Staff report, Port of San Francisco, May 13, 1987

Staff report, Port of San Francisco, May 13, 1987 : summary of findings and recommendation for further study : commercial fishing facilities at Fisherman's Wharf

A staff report by the Port of San Francisco on commercial fishing facilities at Fisherman's Wharf, with findings and a recommendation for further study. Scan on the Internet Archive ↗

Phase I cost
$27 and $35 millionScan 12 ↗
Phase II cost
$18 and $39 millionScan 14 ↗
Pier removal cost
$258,990 per acreScan 18 ↗

“[name withheld]” stands for a name the release withholds (Privacy).

Report recommendations
  • The report recommends the second course, placing some commercial fishing infrastructure on Pier 45.Scan 18 ↗
  • The staff recommends that the Port Commission authorize the conceptual design team to study three alternatives for commercial fishing facilities within the Pier 45 development.Scan 20 ↗
  • The analysis recommends that Phase II reserve an area for GGNRA to berth and interpret its vessels.Scan 12 ↗
Board decisions
  • Support for state study of fish research center at Pier 45.Record · Journal page ↗
  • 1987 · This reportPort of San Francisco
  • Port of San Francisco may apply for a $4.8 million (≈ $10.9 million in 2026 dollars) state loan to help build the Fisherman's Wharf fishing harbor; referred to Budget Committee.Record · Journal page ↗
  • Port authorized to accept an additional $1.8 million (≈ $4.1 million in 2026 dollars) state loan, totaling $4.8 million (≈ $10.9 million in 2026 dollars), for Fisherman's Wharf fishing harbor.Record · Journal page ↗
  • Lease of Pier 47 at Fisherman's Wharf for fish processing and sport fishing assigned to United Shellfish Company; finally passed.Record · Journal page ↗
  • H&N Fish Company to get a ten-year lease at Pier 45Record · Journal page ↗
  • Commemorative resolution marks the reopening of the Pier 45 Commercial Fishing Center.Record · Journal page ↗
3 more Board decisions after the report
  • Controller's $477,000 (≈ $1.0 million in 2026 dollars) Port appropriation relocates tenants from Pier 46; referred to Finance Committee for consideration May 21, 1997.Record · Journal page ↗
  • A $3.5 million (≈ $7.3 million in 2026 dollars) loan appropriation for the Hyde Street fishing harbor design and construction was referred to the Finance Committee.Record · Journal page ↗
  • $3.5M (≈ $7.3 million in 2026 dollars) for the Hyde Street fishing harbor sent to committeeRecord · Journal page ↗
16 quotes from the scan

Printed words Quoted from the page as read from the scan.

Findings-1a0cce7ad770

“This agreement resolved funding and siting issues and was a catalyst to planning the full fisheries development. The breakwater was completed in October 1986.”

Scan 2

Backgrounds-49e31f3cc5c0

“Prior to the Port's amendment to the Action Plan, the US Army Corps of Engineers and Port Commission gave final approval to a plan for a free standing protective breakwater.”

Scan 2

Backgrounds-f31e922564f3

“In 1985 the Port Commission amended the Action Plan to include this recommendation.”

Scan 2

Findings-6523c7016a78

“As will be described below, issues identified during the initial phase of the project prevented the reduction of alternatives to two as originally anticipated. The design work now stands in an extended Phase II.”

Scan 4

Report recommendations-59f1a8119e86

“A series of alternatives were developed in response to accommodating the infrastructure program for both berthing and fish handling at Hyde Street.”

Scan 8

Findings-24d7316449ff

“Complete reconstruction of Fish Alley (Scheme B) did not appear to result in a more acceptable design either in terms of disruption to existing businesses, cost, or vehicle and vessel access.”

Scan 12

Findings-337c14c3c83f

“The development cost estimates during Phase I ranged between $27 and $35 million.”

Scan 12

Findings-6a1d09801358

“From an operational standpoint, Scheme E incorporates the most desirable features. However, the issue of building height versus the needs of the industry remains unresolved.”

Scan 14

Findings-b27c1d2ca16f

“Scheme F, depicting a minimum area of new pier construction jeopardizes vehicular operations sufficiently to make it unacceptable.”

Scan 14

Findings-bae707c62b89

“Appendix B contains a summary of estimated costs for each of the Phase II alternatives. They range between $18 and $39 million.”

Scan 14

Report recommendations-31d3680db78e

“The second course is recommended. This will entail studying three alternative schemes for placing commercial fishing infrastructure on Pier 45.”

Scan 18

Report recommendations-11b145842fde

“The results of this analysis, including physical and financial feasiblity will be reported to the Port Commission by June 15, 1987.”

Scan 20

Report recommendations-b16ddf084d7a

“It is the staff's recommendation that the Port Commission authorize the conceptual design team to study three alternatives for including commercial fishing industry facilities within the Pier 45 development.”

Scan 20

Findings-db36c569c787

“Chance of Approval: Fair (exclusive commercial use is a problem). Contact: [name withheld] (916) 322-1800.”