading | Board decision scanned page ↗ |
| 2011-07-12 | Executive Park parcels in Bayview rezoned from business and light industrial to medium-density residential-commercial, finally passed. | passed | Board decision scanned page ↗ |
| 2011-07-12 | Some Executive Park lots finally set to allow homes and shops | passed | Board decision scanned page ↗ |
| 2011-07-12 | Zoning map changes proposed for Executive Park parcels | ordinance | Board decision scanned page ↗ |
| 2011-07-12 | Special use district with new height and bulk rules for Executive Park in Bayview finally passed. | passed | Board decision scanned page ↗ |
| 2011-07-12 | The General Plan's Executive Park subarea plan in Bayview Hunters Point was amended and the ordinance passed finally. | passed | Board decision scanned page ↗ |
All 404 records, with filters · this place's data as JSON · release v0.7.1 · CC0 1.0