Mission Bay Project
Named in the records1983–2020
149 records of San Francisco tie this place, 1983–2020: 21 decisions of the Board of Supervisors and 128 facts read from city reports. Open the full list, with filters for years, kind and outcome. See the page about Mission Bay Project: what it is, who appears with it.
- Kind
- Named in the records
- Records
- 149: 21 Board decisions, 128 facts from city reports
- Years
- 1983–2020
What the records say
The 60 most telling of its 149 records, in date order: the ones an editor picked first, then the highest scored. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1983 | Southern Pacific Mission Bay project · floor area sqft: 2.8 million square feet of office space on two blocks owned by the Company | project | City report: Stadium feasibility analysis : task force report to the mayor, October 1983 scanned page ↗ |
| 1983 | Southern Pacific Mission Bay project · other: Over 3,700 parking spaces on the two blocks owned by Southern Pacific | project | City report: Stadium feasibility analysis : task force report to the mayor, October 1983 scanned page ↗ |
| 1983 | Mission Bay project · sponsor: Southern Pacific | project | City report: Stadium feasibility analysis : task force report to the mayor, October 1983 scanned page ↗ |
| 1983 | Mission Bay project · proposes: over 12,000 parking spaces | project | City report: Stadium feasibility analysis : task force report to the mayor, October 1983 scanned page ↗ |
| 1983 | Mission Bay project · finding: stadium sites located on or adjacent to Mission Bay project; shared parking could eliminate stadium parking need | finding | City report: Stadium feasibility analysis : task force report to the mayor, October 1983 scanned page ↗ |
| 1983 | Mission Bay project · other: over 12,000 parking spaces | project | City report: Stadium feasibility analysis : task force report to the mayor, October 1983 scanned page ↗ |
| 1984 | Site 14 / Mission Bay Project · other: Site 14 located within boundaries of Southern Pacific's Mission Bay Project | project | City report: Report to the Board of Supervisors of the City and County of San Francisco : review of the report of the Mayor's Stadium Task Force scanned page ↗ |
| 1984 | Southern Pacific Mission Bay Project · other: up to 16,410 future parking spaces | project | City report: Report to the Board of Supervisors of the City and County of San Francisco : review of the report of the Mayor's Stadium Task Force scanned page ↗ |
| 1984 | Southern Pacific Mission Bay Project · other: future development could increase parking supply significantly | finding | City report: Report to the Board of Supervisors of the City and County of San Francisco : review of the report of the Mayor's Stadium Task Force scanned page ↗ |
| 1984 | Downtown stadium site zone · other: Four sites selected for detailed analysis within Task Force site zone | site | City report: Report to the Board of Supervisors of the City and County of San Francisco : review of the report of the Mayor's Stadium Task Force scanned page ↗ |
| 1984-07-30 | Resolution urges the Mayor to approve a supplemental appropriation for an appraisal of the Mission Bay Project; referred to Finance Committee. | referred | Board decision scanned page ↗ |
| 1985 | Mission Bay project · finding: Expected to provide large floor space for back office, business service, manufacturing and wholesale/distribution activities | project | City report: South of Market rezoning study : housing, business activity, neighborhood livability, research findings scanned page ↗ |
| 1985-06-03 | Renne asked to release $550,000 (≈ $1.7 million in 2026 dollars) in gift funds for the Mission Bay Project; sent to Finance Committee. | referred | Board decision scanned page ↗ |
| 1985-08-19 | Supervisor Molinari's request to review the status of the Mission Bay Project was sent to the Planning, Housing and Development Committee. | referred | Board decision scanned page ↗ |
| 1985-09-10 | The Clerk was directed to release $550,000 (≈ $1.7 million in 2026 dollars) in gift funds to City Planning for the Mission Bay Project; outcome not shown. | motion | Board decision scanned page ↗ |
| 1986 | Mission Bay project · finding: office development portion exceeds 400,000 square feet | finding | City report: Legal effect of Proposition M scanned page ↗ |
| 1987 | Mission Bay Project · other: planning consultants to [name withheld]/Southern Pacific | project | City report: [Study of the San Francisco juvenile probation system] : [fact sheets] scanned page ↗ |
| 1989 | Mission Bay project · other: pending; half of the remaining housing units accounted for in Redevelopment areas and Mission Bay | project | City report: An affordable housing action plan for San Francisco : draft report scanned page ↗ |
| 1989 | Mission Bay Project · finding: annual net fiscal balance slightly positive in initial years with first year surplus of approximately $100,000 | project | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1989 | Mission Bay Project · other: Figure 6: graphic comparison of annual net fiscal effects on General Fund for Land Use Program (1989 dollars) | finding | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1989 | Mission Bay Project · cost usd: approximately $90 million (1989 dollars) city subsidy | project | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · units: 8,000 housing units | measure | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · units: 800 units | project | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · units: 3,000 affordable housing units | project | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · units: 800 units built directly by the Project Sponsor | project | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay · other: nearly 32% of project area devoted to housing | project | City report: Mission Bay : a new San Francisco neighborhood scanned page ↗ |
| 1990 | Mission Bay · other: about 20% of project area allocated to open space | project | City report: Mission Bay : a new San Francisco neighborhood scanned page ↗ |
| 1990 | Mission Bay · other: about 10.5% of land set aside for office and commercial/light industrial uses | project | City report: Mission Bay : a new San Francisco neighborhood scanned page ↗ |
| 1990 | Mission Bay project · other: fiscal impact analysis by the Budget Division | project | City report: Report to the Board of Supervisors, city and county of San Francisco : review and analysis of the Deputy Mayor function in the Office of the Mayor scanned page ↗ |
| 1990 | Mission Bay Project · other: Development Agreement obliges City to approve development consistent with Land Use Program | project | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · cost usd: approximately $300 million total infrastructure, parks, and community facilities | project | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Transportation Impact Development Fee (TIDF) · cost usd: $5 per square foot of office development, totalling $24 million | measure | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · other: lien-to-value ratio just over 10 percent | finding | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | School impact fee · cost usd: $1.56 per square foot of residential development | measure | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Economic development fee · cost usd: $2 per square foot fee on office development, totalling between $9.6 and 11.4 million | measure | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Public Art Program · cost usd: 1% of construction costs | measure | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project capital cost estimates · other: contingency cost factor of 10 percent included | finding | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project capital improvements · cost usd: Project Sponsor costs for capital improvement items, at $231 million | finding | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · finding: substantial positive cost/revenue balance to the City | finding | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project fiscal model · other: model projected public revenues and costs for a 35-year period | finding | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · finding: total General Fund revenues will exceed $36 million annually at buildout | project | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · finding: annual net surplus may reach $2.0 million by end of fifth year | project | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · alternative: four Project Alternatives considered in the EIR | alternative | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · finding: Alternatives with the highest commercial densities generate the largest fiscal surpluses | finding | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1990 | Mission Bay Project · other: assumed buildout period of 30 years | project | City report: Fiscal and financial evaluation of the Mission Bay Project scanned page ↗ |
| 1991 | Mission Bay Project · units: up to an additional 250 on-site affordable housing units | project | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1991-01-07 | Board adopted a resolution declaring intent to fund affordable housing obligations from Mission Bay project revenues. | passed | Board decision scanned page ↗ |
| 1991-01-07 | Board adopted California environmental findings for the Mission Bay Project, citing overriding benefits, over two dissenting votes. | passed | Board decision scanned page ↗ |
| 1991-01-07 | Board adopted the final environmental impact report for the proposed Mission Bay Project, a specific plan with zoning and Master Plan changes. | passed | Board decision scanned page ↗ |
| 1991-02-25 | Environmental review findings for the Mission Bay project were adopted, modifying earlier Mission Bay approvals and findings. | passed | Board decision scanned page ↗ |
| 1991-04-01 | City Planning receives $271,360 (≈ $671,307 in 2026 dollars) for capital work on the Mission Bay Project, passed for second reading. | passed first reading | Board decision scanned page ↗ |
| 1991-04-08 | City Planning's Mission Bay Project received a $271,360 (≈ $671,307 in 2026 dollars) appropriation, with earlier action ratified, finally passed. | passed | Board decision scanned page ↗ |
| 1992-02-03 | Licences and options on surplus city property under the Mission Bay Port Agreement with Catellus were adopted as part of the Mission Bay project. | passed | Board decision scanned page ↗ |
| 1992-02-03 | Board found proposed Port land transfers to Catellus are part of the Mission Bay project for environmental review. | passed | Board decision scanned page ↗ |
| 1997 | Mission Bay Project · units: 3,000 units of affordable housing on-site | project | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1998-10-26 | Settlement with defendant 1900 Third Street, LLC in the City's Mission Bay project area lawsuit was finally passed. | passed | Board decision scanned page ↗ |
| 2000 | Mission Bay project · other: Sanitary sewage directed to SEWPCP at build-out | project | City report: Final environmental impact statement for the disposal and reuse of Hunters Point Shipyard scanned page ↗ |
| 1984 | Mission Bay stadium plan · rejected: rejected by Southern Pacific because it ranked low in public and private goals | alternative | City report: Report to the Board of Supervisors of the City and County of San Francisco : review of the report of the Mayor's Stadium Task Force scanned page ↗ |
| 1997 | Mission Bay project · other: major waterfront park system, affordable housing plan, cultural center, child care, school site and hazardous materials remediation plan | project | City report: San Francisco general plan : amendments to the general plan : adopted between September 1988 and July 1997 scanned page ↗ |
| 1984 | Mission Bay stadium plan · alternative: one of eleven potential development plans considered by Southern Pacific | alternative | City report: Report to the Board of Supervisors of the City and County of San Francisco : review of the report of the Mayor's Stadium Task Force scanned page ↗ |