38 records of San Francisco tie this place, 1965–1993: 1 decision of the Board of Supervisors and 37 facts read from city reports. Open the full list, with filters for years, kind and outcome.

Kind
Named in the records
Records
38: 1 Board decision, 37 facts from city reports
Years
1965–1993

What the records say

All 38 records, in date order. The one-line summaries were written by a language model from the printed page; open the page to check the wording.

WhenWhat the record saysOutcomeSource
1990Status & Trends Report on dredging and waterway modification, San Francisco Estuary · recommendation: Identify and discuss the RWQCB water quality plans and policies in the final reportrecommendationCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1965San Francisco Estuary dredging · other: 11 million yd3 (8.4 million m3) dredged annuallyfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1987San Francisco Estuary shoreline · finding: sea-level rise increased to about 20 cm per centuryfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1987San Francisco Estuary Project · lead agency: U.S. Environmental Protection AgencyprojectCity report: Estuarywise : 100 tips on how you can prevent pollution of our bay and delta : handbook for the San Francisco Bay-Delta Estuary
scanned page ↗
1989USCOE San Francisco District maintenance dredging estimates · cost usd: 15,430,000 cubic yards total, 1989 to 1992measureCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990Estuary dredge disposal standards · recommendation: adopt estuary standards at least as firm as federal ocean disposal standardsrecommendationCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990Dredging and disposal of sediments in the San Francisco Estuary · finding: dredging and disposal of sediments was found to represent a relatively minor contribution to the overall loads of trace metals, PCBs, and PAHs in the EstuaryfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary · finding: Little is known regarding the structure of food webs in the Estuary; additional study will be requiredfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary · finding: Food-chain transport of metals and organic contaminants is an ongoing phenomenon in the EstuaryfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary mussels · other: PCB body burdens in mussels ranged from about 0.2 to 1.5 ug/g dry wt.measureCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary striped bass · other: Striped bass PCB concentrations in the Estuary range from about 0.1 to 1.0 ug/g dry wt.measureCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990Biota of the San Francisco Estuary · finding: Biota have accumulated measurable concentrations of a wide variety of contaminantsfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary fish PCB levels · finding: Starry flounder, striped bass and white croaker have higher PCB concentrations than clean sitesfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990PCB-contaminated dredged material disposal · finding: PCB-contaminated dredged material is disposed at dispersive sites in the EstuaryfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990PCB accumulation in Estuary biota · finding: Whether elevated PCB concentrations can be attributed to dredging cannot be stated at presentfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990Dredging effects on biota, San Francisco Estuary · finding: Few if any acute effects of metals and organic contaminants observed in the EstuaryfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990Dredged material contaminants, San Francisco Estuary · finding: Contaminants from dredged material may be exerting a negative influence in the Estuary, not yet proven or disprovenfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990Suspended solids from dredged material disposal, San Francisco Estuary · finding: Lethal suspended-solids concentrations are at least an order of magnitude higher than concentrations observed in the estuary water column during disposal eventsfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990USCOE dredged material disposal modeling effort · recommendation: Continue the USCOE modeling effort with a focus on circumventing existing model limitationsrecommendationCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990Dredged material disposal, San Francisco Estuary · finding: worst-case scenario: 25% of deposited material retained in the water columnfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary sediments · other: over 100 million yd3 of sediments resuspended annuallyfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary dredging and dredged material disposal · finding: no evidence of biomagnification in the San Francisco Estuary due to dredging and dredged material disposalfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary shoreline · finding: net shoreline retreat around the Estuary perimeterfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary shoreline · finding: erosion rate of about 1 m per year over last 30 yearsfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990DSTR (dredging status and trends report) · finding: repeated references to inadequate records for disposal amounts and locationsfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990Corps and other permitting agencies · recommendation: develop permitting, reporting, monitoring and enforcement system ensuring adequate dredge and disposal datarecommendationCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary Project Dredging and Waterway Modification Subcommittee · recommendation: short-term management actions to be implemented immediatelyrecommendationCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1992-08-31Supervisor Shelley requested a hearing on the San Francisco Estuary Project; it was referred to City Services Committee for September 15.referredBoard decision
scanned page ↗
1993Regional Monitoring Program · finding: most of the marshes and mudflats in the Estuary were surveyed for chemical contamination and toxicityfindingCity report: Bay protection and toxic cleanup program : status report
scanned page ↗
1993Regional Monitoring Program · other: Baseline Monitoring Program established, to start in 1993projectCity report: Bay protection and toxic cleanup program : status report
scanned page ↗
1990San Francisco Estuary Project · event: formally established by EPA AdministratorprojectCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990Dredging and Waterway Modification goals, actions and options · adopted: Adopted by the Management CommitteeeventCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary Project Management Conference dredging resolution · adopted: adopted by the Dredging and Waterway Modification Subcommittee and approved by the Management CommitteeeventCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990Hunters Point stations (San Francisco Estuary sediments) · finding: Hunters Point stations more toxic than Alameda or Treasure Island stations in combined bioassaysfindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990Hunters Point site (San Francisco Estuary sediments) · finding: Hunters Point site 3.6x more degraded than Treasure Island site and overall the most degraded sitefindingCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary Project · other: CCMP completion scheduled by November 1992projectCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990San Francisco Estuary Project · other: Comprehensive Conservation and Management Plan completion scheduledprojectCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary
scanned page ↗
1990USCOE San Francisco District new work dredging · other: 15.4 million cubic yards of new work dredging expected by 1992agencyCity report: Status and trends report on dredging and waterway modification in the San Francisco Estuary