277 records of San Francisco tie this place, 1930–2025: 230 decisions of the Board of Supervisors and 47 facts read from city reports. Open the full list, with filters for years, kind and outcome.
- Kind
- Named in the records
- Records
- 277: 230 Board decisions, 47 facts from city reports
- Years
- 1930–2025
What the records say
The 60 most telling of its 277 records, in date order: the ones an editor picked first, then the highest scored. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1930 | San Francisco Public Utilities Commission (SFPUC) · other: SFPUC formed when Spring Valley Water Company was purchased by the City of San Francisco | agency | City report: Peninsula Watershed management plan : [draft] scanned page ↗ |
| 1992-01-27 | Board approved an indemnity provision in a cooperative agreement between Daly City and the San Francisco Public Utilities Commission. | passed | Board decision scanned page ↗ |
| 1996-07-22 | Board approved Mayor's appointment of Frank Cook to the San Francisco Public Utilities Commission. | passed | Board decision scanned page ↗ |
| 2000-05-22 | Revised water rates for suburban resale customers of the San Francisco Public Utilities Commission passed on first reading. | passed first reading | Board decision scanned page ↗ |
| 2001-06-11 | Board passed a revised schedule of water rates for San Francisco Public Utilities Commission retail customers inside and outside the city. | passed | Board decision scanned page ↗ |
| 2001-06-11 | Board passed a revised schedule of water rates for suburban resale customers of the San Francisco Public Utilities Commission. | passed | Board decision scanned page ↗ |
| 2003-08-26 | Easements over San Francisco Public Utilities Commission property in [name withheld] granted to the [name withheld] Authority. | passed | Board decision scanned page ↗ |
| 2009-06-09 | The Board approved a memorandum of understanding for the Treasure Island Development Authority to pay unpaid utility amounts to the San Francisco Public Utilities Commission. | passed | Board decision scanned page ↗ |
| 2010-11-16 | Art Torres confirmed to the San Francisco Public Utilities Commission, Seat 2, by Board motion. | passed | Board decision scanned page ↗ |
| 2018-06-12 | $154.9M (≈ $207.8 million in 2026 dollars) in power bonds for city electricity projects approved | passed | Board decision scanned page ↗ |
| 2018-06-12 | $478M (≈ $641.4 million in 2026 dollars) in water bonds for city water projects approved | passed | Board decision scanned page ↗ |
| 2018-06-12 | Hetch Hetchy water and power upgrades get $340 million (≈ $456.2 million in 2026 dollars) | passed | Board decision scanned page ↗ |
| 2018-06-12 | $987M (≈ $1.3 billion in 2026 dollars) in sewer bonds for city projects approved | passed | Board decision scanned page ↗ |
| 2018-09-18 | Small land easement in Sunol sold to Alameda County | passed | Board decision scanned page ↗ |
| 2019-02-26 | City urges utilities agency to report on renewable power on city land | passed | Board decision scanned page ↗ |
| 2019-05-14 | Power bond limit of $199,898,526 (≈ $263.5 million in 2026 dollars) proposed for the utilities commission | ordinance | Board decision scanned page ↗ |
| 2019-05-14 | Higher power bond ceiling of $199,898,526 (≈ $263.5 million in 2026 dollars) sent to committee | ordinance | Board decision scanned page ↗ |
| 2019-05-21 | Water bond limit of $513,524,665 (≈ $676.8 million in 2026 dollars) proposed for the utilities commission | ordinance | Board decision scanned page ↗ |
| 2019-05-21 | Water bond ceiling of $513,524,665 (≈ $676.8 million in 2026 dollars) sent to committee | ordinance | Board decision scanned page ↗ |
| 2019-06-18 | Higher power bond ceiling of $199,898,526 (≈ $263.5 million in 2026 dollars) introduced | ordinance | Board decision scanned page ↗ |
| 2019-06-18 | Power revenue bond ceiling raised to $199,898,526 (≈ $263.5 million in 2026 dollars) on first reading | ordinance | Board decision scanned page ↗ |
| 2019-06-18 | Higher water bond ceiling of $513,524,665 (≈ $676.8 million in 2026 dollars) introduced | ordinance | Board decision scanned page ↗ |
| 2019-06-18 | Water revenue bond ceiling raised to $513,524,665 (≈ $676.8 million in 2026 dollars) on first reading | ordinance | Board decision scanned page ↗ |
| 2019-06-25 | Higher power bond ceiling of $199,898,526 (≈ $263.5 million in 2026 dollars) taken up | ordinance | Board decision scanned page ↗ |
| 2019-06-25 | Power bond ceiling would rise from $154,928,059 (≈ $204.2 million in 2026 dollars) to $199,898,526 (≈ $263.5 million in 2026 dollars) | ordinance | Board decision scanned page ↗ |
| 2019-06-25 | Power bond borrowing limit raised to $199.9 million (≈ $263.5 million in 2026 dollars) | passed | Board decision scanned page ↗ |
| 2019-06-25 | Higher water bond ceiling of $513,524,665 (≈ $676.8 million in 2026 dollars) taken up | ordinance | Board decision scanned page ↗ |
| 2019-06-25 | Water bond ceiling would rise from $478,440,136 (≈ $630.6 million in 2026 dollars) to $513,524,665 (≈ $676.8 million in 2026 dollars) | ordinance | Board decision scanned page ↗ |
| 2019-06-25 | Water bond borrowing limit raised to $513.5 million (≈ $676.8 million in 2026 dollars) | passed | Board decision scanned page ↗ |
| 2020-09-29 | $143 million (≈ $186.2 million in 2026 dollars) power project borrowing | passed | Board decision scanned page ↗ |
| 2020-09-29 | $350 million (≈ $455.7 million in 2026 dollars) sewer project borrowing | passed | Board decision scanned page ↗ |
| 2020-09-29 | $347 million (≈ $451.8 million in 2026 dollars) water project borrowing | passed | Board decision scanned page ↗ |
| 2020-11-03 | $85,000,000 (≈ $110.7 million in 2026 dollars) of earthquake safety bond money sent to committee | ordinance | Board decision scanned page ↗ |
| 2021-07-13 | Mayor asks to raise power revenue bonds to $162,314,897 (≈ $201.8 million in 2026 dollars) | ordinance | Board decision scanned page ↗ |
| 2021-07-13 | Utilities commission could issue up to $162,314,897 (≈ $201.8 million in 2026 dollars) in power bonds | ordinance | Board decision scanned page ↗ |
| 2021-07-13 | Mayor asks to raise wastewater revenue bonds to $563,430,430 (≈ $700.6 million in 2026 dollars) | ordinance | Board decision scanned page ↗ |
| 2021-07-13 | Utilities commission could issue up to $563,430,430 (≈ $700.6 million in 2026 dollars) in wastewater bonds | ordinance | Board decision scanned page ↗ |
| 2021-07-20 | Mayor asks to raise power revenue bonds to $162,314,897 (≈ $201.8 million in 2026 dollars) | ordinance | Board decision scanned page ↗ |
| 2021-07-20 | Power revenue bonds to be raised to $162,314,897 (≈ $201.8 million in 2026 dollars) for capital projects; amended, no final vote found | ordinance | Board decision scanned page ↗ |
| 2021-07-20 | Mayor asks to raise wastewater revenue bonds to $563,430,430 (≈ $700.6 million in 2026 dollars) | ordinance | Board decision scanned page ↗ |
| 2021-07-20 | Wastewater revenue bonds to be raised to $563,430,430 (≈ $700.6 million in 2026 dollars) for capital projects; amended, no final vote found | ordinance | Board decision scanned page ↗ |
| 2021-07-27 | Mayor's power revenue bond increase reaches its final vote | ordinance | Board decision scanned page ↗ |
| 2021-07-27 | Utilities commission could issue up to $162,314,897 (≈ $201.8 million in 2026 dollars) in power bonds | ordinance | Board decision scanned page ↗ |
| 2021-07-27 | Mayor's wastewater revenue bond increase reaches its final vote | ordinance | Board decision scanned page ↗ |
| 2021-07-27 | Utilities commission could issue up to $563,430,430 (≈ $700.6 million in 2026 dollars) in wastewater bonds | ordinance | Board decision scanned page ↗ |
| 2023-04-18 | $4.6 million (≈ $5.1 million in 2026 dollars) energy upgrades for community food services approved | passed | Board decision scanned page ↗ |
| 2023-07-25 | Borrowing up to $359 million (≈ $397.0 million in 2026 dollars) for water projects approved | passed | Board decision scanned page ↗ |
| 2023-07-25 | Borrowing up to $1.05 billion (≈ $1.2 billion in 2026 dollars) for sewer projects approved | passed | Board decision scanned page ↗ |
| 2023-07-25 | Borrowing up to $41 million (≈ $45.3 million in 2026 dollars) for power projects approved | passed | Board decision scanned page ↗ |
| 2024-04-16 | $500,000 (≈ $537,061 in 2026 dollars) appropriation for Public Utilities Commission approved | passed | Board decision scanned page ↗ |
| 2024-06-11 | Up to $1.7 billion (≈ $1.8 billion in 2026 dollars) in sewer bonds | passed | Board decision scanned page ↗ |
| 2024-06-18 | Up to $1.04 billion (≈ $1.1 billion in 2026 dollars) in water bonds approved for water projects | passed | Board decision scanned page ↗ |
| 2025-06-03 | Public Utilities capital budget change sent to committee | ordinance | Board decision scanned page ↗ |
| 2025-07-08 | $86,916 (≈ $90,965 in 2026 dollars) de-appropriation from the Public Utilities Commission capital budget | ordinance | Board decision scanned page ↗ |
| 2025-07-15 | $86,916 (≈ $90,965 in 2026 dollars) taken back from utilities capital projects on first reading | ordinance | Board decision scanned page ↗ |
| 2025-07-22 | Up to $1,054,138,857 (≈ $1.1 billion in 2026 dollars) in water bonds | passed | Board decision scanned page ↗ |
| 2025-07-22 | $12,990,064 (≈ $13.6 million in 2026 dollars) finally taken back from the Public Utilities Commission | passed | Board decision scanned page ↗ |
| 2025-07-22 | $86,916 (≈ $90,965 in 2026 dollars) de-appropriation from the Public Utilities Commission capital budget | ordinance | Board decision scanned page ↗ |
| 2002 | SFPUC infrastructure vulnerability briefing paper · finding: An Earthquake Vulnerable, Aging System Could Leave 2.4 Million Bay Area Customers With Little or No Water for Up to 60 Days | event | City report: San Francisco Public Utilities Infrastructure Task Force : final report : June 1, 2000-June 17, 2002 scanned page ↗ |
| 2002 | SFPUC earthquake crisis cost, timing and risk · finding: The crisis cost, timing, and risk calculations have yet to pass consensus TF scrutiny | finding | City report: San Francisco Public Utilities Infrastructure Task Force : final report : June 1, 2000-June 17, 2002 scanned page ↗ |
All 277 records, with filters · this place's data as JSON · release v0.7.1 · CC0 1.0