45 records of San Francisco tie this place, 1954–1988: 22 decisions of the Board of Supervisors and 23 facts read from city reports. Open the full list, with filters for years, kind and outcome.
- Kind
- Named in the records
- Records
- 45: 22 Board decisions, 23 facts from city reports
- Years
- 1954–1988
What the records say
All 45 records, in date order. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1954 | Firehouse · recommendation: retained, rebuilt under the 1954 firehouse program | recommendation | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Recommended Project Area D-1 · proposes: Recommended Project Area D-1 within Redevelopment Area D | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Preliminary Redevelopment Plan, Project Area D-1, South of Market Redevelopment Area · other: Project area bounded by the center lines of Eighth, Harrison, Hawthorne, Folsom, Third, Natoma and Fourth Streets | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Preliminary Redevelopment Plan, Project Area D-1, South of Market Redevelopment Area · other: Comprises Assessor's Blocks 3734, 3751, 3752, 3753, 3754, 3755, and portions of Assessor's Blocks 3723 and 3750 | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Redevelopment Project Area D-1 · recommendation: Establish first project area D-1 including six Assessor's Blocks and parts of two others | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Redevelopment Project Area D-1 · acreage: 61 acres | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Redevelopment Project Area D-1 · other: Located just north of the freeway and bridge distribution system, in the blocks between Harrison and Bryant Streets | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 · acreage: 1,140,000 square feet of land to be acquired | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Remainder of Project Area D-1 · rezoned: M-1 (light industrial) | measure | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 · other: federal capital grant of four million dollars and local aid of two million dollars | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 land use · use: Predominately industrial: C-M Heavy Commercial and M-1 Light Industrial, plus a public park area | measure | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 street layout · other: Continued use of the existing grid of streets within and bounding the project area, with principal streets providing through traffic and access | measure | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 interior alleys · other: Closing of interior alleys to create sites of one or more acres with safe and efficient access | measure | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | South of Market Urban Renewal Project Area D-1 · acreage: approximately seven large blocks or 61.2 net acres | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | South of Market Urban Renewal Project Area D-1 · other: bounded on the north by Natoma Street, south by Harrison Street, east by Hawthorne Street, west by Eighth Street | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | South of Market Urban Renewal Project Area D-1 · other: a little more than one-half of the Renewal Area | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 · proposes: Project Area D-1 be established in the blocks bounded by Highth Street, Harrison Street, Hawthorne Street, Folsom Street, Third Street, Natoma Street, Fourth Street, and Folsom Street | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 · proposes: including all of Assessor's Blocks 3754, 3755 and parts of Assessor's Blocks 37 and 3750 | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 · proposes: clearance of all residential structures, clearance of some older industrial structures, closing of some interior streets, and widening and opening of others | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 · use: frontage on Third and Fourth Streets used for general commercial purposes; remainder of the project used for light industry | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 · cost usd: net project cost estimated at six million dollars | project | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 · population: 3850 persons | finding | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1957 | Project Area D-1 · households displaced: 1850 single individuals and 800 families | finding | City report: A preliminary plan for a project in the South of Market Redevelopment Area "D" : report to the City Planning Commission and the Redevelopment Agency scanned page ↗ |
| 1966-01-03 | The Board set a February 14, 1966 public hearing on the proposed Yerba Buena Center Redevelopment Project Area D-1 plan; adopted. | passed | Board decision scanned page ↗ |
| 1966-02-14 | Consideration of the Yerba Buena Center redevelopment plan for Project Area D-1 was continued to February 21, 1966. | continued | Board decision scanned page ↗ |
| 1966-03-28 | The Board approved a cooperation agreement between the City and the Redevelopment Agency for Yerba Buena Center Project Area D-1. | passed | Board decision scanned page ↗ |
| 1966-03-28 | Redevelopment plan for Yerba Buena Center Project Area D-1 passed for second reading. | passed first reading | Board decision scanned page ↗ |
| 1966-03-28 | Redevelopment plan for the Yerba Buena Center Project Area D-1 was postponed until Supervisor Boas arrives. | continued | Board decision scanned page ↗ |
| 1966-04-04 | Redevelopment plan for Yerba Buena Center Project Area D-1 was proposed; supervisors moved to continue it one week. | continued | Board decision scanned page ↗ |
| 1966-04-18 | Redevelopment plan for the Verba Buena Center Project Area D-1 was taken up; its outcome is not shown on this page. | continued | Board decision scanned page ↗ |
| 1966-04-18 | Verba Buena Center redevelopment deal delayed one week. | pending | Board decision scanned page ↗ |
| 1966-04-18 | Verba Buena Center redevelopment deal delayed one week. | pending | Board decision scanned page ↗ |
| 1966-04-25 | Board passed the Yerba Buena Center redevelopment plan for Project Area D-1, with building use and height changes, 9 to 2. | passed | Board decision scanned page ↗ |
| 1966-04-25 | Board approved a supplemental agreement with the Redevelopment Agency for the Yerba Buena Center Project Area D-1. | passed | Board decision scanned page ↗ |
| 1966-04-25 | Verba Buena Center redevelopment deal approved, with local business preferences | passed | Board decision scanned page ↗ |
| 1969-05-05 | Board cancelled taxes on property the Redevelopment Agency acquired in the Verba Buena Center Redevelopment Project Area D-1. | passed | Board decision scanned page ↗ |
| 1971-07-19 | Board passed on first reading an ordinance amending the Yerba Buena Center redevelopment plan for Project Area D-1. | passed first reading | Board decision scanned page ↗ |
| 1972-03-27 | The Yerba Buena Center redevelopment area resolution, removing lands outside Project Area D-1, was adopted. | passed | Board decision scanned page ↗ |
| 1973-06-11 | Changes to Yerba Buena Center redevelopment plan proposed; outcome not shown. | unknown | Board decision scanned page ↗ |
| 1973-08-27 | Ordinance amending the Yerba Buena Center redevelopment plan, Project Area D-1, continued to October 1, 1973. | continued | Board decision scanned page ↗ |
| 1973-10-01 | Supervisors passed on second reading, as amended, amendments to the Redevelopment Plan for Yerba Buena Center Project Area D-1. | passed first reading | Board decision scanned page ↗ |
| 1973-10-09 | Board finally passed an ordinance amending the Yerba Buena Center redevelopment plan for Project Area D-1. | passed | Board decision scanned page ↗ |
| 1973-10-09 | The Board finally passed an amendment to the Yerba Buena Center redevelopment plan for Project Area D-1. | passed | Board decision scanned page ↗ |
| 1975-03-03 | City will close parts of Tehama Street in Yerba Buena | passed | Board decision scanned page ↗ |
| 1988-08-22 | Supervisors tabled a proposal to merge the Yerba Buena Center redevelopment project area D-1 into a larger project. | tabled | Board decision scanned page ↗ |