Union Square Station
Named in the records1998–2012
15 records of San Francisco tie this place, 1998–2012: 1 decision of the Board of Supervisors and 14 facts read from city reports. Open the full list, with filters for years, kind and outcome.
- Kind
- Named in the records
- Records
- 15: 1 Board decision, 14 facts from city reports
- Years
- 1998–2012
What the records say
All 15 records, in date order. The one-line summaries were written by a language model from the printed page; open the page to check the wording.
| When | What the record says | Outcome | Source |
|---|---|---|---|
| 1998 | Optional bypass subway tunnel · other: Optional subway on west side of Stockton would bypass Union Square station centered on Post Street | alternative | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | New Central Subway, Union Square station · proposes: underground station with two platform levels and a mezzanine, centered on Post | alternative | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | Union Square station · proposes: Station constructed simultaneously with subway on Geary Street | project | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | New Central Subway construction at Union Square station · other: Stockton Street between Sutter and Geary may be closed to traffic for six to eight months | action | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | Stockton Street bus diversion during Union Square station construction · alternative: diesel shuttle buses along Powell, Market, Third and Fourth Streets | alternative | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | New Central Subway Union Square station excavation · other: Stockton Street between Sutter and Geary Streets may need full closure to traffic for six to eight months | action | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | Union Square station · proposes: two sets of stairs, one escalator, and one elevator on east side of Stockton Street; one escalator on west side | project | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | Union Square station · finding: pedestrian overcrowding would occur during peak conditions | finding | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | Union Square station optional subway bypass · other: fifty additional parking spaces displaced if bypass constructed | property_record | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | Union Square station · other: Pedestrian connection to Union Square garage elevators displaces two or three parking spaces | alternative | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | Third Street Light Rail Project · other: Subway continues in mined tunnel under Stockton north of Union Square station | alternative | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | Union Square station entrances · other: Surface disruption at station entrances at Stockton and Clay; existing curb parking displaced | action | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | Union Square station · recommendation: consider widening Stockton Street sidewalks near the station and/or using narrower stairways and escalators | recommendation | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 1998 | Union Square station · other: Sidewalk on eastern edge of the Square closed for several months during excavation | action | City report: Draft environmental impact statement/draft environmental impact report for the Third Street light rail project in the City and County of San Francisco scanned page ↗ |
| 2012-10-23 | Surface and subsurface structures in Union Square Park for the Central Subway's Union Square station approved. | passed | Board decision scanned page ↗ |
All 15 records, with filters · this place's data as JSON · release v0.7.1 · CC0 1.0