What the records say
All 5 records, in date order. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1945-06-04 | Public Works approved spending $1,345,000 (≈ $25.2 million in 2026 dollars) of sewer bond funds on North Point treatment plant land and Hampshire and La Playa sewers. | passed | Board decision scanned page ↗ |
| 1950-10-09 | Ordinance passed for second reading to appropriate $160,000 (≈ $2.2 million in 2026 dollars) for extra sewer construction costs at North Point treatment plant. | passed first reading | Board decision scanned page ↗ |
| 1980 | North Point Treatment Plant · other: Provides primary treatment to 20 to 30% of City's sewage; operates only during rainy weather under staged program | project | City report: Clean water reporter. June 1980 scanned page ↗ |
| 1994-10-31 | A $300,000 (≈ $682,065 in 2026 dollars) transfer from the North Point treatment plant project to a Bay Area water reuse project was sent to committee. | referred | Board decision scanned page ↗ |
| 1994-12-05 | Board finally passed a $300,000 (≈ $682,065 in 2026 dollars) transfer of Public Works capital funds from the North Point Treatment Plant to a water reuse project. | passed | Board decision scanned page ↗ |