Transbay Terminal Building
Named in the records1992–1998
12 records of San Francisco tie this place, 1992–1998: 0 decisions of the Board of Supervisors and 12 facts read from city reports. Open the full list, with filters for years, kind and outcome.
- Kind
- Named in the records
- Records
- 12: 0 Board decisions, 12 facts from city reports
- Years
- 1992–1998
What the records say
All 12 records, in date order. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1992 | Transbay Terminal building · finding: Needed substantial upgrades to meet current seismic and other fire/life/safety codes after the 1989 Loma [name withheld] earthquake | finding | City report: Transbay area plan : background data report scanned page ↗ |
| 1992 | Transbay Terminal building · cost usd: about $34 million for basic upgrades (1992 State Architect study) | building | City report: Transbay area plan : background data report scanned page ↗ |
| 1993 | Transbay Terminal MUNI/SamTrans loading areas · other: MUNI/SamTrans loading areas depressed by 2 feet | building | City report: Transit terminal study scanned page ↗ |
| 1993 | Alternative 1 - Expand the Existing Terminal Building To Mission Street · finding: A total of 78 spaces can be accommodated off-street, including 9 MUNI/SamTrans spaces; 82 platforms needed; four spaces on street | finding | City report: Transit terminal study scanned page ↗ |
| 1993 | Alternative 3 (Alternative X) Transbay Terminal · other: MUNI and SamTrans continue to use existing loading areas in front of terminal building | alternative | City report: Transit terminal study scanned page ↗ |
| 1993 | Alternative 1 - Expand the Existing Terminal Building To Mission Street · alternative: Expand the existing Transbay Terminal Building to Mission Street for long-haul bus services | alternative | City report: Transit terminal study scanned page ↗ |
| 1993 | Transbay Terminal Building · other: Increase bus loading platforms in existing building from 39 to 53 | building | City report: Transit terminal study scanned page ↗ |
| 1993 | Transbay Terminal expanded area · other: Additional 16 platforms can be provided in the expanded area | building | City report: Transit terminal study scanned page ↗ |
| 1993 | Transbay Terminal expanded terminal · other: Expanded terminal will be 6-8 feet higher than the existing bus deck | building | City report: Transit terminal study scanned page ↗ |
| 1993 | Alternative 1 - Expand the Existing Terminal Building To Mission Street · finding: Total clearance need is at least 28 feet; elevation difference between bus deck and street level is only 20 feet | finding | City report: Transit terminal study scanned page ↗ |
| 1998 | MUNI bus route 108 special service · event: Special bus service from Transbay Terminal to Treasure Island, 9:30 AM departure | action | City report: Treasure Island and Yerba Buena Island scanned page ↗ |
| 1995 | Alternative X · alternative: Modified existing Terminal building by adding a second bus deck; rail needs accommodated underground | alternative | City report: Transbay area plan : background data report scanned page ↗ |
All 12 records, with filters · this place's data as JSON · release v0.7.1 · CC0 1.0