63 records of San Francisco tie this place, 1907–2006: 13 decisions of the Board of Supervisors and 50 facts read from city reports. Open the full list, with filters for years, kind and outcome.

Kind
Named in the records
Records
63: 13 Board decisions, 50 facts from city reports
Years
1907–2006

What the records say

The 60 most telling of its 63 records, in date order: the ones an editor picked first, then the highest scored. The one-line summaries were written by a language model from the printed page; open the page to check the wording.

WhenWhat the record saysOutcomeSource
1907-04-01Bill 220 proposes erecting a temporary main library building on a Western Addition block, passed for printing.passed first readingBoard decision
scanned page ↗
1907-04-15The Board of Library Trustees was authorized to erect a temporary Main Library building on Block 75, Western Addition.passedBoard decision
scanned page ↗
1917existing Main Library building · built year: Built in 1917, [name withheld] landmarkbuildingCity report: San Francisco new main library : bond program report
scanned page ↗
1922-11-20Library Fund authorization of $2,455 (≈ $49,237 in 2026 dollars) to J. W. Bender Roofing Co. for roofing the main Library building was moved.resolutionBoard decision
scanned page ↗
1944existing Main Library building · finding: declared at capacity in 1944findingCity report: San Francisco new main library : bond program report
scanned page ↗
1960-02-15$21,500 (≈ $244,737 in 2026 dollars) to clean and paint Main Library proposed.pendingBoard decision
scanned page ↗
1960-02-23$21,500 (≈ $244,737 in 2026 dollars) appropriated to clean and paint the Main Library building; the ordinance was finally passed.passedBoard decision
scanned page ↗
1968-11-18The Public Library was authorized to apply for federal funds to plan a new Main Library building.passedBoard decision
scanned page ↗
1968-11-25The Board authorized the Public Library to apply for federal funds to plan and specify a new Main Library building.passedBoard decision
scanned page ↗
1987Main Library building · alternative: Asian Art Museum option, easiest fit and least expensivealternativeCity report: Civic Center proposal
scanned page ↗
1987Asian Art Museum · cost usd: $25 million working figureprojectCity report: Civic Center proposal
scanned page ↗
1987Main Library seismic improvements · cost usd: about $8 million seismic needsprojectCity report: Civic Center proposal
scanned page ↗
1987Main Library building · cost usd: Fitting out for Superior Court civil courts would cost $51 millionbuildingCity report: Civic Center proposal
scanned page ↗
1987Off-street parking for City vehicles · proposes: Off-street parking for City-owned vehicles within a new Civic Center structure, possibly under new Main LibraryprojectCity report: Civic Center proposal
scanned page ↗
1987Main Library Building · proposes: Use Main Library Building for Civil Division of Superior Court space needsalternativeCity report: Civic Center proposal
scanned page ↗
1987Main Library Building pedestals · other: two pedestals provided for possible sculptural siting; no proposal yetmeasureCity report: Civic Center proposal
scanned page ↗
1987Main Library Building · finding: maximum space in present building is 347,000 square feet with no room for expansionfindingCity report: Civic Center proposal
scanned page ↗
1987Main Library Building · finding: Present library building is functionally obsoletefindingCity report: Civic Center proposal
scanned page ↗
1987Main Library · other: 2,800 daily walk-in patronsproperty_recordCity report: Civic Center proposal
scanned page ↗
1987Main Library Building remodel and expansion · finding: Degree of renovation and expansion work will be quite extensive and require a substantial capital commitment by the CityfindingCity report: Civic Center proposal
scanned page ↗
1987Main Library Building remodel and expansion · finding: No significant interim occupancy of the Main Library Building would be feasible during constructionfindingCity report: Civic Center proposal
scanned page ↗
1987Main Library Building remodel and expansion · finding: Expansion program will consume all of the building's capacity, leaving no future expansion potentialfindingCity report: Civic Center proposal
scanned page ↗
1987Main Library Building remodel and expansion · other: Remodeled and expanded building will provide 347,700 gross square feet of projected library spacemeasureCity report: Civic Center proposal
scanned page ↗
1987Main Library Building remodel and expansion · finding: Practical feasibility of using the building to meet future main library needs is questionablefindingCity report: Civic Center proposal
scanned page ↗
1987Main Library Building museum re-use · floor area sqft: 136,000 gross square feet for museum purposesbuildingCity report: Civic Center proposal
scanned page ↗
1987Main Library Building museum re-use with 45 Hyde Street · floor area sqft: 217,000 square feet including 45 Hyde Street sitebuildingCity report: Civic Center proposal
scanned page ↗
1987Asian Art Museum re-use of Main Library Building · recommendation: Asian Art Museum is an appropriate re-use option for the existing Main Library BuildingrecommendationCity report: Civic Center proposal
scanned page ↗
1987Main Library Building · floor area sqft: about 142,255 net square feet existing, including 45 Hyde Streetproperty_recordCity report: Civic Center proposal
scanned page ↗
1987Main Library Building · finding: remodeling and expansion would render the existing building unusable for two to three yearsfindingCity report: Civic Center proposal
scanned page ↗
1987Main Library Block · recommendation: Convert the existing Main Library Building into a museum to accommodate the space needs of the Asian Art MuseumrecommendationCity report: Civic Center proposal
scanned page ↗
1987Main Library Building · finding: the library would be closed for 2 to 3 years during the construction periodfindingCity report: Civic Center proposal
scanned page ↗
1987Main Library Building performing arts theater option · alternative: performing arts theateralternativeCity report: Civic Center proposal
scanned page ↗
1987Main Library Building Superior Court option · other: 23 courtrooms and chambers, Law Library, County Clerk spacealternativeCity report: Civic Center proposal
scanned page ↗
1987Main Library Building · proposes: Construct a new Main Library Building on [name withheld] and modify access to [name withheld]projectCity report: Civic Center proposal
scanned page ↗
1987New Main Library Building · proposes: Construct a new Main Library Building on [name withheld]recommendationCity report: Civic Center proposal
scanned page ↗
1987Main Library Building · recommendation: Construct a New Main Library Building on [name withheld], and Modify Vehicular and Pedestrian Access to [name withheld]recommendationCity report: Civic Center proposal
scanned page ↗
1987[name withheld], New Main Library Building · cost usd: $70.0 - $85.0 million (1987 dollars)projectCity report: Civic Center proposal
scanned page ↗
1987[name withheld], New Main Library Building · cost usd: $70.0 - $85.0 million (1987 dollars)projectCity report: Civic Center proposal
scanned page ↗
1987Main Library Building · recommendation: a new main library building be constructed on [name withheld]recommendationCity report: Civic Center proposal
scanned page ↗
1988New Main Library Building · proposes: Granite veneer for all exterior wall surfacesbuildingCity report: San Francisco new main library : bond program report
scanned page ↗
1988New Main Library Building · proposes: Combination of flat roofs and sloped mansard roofsbuildingCity report: San Francisco new main library : bond program report
scanned page ↗
1988New Main Library Building · proposes: Halon gas fire suppression system for rare book and document roomsbuildingCity report: San Francisco new main library : bond program report
scanned page ↗
1988New Main Library Building · other: Fully equipped with automatic fire sprinkler systembuildingCity report: San Francisco new main library : bond program report
scanned page ↗
1988existing Main Library building · finding: too small, unsafe, and antiquated; cannot accommodate existing collections and departmentsfindingCity report: San Francisco new main library : bond program report
scanned page ↗
1988existing Main Library building · finding: remodeling or expansion of the present building is not feasible (all four studies)findingCity report: San Francisco new main library : bond program report
scanned page ↗
1996Main Library renovation · event: Court space crunch would continue at least until 1996eventCity report: Civic Center proposal
scanned page ↗
1997Asian Art Museum · other: Slated to leave the Music Concourse area and relocate to the Old Main Library buildingeventCity report: M.H. deYoung Memorial Museum site selection study
scanned page ↗
1997Former Main Library building · alternative: Existing Library as Courts Facility, infeasiblealternativeCity report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997
scanned page ↗
1999-12-08Committee approved and filed release of $32,002,738 (≈ $64.7 million in 2026 dollars) in reserved funds to upgrade the Old Main Library building.passedBoard decision
scanned page ↗
1999-12-08Funds approved to upgrade the Old Main Library buildingordinanceBoard decision
scanned page ↗
1999-12-08$32 million (≈ $64.7 million in 2026 dollars) to renovate old Main Library for Asian Art Museum proposed.unknownBoard decision
scanned page ↗
2000Main Library Building · finding: the remodeling and expansion program will consume all of the site's capacity, leaving no area for expansion beyond the year 2000findingCity report: Civic Center proposal
scanned page ↗
2003-03-04Board ordinance appropriates $3,742,290 (≈ $6.9 million in 2026 dollars) in bond interest for converting the Old Main Library building into the Asian Art Museum; finally passed.passedBoard decision
scanned page ↗
2006Main Library Building remodel and expansion · finding: Renovation and expansion can theoretically accommodate quantitative space needs of library operations projected through 2006alternativeCity report: Civic Center proposal
scanned page ↗
1990Main Library building, Civic Center · use: transfer of current Main Library building to become new home of the San Francisco Asian Art MuseumbuildingCity report: Getting things done : visions & goals for San Francisco : a two-year progress report
scanned page ↗
1994Asian Art Museum (former Main Library building) · cost usd: $41.7 million general obligation bonds approved by votersbuildingCity report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997
scanned page ↗
1994Former Main Library building · cost usd: $41.7 million in general obligation bonds approved for upgrade for Asian Art MuseumbuildingCity report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997
scanned page ↗
1987Main Library Building · other: designed for 500,000 volumes, exceeds design capacity by 100 percentbuildingCity report: Civic Center proposal
scanned page ↗
1987Asian Art Museum · cost usd: additional annual operating and maintenance subsidy greater than $2 millionprojectCity report: Civic Center proposal
scanned page ↗
1987Superior Court civil courthouse · cost usd: $51 million by recent estimatealternativeCity report: Civic Center proposal