San Francisco water & power (1985)

San Francisco water & power : a history of the Municipal Water Department and Hetch Hetchy System

A history by the San Francisco Public Utilities Commission of the city's water department and the Hetch Hetchy system, from early supply to its later expansion.In August 1987 the Board adopted a resolution opposing the Interior Secretary's proposal to dismantle the Hetch Hetchy Water System. Scan on the Internet Archive ↗

Cost
$45 million bond issueScan 2 ↗
Dam height
226.6 feetScan 1 ↗
Pipeline
1,191 miles of pipelineScan 20 ↗
Initial cost
just over $100 millionScan 37 ↗
Report recommendations
  • A Board of Army Engineers report recommends San Francisco develop Hetch Hetchy.Scan 1 ↗
Findings
  • Grunsky's investigation established the superiority of the Tuolumne River system, later called Hetch Hetchy.Scan 22 ↗
  • The total initial cost of Hetch Hetchy development was just over $100 million (≈ $2.5 billion in 2026 dollars), met solely by the City.Scan 37 ↗
Board decisions
  • 1985 · This reportSan Francisco Public Utilities Commission
  • An ordinance establishing a Hetch Hetchy Water and Power Project Stores Fund and repealing older store-fund sections was finally passed.Record · Journal page ↗
  • Board adopted a resolution opposing the Interior Secretary's proposal to dismantle the Hetch Hetchy Water System.Record · Journal page ↗
  • Ordinance appropriating $10,716,761 (≈ $25.7 million in 2026 dollars) for Hetch Hetchy Water and Power capital projects was finally passed.Record · Journal page ↗
31 quotes from the scan

Printed words Quoted from the page as read from the scan.

Board decision citedPrinted words, misread in placess-655467ff10b5

“Board of Supervisors adopts resolution #6949 formally abandoning the Hetch Hetchy development”

Scan 2

Backgrounds-81777e517714

“The Hetch Hetchy System had its birth in the Raker Act of 1913 which granted water resource rights-of-way on the Tuolumne River in Yosemite National Park to San Francisco.”

Scan 7

Findings-c16e26d6fc95

“Mayor “Sunny Jim” Rolph purchased the fully developed, mature water works for San Francisco ata cost of $39,962,606.51 on March 3, 1930.”

Scan 7

Findings-d60ab552c6b5

“A very busy 20 years of construction on the Hetch Hetchy dams and aqueducts resulted in Sierra Nevada water being delivered into the Water Department local distribution system by 1934.”

Scan 7

Findings-08f66db30728

“Within the two years, 1850-1852, San Francisco was entirely destroyed by fire six times, with staggering losses of property, and was as often rebuilt.”

Scan 10

Backgrounds-16f317ad67b1

“In 1856, the San Francisco City Water Works, popularly known as the Bensley Company, was franchised by San Francisco Order No. 46.”

Scan 10

Findings-5346b3cd478a

“By 1859, the City was solidly built of brick and stone with nearly 100,000 inhabitants having all the accomplishments of wealth and culture.”

Scan 10

Findings-a8061da851bc

“The Pueblo of Yerba Buena, a town government organized by 450 residents, was taken by the U.S.S. Portsmouth, commanded by Captain R.B. Montgomery, on July 9, 1846.”

Scan 10

Backgrounds-d6b9e634e25f

“George H. Ensign obtained a water charter from the California Legislature in 1858 and organized the Spring Valley Water Works.”

Scan 11

Findings-8a1c7c544f92

“San Andrés Reservoir entered water operations for San Francisco in November 1870.”

Scan 14

Findings-9e0ab722c932

“The American Society of Civil Engineers designated Crystal Springs Dam as a California Historic Civil Engineering landmark in 1976.”

Scan 17

Findings-41e105cf8a1d

“Turner Dam is a compacted earth-fill structure 195 feet high, 2,160 feet long and 1,075 feet wide at the base.”

Scan 20

Findings-7f9abce7287b

“San Francisco’s twelve municipal reservoirs can hold, at capacity, some 414 million gallons (1,271 acre feet), about a five-day supply for the City.”

Scan 20

Backgrounds-050a74baaac2

“The Park was created by Congress on October 1, 1890, but at the time it did not include Yosemite Valley and Mariposa Grove.”

Scan 23

Backgrounds-6ff23ead1fb6

“Pay an annual rental starting at $15,000 and rising to $30,000 after 20 years.”

Scan 32

Findings-308b89cdbb41

“At its dedication on July 7, 1923, it was acclaimed the largest single structure of the West Coast.”

Scan 37

Findings-72f5a80806d2

“The cost was met solely by the City — without State or Federal assistance.”

Scan 37

Backgrounds-25607d6b0ba1

“When the budget was finally adopted in 1927, tunnel drilling started without delay.”

Scan 41

Findings-43067a709974

“The line cost $12.3 million and increased the aqueduct capacity by 80 million gallons to 140 million gallons per day.”

Scan 41

Findings-6ed78fcf82ab

“330 feet high above bedrock, 2,600 feet long, and 1,320 feet thick at the base.”

Scan 46

Findings-9b6bcc26db2e

“Transbay Construction Company made the low bid of $3,219,965 and construction started in January 1935.”

Scan 46

Backgrounds-e04a8e4fab79

“San Francisco had approved a $3.5 million bond issue for this project in November 1933.”

Scan 46

Findings-1664f7961df1

“The Moccasin-Newark line operates at 115 kV for its 98.5-mile length.”

Scan 47

Findings-8647d2500f66

“In 1984, these sales produced over $70 million in gross revenues and $42 million for the General Fund and San Francisco taxpayer relief.”

Scan 47

Findings-9d50752f168b

“Holm Powerhouse came on line in 1960, and is the largest of the three Hetch Hetchy powerhouses.”

Scan 47

Identifier ia:C124889945