Findings-1a0cce7ad770
“This agreement resolved funding and siting issues and was a catalyst to planning the full fisheries development. The breakwater was completed in October 1986.”
Scan 2Records › City reports › Staff report, Port of San Francisco, May 13, 1987
Staff report, Port of San Francisco, May 13, 1987 : summary of findings and recommendation for further study : commercial fishing facilities at Fisherman's Wharf
A staff report by the Port of San Francisco on commercial fishing facilities at Fisherman's Wharf, with findings and a recommendation for further study. Scan on the Internet Archive ↗
“[name withheld]” stands for a name the release withholds (Privacy).
Printed words Quoted from the page as read from the scan.
Findings-1a0cce7ad770
“This agreement resolved funding and siting issues and was a catalyst to planning the full fisheries development. The breakwater was completed in October 1986.”
Scan 2Backgrounds-49e31f3cc5c0
“Prior to the Port's amendment to the Action Plan, the US Army Corps of Engineers and Port Commission gave final approval to a plan for a free standing protective breakwater.”
Scan 2
Scan 2Backgrounds-f31e922564f3
“In 1985 the Port Commission amended the Action Plan to include this recommendation.”
Scan 2Findings-6523c7016a78
“As will be described below, issues identified during the initial phase of the project prevented the reduction of alternatives to two as originally anticipated. The design work now stands in an extended Phase II.”
Scan 4Report recommendations-59f1a8119e86
“A series of alternatives were developed in response to accommodating the infrastructure program for both berthing and fish handling at Hyde Street.”
Scan 8Findings-24d7316449ff
“Complete reconstruction of Fish Alley (Scheme B) did not appear to result in a more acceptable design either in terms of disruption to existing businesses, cost, or vehicle and vessel access.”
Scan 12Findings-337c14c3c83f
“The development cost estimates during Phase I ranged between $27 and $35 million.”
Scan 12Findings-6a1d09801358
“From an operational standpoint, Scheme E incorporates the most desirable features. However, the issue of building height versus the needs of the industry remains unresolved.”
Scan 14Findings-b27c1d2ca16f
“Scheme F, depicting a minimum area of new pier construction jeopardizes vehicular operations sufficiently to make it unacceptable.”
Scan 14Findings-bae707c62b89
“Appendix B contains a summary of estimated costs for each of the Phase II alternatives. They range between $18 and $39 million.”
Scan 14Report recommendations-31d3680db78e
“The second course is recommended. This will entail studying three alternative schemes for placing commercial fishing infrastructure on Pier 45.”
Scan 18
Scan 18Report recommendations-11b145842fde
“The results of this analysis, including physical and financial feasiblity will be reported to the Port Commission by June 15, 1987.”
Scan 20Report recommendations-b16ddf084d7a
“It is the staff's recommendation that the Port Commission authorize the conceptual design team to study three alternatives for including commercial fishing industry facilities within the Pier 45 development.”
Scan 20Findings-db36c569c787
“Chance of Approval: Fair (exclusive commercial use is a problem). Contact: [name withheld] (916) 322-1800.”
Scan 72Identifier ia:C124891468