Laguna Honda Hospital site
Named in the records1866–1994
65 records of San Francisco tie this place, 1866–1994: 0 decisions of the Board of Supervisors and 65 facts read from city reports. Open the full list, with filters for years, kind and outcome.
- Kind
- Named in the records
- Records
- 65: 0 Board decisions, 65 facts from city reports
- Years
- 1866–1994
What the records say
The 60 most telling of its 65 records, in date order: the ones an editor picked first, then the highest scored. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1994 | Laguna Honda Hospital recommended project · cost usd: $486.1 million over a 10 year period, escalated to midpoint of construction | project | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1866 | Laguna Honda Hospital site · acquired: 80 acre site west of Twin Peaks, purchased by the city | site | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1992 | Alternate B Phase I · other: build a new addition containing 660 patient beds, support services, and a new replacement power plant | action | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Alternate B new construction · stories: eight stories | alternative | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Alternate B new construction · other: 1207 beds | alternative | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Alternate B new construction · floor area sqft: about 837,000 gross square feet of new construction | alternative | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Alternate B residential care facility · floor area sqft: 32,000 square foot residential care facility | alternative | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Alternate B · finding: intrudes into the view lines of neighboring single family homes; fairly obtrusive building | alternative | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital site · acreage: 64-acre | site | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital site · other: bounded by Laguna Honda Boulevard, 7th Avenue, Clarendon Avenue, and Woodside Avenue | site | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Clarendon Hall · other: situated across Clarendon Valley from the main building | building | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Recommended Project, Laguna Honda Hospital replacement · cost usd: $211.4 million less than Alternate A | alternative | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Recommended Project, Laguna Honda Hospital replacement · cost usd: $25.6 million less than Alternate B | alternative | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Two-Phased Replacement of Laguna Honda Hospital · proposes: Two-Phased Replacement of Laguna Honda Hospital | project | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital site · other: potential future need for another 390 beds at the site, not in the proposed Project | finding | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital campus · finding: traffic circulation within the steeply sloped site is currently difficult | finding | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital replacement project · proposes: new main entry to the hospital while maintaining the current front door entry | project | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Alternate A · stories: 5-story building (four above-grade stories) | alternative | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Recommended Project, Laguna Honda Hospital replacement · cost usd: Per Bed construction cost $225,000 in 1992 dollars | project | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Internal remodeling to create 4-bed rooms · rejected: reduces bed capacity by nearly 50%; not pursued further | alternative | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital new facility Phase One · units: 650 new nursing beds | project | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital new facility Phase One · floor area sqft: approximately 442,000 square feet | project | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital new facility Phase One western block · stories: 7-story structure | project | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital new facility Phase One eastern portion · stories: 4-stories tall | project | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital new facility Phase Two · floor area sqft: about 424,000 square feet of new construction | project | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital new facility Phase Two · units: 557 beds, total 1207 beds | project | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
| 1992 | Laguna Honda Hospital Alternate A · cost usd: $377,300,000 in 1992 dollars; $759,800,000 with escalation | measure | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital recommended project · acquired: no acquisition of any land areas; all development within existing site | measure | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Clarendon Hall · other: Located in north central part of the site on a knoll, separated from main hospital complex by a depression | building | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital site · finding: No alternative site offered the advantages of the current site | finding | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital replacement · alternative: Alternate C (Three-Phased Replacement) preferred approach | alternative | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Alternate C · finding: unanimously selected by the Community Advisory Group and the Task Force as the recommended direction | finding | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Alternate C · finding: lowest construction and project cost | finding | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Alternate C · finding: shortest time frame for construction | finding | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Alternate C · finding: best neighborhood compatibility and acceptance due to low profile in valley portion of the site | finding | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital recommended project · floor area sqft: about 900,000 new square feet | project | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital recommended project · other: 1,207 patient beds, 60 more than present | project | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | residential care facility · units: 50-unit residential care facility with two beds per unit | project | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital replacement · stories: seven stories tall | building | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital Alternate A · other: Eleven and one half years of construction | measure | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital site · acreage: original 80 acre parcel of land | site | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital · acreage: sloping 62-acre site | site | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital site · use: Public Use District (P), owned by a governmental agency and used for public purposes | site | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital service road · proposes: dedicated service road separating service traffic from staff and visitor traffic | site | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital recommended project · proposes: new main entry to the hospital from Woodside Avenue access drive | alternative | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital main parking lot · other: 460 parking spaces | building | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital recommended project · other: 648 parking spaces total | building | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital recommended project · other: increase of 68 parking stalls | building | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital recommended project · cost usd: $486.1 million over ten years | project | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital recommended project · cost usd: per-square-foot construction cost approximately $333 in 1994 dollars | project | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital · other: existing site boundaries owned by the City & County of San Francisco | site | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital development plan · units: 60 additional beds, just over 5% of existing bed capacity | project | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital Institutional Master Plan · proposes: replaces the aging facility within the boundaries of the existing hospital site | project | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital Alternate A (Minimum New Construction) · alternative: Minimum New Construction; existing hospital retained and renovated | alternative | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital Alternate C (Three-Phased Replacement) · approved: Identified as preferred approach by Hospital Task Force and Community Advisory Group | alternative | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital · owned by city: City and County of San Francisco | property_record | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital · acreage: 62 acre site | site | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital · acreage: 62 acre site | site | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1994 | Laguna Honda Hospital site · acquired: site acquired by San Francisco | property_record | City report: Laguna Honda Hospital institutional master plan scanned page ↗ |
| 1992 | Recommended Project, Laguna Honda Hospital replacement · cost usd: $548.4 million over ten years (escalated to mid-point of construction) | project | City report: Into the 21st century : building a new facility to continue Laguna Honda Hospital's mission scanned page ↗ |
All 65 records, with filters · this place's data as JSON · release v0.7.1 · CC0 1.0