Jefferson School
Campus1919–2006
127 records of San Francisco tie this place, 1919–2006: 81 decisions of the Board of Supervisors and 46 facts read from city reports. Open the full list, with filters for years, kind and outcome. See the page about Jefferson School: what it is, who appears with it.
- Kind
- Campus
- Assessor block
- 1773
- Records
- 127: 81 Board decisions, 46 facts from city reports
- Years
- 1919–2006
What the records say
The 60 most telling of its 127 records, in date order: the ones an editor picked first, then the highest scored. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1919-07-21 | Payment of $1,205.66 (≈ $23,482 in 2026 dollars) to architect James R. Miller for first work on Jefferson School was approved from the School Bond Fund. | passed | Board decision scanned page ↗ |
| 1919-08-04 | Resolution to pay architect James R. Miller $1,205.66 (≈ $23,482 in 2026 dollars) for Jefferson School was refused passage. | refused | Board decision scanned page ↗ |
| 1919-08-11 | Board passed for printing $27,792.45 (≈ $541,294 in 2026 dollars) for Galileo School and $6,028.30 (≈ $117,409 in 2026 dollars) for Jefferson School architectural services. | passed first reading | Board decision scanned page ↗ |
| 1919-08-11 | Payment of $1,205.66 (≈ $23,482 in 2026 dollars) to architect James R. Miller for Jefferson School was moved; outcome continues on next page. | passed first reading | Board decision scanned page ↗ |
| 1919-08-18 | The Board set aside $27,792.45 (≈ $541,294 in 2026 dollars) for Galileo School and $6,028.30 (≈ $117,409 in 2026 dollars) for Jefferson School architectural services. | passed | Board decision scanned page ↗ |
| 1919-08-18 | The Board authorized a $1,205.66 (≈ $23,482 in 2026 dollars) first payment to architect James R. Miller for the Jefferson School. | passed | Board decision scanned page ↗ |
| 1920-05-03 | Jefferson School to be built at 19th Avenue and Irving Street | passed | Board decision scanned page ↗ |
| 1920-05-03 | Jefferson School to be built at 19th Avenue and Irving Street | passed | Board decision scanned page ↗ |
| 1920-05-03 | Proposed ordinance letting Public Works contract to build Jefferson School at Nineteenth Avenue and Irving Street. | passed | Board decision scanned page ↗ |
| 1920-05-03 | Jefferson School to be built at Nineteenth Avenue and Irving Street | passed | Board decision scanned page ↗ |
| 1920-05-10 | Payment of $2,411.32 (≈ $40,624 in 2026 dollars) to architect J. R. Miller for Jefferson School work was passed for printing on McLeran's motion. | passed first reading | Board decision scanned page ↗ |
| 1920-05-11 | Jefferson School to be built at Nineteenth Avenue and Irving Street | passed | Board decision scanned page ↗ |
| 1920-05-11 | Jefferson School ordered built at 19th Avenue and Irving Street | passed | Board decision scanned page ↗ |
| 1920-07-19 | Proposed appropriation of $274,289.75 (≈ $4.6 million in 2026 dollars) from school bond money to build Jefferson School. | resolution | Board decision scanned page ↗ |
| 1920-07-26 | Board set aside $274,289.75 (≈ $4.6 million in 2026 dollars) from 1918 bond funds for Jefferson School construction contracts. | passed | Board decision scanned page ↗ |
| 1920-09-16 | Resolution authorizes payments to contractors and suppliers for Hetch Hetchy, Jefferson School, Municipal Railways and other city work. | resolution | Board decision scanned page ↗ |
| 1920-12-20 | Nine payments totalling about $70,000 (≈ $1.2 million in 2026 dollars) were authorized for Hetch Hetchy work and Excelsior and Jefferson school construction. | resolution | Board decision scanned page ↗ |
| 1921 | Jefferson School · owned by city: Education | property_record | City report: Valuation of real property owned by city and county of San Francisco ... / 1935-1954 scanned page ↗ |
| 1921-01-10 | Resolution authorizing payments to contractors and suppliers from city funds, including Hetch Hetchy and Jefferson School work, passed for printing. | passed first reading | Board decision scanned page ↗ |
| 1921-01-17 | Resolution authorizes payment of city claims to suppliers and contractors for Hetch Hetchy, Jefferson School, Municipal Railways and police. | resolution | Board decision scanned page ↗ |
| 1921-01-24 | Payments authorized to contractors and suppliers for Hetch Hetchy, Jefferson School, Municipal Railways and city departments. | resolution | Board decision scanned page ↗ |
| 1921-02-07 | Resolution authorizes about thirty city payments to contractors and suppliers, including Jefferson School, Hetch Hetchy and Market Street work. | passed | Board decision scanned page ↗ |
| 1921-02-21 | Proposal to authorize Municipal Railway power, printing, and Jefferson School heating payments for Pacific Gas & Electric, United Railroads, Hancock Bros. and Scott Company; passed first reading only. | passed first reading | Board decision scanned page ↗ |
| 1921-06-13 | Resolution proposes $15,000 (≈ $282,352 in 2026 dollars) for Jefferson School equipment and $1,500 (≈ $28,235 in 2026 dollars) for a sewer near Prague and Dublin streets. | resolution | Board decision scanned page ↗ |
| 1921-06-13 | $15,000 (≈ $282,352 in 2026 dollars) to equip the Jefferson School | resolution | Board decision scanned page ↗ |
| 1921-06-20 | Money set aside for Jefferson School equipment and Divisadero Street widening | passed | Board decision scanned page ↗ |
| 1921-06-20 | Money set aside for Jefferson School equipment and Divisadero Street widening | passed | Board decision scanned page ↗ |
| 1921-07-05 | Payments to Joost Bros. and Alex Coleman for Grant and Jefferson School work authorized; final vote continues on next page. | passed | Board decision scanned page ↗ |
| 1921-07-25 | Resolution 19093 authorizes dozens of city payments to suppliers, schools, hospitals and institutions, including $46,228.85 (≈ $870,187 in 2026 dollars) to O. Monson for Jefferson School. | resolution | Board decision scanned page ↗ |
| 1921-08-01 | Resolution authorizes payment of about $50,000 (≈ $941,173 in 2026 dollars) in claims for Jefferson School, Municipal Railways and Hetch Hetchy, passed for printing. | passed first reading | Board decision scanned page ↗ |
| 1921-08-08 | Resolution authorizes payments to firms and claimants for Municipal Railways, Hetch Hetchy and Jefferson School work, claims dated June 1921. | passed | Board decision scanned page ↗ |
| 1921-08-15 | The Board passed $3,500 (≈ $65,882 in 2026 dollars) for grading, loaming and sidewalks at the Jefferson School. | passed | Board decision scanned page ↗ |
| 1921-08-22 | Payments authorized to suppliers and contractors for Jefferson School and Hetch Hetchy work, pending final passage. | resolution | Board decision scanned page ↗ |
| 1921-11-07 | Payment of $17,650 (≈ $332,234 in 2026 dollars) to O. Monson for building the Jefferson School approved. | resolution | Board decision scanned page ↗ |
| 1921-11-21 | Payment of $17,650 (≈ $332,234 in 2026 dollars) to O. Monson for building the Jefferson School approved. | resolution | Board decision scanned page ↗ |
| 1925-11-09 | Ordinance proposed for additions to Jefferson School on the east side of Nineteenth Avenue between Irving and Judah streets. | ordinance | Board decision scanned page ↗ |
| 1925-11-09 | Jefferson School to get additions on Nineteenth Avenue | ordinance | Board decision scanned page ↗ |
| 1925-11-23 | Ordinance passed authorising contracts for additions to Jefferson School on Nineteenth Avenue between Irving and Judah. | passed | Board decision scanned page ↗ |
| 1925-11-23 | Jefferson School additions ordered on east side of 19th Avenue | passed | Board decision scanned page ↗ |
| 1927-10-31 | Bill 8278 proposed to let Public Works plan and build additions to Jefferson School on Nineteenth Avenue. | ordinance | Board decision scanned page ↗ |
| 1927-11-07 | Ordinance authorizes additions and alterations to Jefferson School on Nineteenth avenue between Irving and Judah streets. | passed | Board decision scanned page ↗ |
| 1927-11-07 | Jefferson School additions and alterations ordered on 19th Avenue | passed | Board decision scanned page ↗ |
| 1928-06-04 | $89K (≈ $1.8 million in 2026 dollars) to enlarge Jefferson School on 19th Avenue | passed | Board decision scanned page ↗ |
| 1928-06-11 | Jefferson School additions on Nineteenth Avenue were funded with $89,434 (≈ $1.8 million in 2026 dollars), paid to several contractors. | passed | Board decision scanned page ↗ |
| 1928-10-08 | Payment of $12,286.99 (≈ $242,104 in 2026 dollars) to Meyer Bros. for additions to Jefferson School approved. | passed | Board decision scanned page ↗ |
| 1928-10-08 | Payment of $1,210.14 (≈ $23,845 in 2026 dollars) to Scott Company for mechanical equipment at Jefferson School approved. | passed | Board decision scanned page ↗ |
| 1928-11-19 | Fourth payment of $669.38 (≈ $13,190 in 2026 dollars) to Newberry, Pearce Electric Co. for Jefferson School electrical work was approved. | passed | Board decision scanned page ↗ |
| 1929-01-14 | Payment of $1,754.77 (≈ $34,576 in 2026 dollars) to Thos. Skelly as final payment for plumbing at Jefferson School approved. | passed | Board decision scanned page ↗ |
| 1938-10-10 | Sale of portable buildings at Jefferson School was proposed on the Board of Education's recommendation; outcome continues on next page. | resolution | Board decision scanned page ↗ |
| 1947-11-10 | City bought easements for the Sunset Supply Line from Jefferson School District for $1,625 (≈ $24,553 in 2026 dollars) and Henry Stoneson for $100 (≈ $1,511 in 2026 dollars). | passed | Board decision scanned page ↗ |
| 1957-09-16 | Board adopted a resolution asking the State Allocation Board to rehear Jefferson school district's application for San Francisco land funds. | passed | Board decision scanned page ↗ |
| 1958-07-28 | Supervisor Halley was authorized to attend a State Department of Finance meeting in Daly City on a Jefferson school site purchase. | passed | Board decision scanned page ↗ |
| 1958-12-22 | [name withheld] directed to submit a legal opinion on the city's stance toward the Jefferson school land purchase. | other | Board decision scanned page ↗ |
| 2002 | JEFFERSON SCHOOL (ELEMENTARY) · owned by city: SF Unified School District (SFUSD) | property_record | City report: Real property owned by the city and county of San Francisco / 2003 scanned page ↗ |
| 2003 | JEFFERSON SCHOOL (ELEMENTARY) · owned by city: SF Unified School District (SFUSD) | property_record | City report: Real property owned by the city and county of San Francisco / 2004 scanned page ↗ |
| 2004 | JEFFERSON SCHOOL (ELEMENTARY) · owned by city: SF Unified School District (SFUSD) | property_record | City report: Real property owned by the city and county of San Francisco / 2005 scanned page ↗ |
| 2001 | JEFFERSON SCHOOL (ELEMENTARY) · owned by city: SF Unified School District (SFUSD) | property_record | City report: Real property owned by the city and county of San Francisco / 2001 scanned page ↗ |
| 2006 | JEFFERSON SCHOOL (ELEMENTARY) (Portion) · owned by city: SF Unified School District (SFUSD) | property_record | City report: Real property owned by the city and county of San Francisco / 2006 scanned page ↗ |
| 2002 | Jefferson School (Elementary) · owned by city: SF Unified School District (SFUSD) | property_record | City report: Real property owned by the city and county of San Francisco / 2002 scanned page ↗ |
| 1935 | Jefferson School · owned by city: Board of Education | property_record | City report: Valuation of real property owned by city and county of San Francisco ... / 1935-1954 scanned page ↗ |
All 127 records, with filters · this place's data as JSON · release v0.7.1 · CC0 1.0